HomeMy WebLinkAboutCapital Improvement Program Budget FY 2018-2023    Otay Water District Capital Improvement Program Budget Fiscal Year 2018-2023 BOARD OF DIRECTORS Mark Robak, Division 5 President Tim Smith, Division 1 Vice President Mitch Thompson, Division 2 Treasurer Gary Croucher, Division 3  Hector Gastelum, Division 4 MANAGEMENT TEAM Mark Watton General Manager Joseph R. Beachem Chief Financial Officer Adolfo Segura Chief, Administrative Services Pedro Porras Chief, Water Operations Jose Martinez Assistant Chief, Water Operations Rod Posada Chief, Engineering Table of Contents Page Letter of Transmittal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii Awards. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xi Resolution No. 4336 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xv OVERVIEW CIP Budget Guide . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Mission Statement, Vision, Key Challenge, Statement of Values. . . . . . . . . . . . . . . . . . . . 2 District Formation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 Service Area . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 Organizational Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 Budget Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 Budget Basis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 Fund Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 CIP Budget Calendar . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 Demographics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 Service Area Assessed Valuation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 Ten Principal Taxpayers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 Ten Largest Customers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 Water Rate Comparison – Member Agency Water Rates. . . . . . . . . . . . . . . . . . . . . . . . . . 12 Sewer Rate Comparison. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 San Diego Rainfall. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 Current Economic Conditions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 Economic Outlook. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 The Future . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 Strategic Plan Balanced Scorecard. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19 Administrative Services . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 Finance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23 Water Operations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 Engineering . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 CAPITAL BUDGET Capital Budget Narrative. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35 CIP Reserve Funds ($1,000s) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37 Six-Year CIP Projects Summary by Source ($1,000s). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38 Six-Year CIP Projects Summary by Fund ($1,000s) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38 Six-Year CIP Projects by Source and Fund ($1,000s) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39 Six-Year CIP Projects Schedule. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43 CIP Justification and Impact on Operating Budget. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47 i Table of Contents CIP PROJECTS CIP Project Sheet Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49 CIP Project Index . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51 CIP Projects. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55 APPENDIX Annual CIP Development Policy No. 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 261 Water Meter Capacity Fees . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 262 Glossary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 263 List of Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 266 Index . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 275 ii September 30, 2017 Honorable Board of Directors Otay Water District I am pleased to present the Otay Water District’s Adopted Operating and Capital Budget for FY 2018. The budget supports the District’s updated FY 2015-2018 Strategic Plan as well as the financing of all of the District’s services, programs, and capital needs during FY 2018. The success as an organization is significantly enhanced by the policies and practices put in place by its Board to ensure the strength, stability, and reliability of the District. The management team is fully confident that with these policies, practices, and sound financial management, supported by the FY 2015-2018 Strategic Plan, along with a committed and talented staff, the District will achieve continued success as an organization and thus, ensure the well-being and quality of life its customers. Drought Conditions and California State Mandates According to the United States Geological Survey, the State of California has been in a drought for more than five years. Fortunately, in 2017, California experienced above-average precipitation and snowpack. The majority of reservoirs are above historic average levels and most rivers, creeks, and lakes have been reported to be in good condition. On April 7, 2017, Governor Jerry Brown issued an executive order officially ending the drought state of emergency in most of California. The Governor also released the state’s long-term plan to better prepare the state for future droughts and make conservation a way of life in California. On April 26, 2017, the State Water Resources Control Board (SWRCB) rescinded the conservation mandates but continued the water-use reporting requirements and prohibitions against wasteful practices. As part of the Governor’s mandate, the SWRCB adopted Resolution No. 2016-0029, which allowed individual suppliers to self-certify that there would be no supply shortfall assuming three additional dry years. With the certification of the Claude “Bud” Lewis Carlsbad Desalination Plant, additional water storage capacity, and upgraded conveyance systems, the San Diego region’s water agencies have the ability iii to provide sufficient water supplies to meet customer demands, assuring there would be no supply shortfall during three additional dry years. In addition to meeting customer demands during a drought, the District has consistently advocated for state policies and legislation that include supply development and water-use efficiency. The District continues to work closely with the San Diego County Water Authority (CWA), the Association of California Water Agencies, and other water agencies in the region to ensure that the targets and measures in the Governor’s long-term framework support a balanced approach and reflect local water supply investments and conditions. The District continues its efforts to diversify water resources, reducing dependence on traditional water supplies from the Colorado River and the Sacramento-San Joaquin Delta. The District has reached a milestone by obtaining a Presidential Permit, allowing the District to build a nearly four-mile long potable water pipeline that begins at the U.S. Mexico border. The District could potentially begin receiving up to two thirds of its projected water needs from the Rosarito Desalination plant as early as 2024. Although there are additional hurdles to overcome, desalinated water from Rosarito would be a closer option and a drought resistant source of water. With the conservation mandates ending in FY 2017, potable sales volumes increased 7% from FY 2016 levels. Regardless of the end of the drought emergency and the District meeting the state’s mandated conservation targets, the District’s customers were still seeing and hearing public campaigns promoting conservation and drought-related messages throughout the county from the CWA, the state, and the Metropolitan Water District (MWD). Homeowners and businesses have also implemented conservation measures that are expected to generate permanent reductions in water use. As a result, the District expects sales volumes to recover 3% due to continued conservation efforts in FY 2018, but remain 12% below 2015 levels. Additional remaining increases in sales volumes are expected to come from new customers. Staff will continue to monitor these trends as they influence overall District finances. FY 2015 - 2018 Strategic Plan The FY 2015-2018 Strategic Plan consisted of a two-phased approach. Phase 1 has been completed with the primary focus on developing key enterprise-wide projects – SCADA, Work Order/Asset Management, and Emergency Preparedness/NIMS. The District is now entering Phase 2 of the FY 2015-2018 Strategic Plan, where the focus is to build upon the system foundation, business process improvement, and facilities. Where rapid growth had iv been a significant focus in the early years of the District and in its earlier strategic plans, today it is primarily focused on managing long-term maintenance and replacement of infrastructure. This change is based on the recognition that as an organization matures, fewer resources are needed to support growth, but greater effort is required to maintain and upgrade infrastructure and assets. This is important because in this phase of the lifecycle, an organization derives income more from customer rates and less from developer fees. Therefore, the increased maintenance and replacement costs place increased pressure on customer rates. To balance the customer’s interest in minimizing rate increases, while also maintaining an organization’s infrastructure, investments, and a strong financial position, the management team must place greater emphasis on internal efficiency and the development of technology assisted best practices. In effect, the organization must use investments in technology to do more with the same or fewer resources. From a water supply perspective, this means determining the optimum mix of water supply, treatment, and delivery solutions for customers. From a daily operating perspective, efficiency improvements have become the primary source of competitive advantage and cost optimization for utilities. Since its establishment, the District’s motto has been “Dedicated to Community Service”. From modest beginnings in 1956 through today, the District remains dedicated to providing outstanding service to the residents and businesses the District has the honor to serve. This serves as a great reminder as to why the District exists. Finding ways to streamline operations and cut costs is a significant element of the District’s ongoing commitment to its customers. By reducing costs those savings can be passed to the ratepayers. For example, the District is currently upgrading more than 8,000 of its approximately 49,000 automated meter reading (AMR) meters, from 3G to 4G technology, allowing more meters to be read at a faster pace. In an effort to be as cost efficient as possible, the District has decided, in most cases, to replace the meter register instead of the entire meter, avoiding over $700,000 in meter replacement costs. Because of the life expectancy and warranty of the meters, the District is able to delay the replacement of the meters approximately 10 more years. There were many benefits to upgrading to AMR meters, including the reduction of full-time meter reader staff members from nine to three, increased safety of staff members, reduction of the District’s liability, and allowing staff to store historical water use data. These advanced meters can assist customers with unexplained usage by providing leak, tamper, and backflow detection alarms. The efforts v related to meter technology is only one example of cost savings and the District’s ongoing commitment to pursue cost efficiencies. Investing in technology is another strategy the District uses to increase and enhance efficiency and productivity. An ongoing goal included in the District’s past and current strategic plans is to capitalize on these technology investments. The success of this approach is proven by the District’s gains in productivity and reduction in staffing. The following charts show that since 2007, the District has reduced staffing by 40.75 full-time equivalent positions, or 23%, while the number of customer accounts increased by 2,542. Employee Count and Number of Accounts Because of increased efficiency and higher employee productivity, the District has been able to continue absorbing some of the pass-through costs from its water suppliers, including the City of San Diego, CWA, and MWD. This helps to address customer concerns about rising water rates. Other cost savings include reducing the number of vehicles and equipment, reducing fuel consumption, and decreasing water loss through the successful leak detection and repair program. Staff continues to seek out other operational efficiencies, thus reducing costs and minimizing rate impacts on the customers. Based on an annual survey of water and sewer rates conducted by staff, Otay continues to be one of the lower cost providers in San Diego County. The District has the third lowest water rate out of the 22 member agencies in San Diego County and the sixth lowest sewer 17 4 . 7 5 17 2 . 7 5 16 8 . 7 5 16 6 15 9 15 6 14 8 14 3 14 0 13 8 13 5 13 4 52,615 55,157 51,500 52,000 52,500 53,000 53,500 54,000 54,500 55,000 55,500 0 20 40 60 80 100 120 140 160 180 200 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Em p l o y e e  Co u n t Fiscal Year vi rate out of the 28 sewer service providers in the County. The results of the water and sewer surveys are shown on pages 12 and 13, respectively. The following chart shows that since 2007, the wholesale water supply costs have increased 106.7% while the District’s retail water rates have increased a lesser 93.2%. Wholesale Water Supply Costs vs. District Retail Rate Increases The District currently delivers water service to 49,761 potable and 719 recycled water customer accounts. The District purchases all of the potable water sold to customers from the CWA. Forty-seven percent of this water, in turn is purchased from the region’s primary water importer, MWD. This number has decreased significantly compared to previous years due to conservation efforts, the water transfer with Imperial Irrigation District (IID), and seawater desalination. The District has been proactive in reducing its dependence on MWD water treatment facilities. For example, in 2009 the District entered into an agreement with the CWA that allowed the neighboring Helix Water District to treat imported water on behalf of the District at Helix’s Levy Water Treatment Plant. This has brought regional water treatment closer to District customers, which reduces dependence on water treatment facilities located outside of the County. The District also collects and recycles wastewater from approximately 4,669 homes and businesses. The District collects wastewater and delivers it to its Ralph W. Chapman Water 0% 20% 40% 60% 80% 100% 120% 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 106.7% 93.2% CWA Water Cost Increase Otay Water Rate Increase vii Recycling Facility, which is capable of recycling wastewater at a rate of 1.3 million gallons per day. In addition to the Chapman facility, the District continues purchasing up to 6 million gallons per day of recycled water from the City of San Diego’s South Bay Water Reclamation Plant. The use of recycled water for landscape irrigation and industrial processes reduces dependence on imported potable supplies, provides a local supply that is drought proof, and diversifies District sources. Water Cost of Service Study During FY 2017, the District contracted with HDR Engineering, Inc., to perform a cost of service study for potable and recycled water customers. The study recommended changes to the District’s rate structure and the Board directed staff to implement the changes in the FY 2018 budget. The FY 2018 rates include the following proposed changes to the rate structure:  The FY 2017 conservation tier for residential customers has been eliminated, reducing the number of residential tiers from four tiers to three tiers.  The FY 2017 system fee structure was based solely on meter size. The FY 2018 structure bases the fee on both customer type and meter size.  The Irrigation, Commercial, and Public customer’s variable rate structures have been changed from a tiered rate structure to a unitary or flat rate structure. Fiscal Year 2018 Operating Budget Summary The District’s operating expenditures consist of three major sectors: potable water, recycled water, and sewer, which include a total budget of $98,248,200 for FY 2018. Revenues from potable and recycled water are projected to be $86,899,400, approximately $5,760,500 more than the FY 2017 budget. District staff expects water sales volumes to increase by 3.1% compared to FY 2017 budgeted sales. The District projects sewer revenues to be $2,869,400, approximately $49,500 less than FY 2017. The remaining budgeted revenues of $8.4 million come from various special fees, assessments, and miscellaneous income. Other significant aspects of the Operating Budget are:  A balanced budget supporting the goals of the Strategic Plan.  The use of an economist to project growth for the region.  An updated six-year Rate Model to ensure sound financial planning and reserve levels. viii  Ongoing water supply rate increases of 3.9% from MWD and CWA due to the high cost of supply programs, higher energy costs, and increasing operating costs.  No water rate increase budgeted for January 1, 2018 and a 7.5% rate increase for sewer, effective January 1, 2018.  Metro sewer costs includes the minimal impact of the City of San Diego’s Pure Water Program costs.  Reduction in staffing levels from 135 full-time equivalent positions last year to 134 this year, minimizing impacts on rate increases.  District maintains lowest water rates, below the countywide average of the County’s 22 water agencies. Six-Year Capital Improvement Program (CIP) The CIP budget emphasizes long-term planning for ongoing programs to meet population growth, while functioning within fiscal constraints. The FY 2018-2023 CIP Budget contains 103 projects and totals $102.3 million. The District anticipates borrowing $5.5 million from the Clean Water State Revolving Fund for the Campo Road Sewer Replacement project (S2024). The debt will include a 30-year maturity, with an estimated interest cost of 1.7%. The FY 2018 budget contains 87 projects and totals $20.0 million. Of the 87 projects planned for FY 2018, two are designated as reimbursable projects with an estimated cost totaling $45,000 (P2430 and R2084). These projects are built by developers and reimbursed by the District. This year’s CIP budget increased by $12.5 million compared to last year’s projection, primarily due to the addition of the meter replacement project (P2604). The following shows how the $20.0 million of projects are broken down into four categories: Expansion projects $ .2 million Betterment projects $ 2.7 million Replacement projects $ 17.1 million New Supply projects $ .01 million Awards and Acknowledgments  The Government Finance Officers Association of the United States and Canada (GFOA) presented Otay Water District the Distinguished Budget Presentation Award for its annual budget for the fiscal year beginning July 1, 2016. In order to receive this award, a governmental unit must publish a budget document that meets program ix criteria as a policy document, as an operations guide, as a financial plan, and as a communications device. Awards and Acknowledgments (continued)  The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Certificate of Award for Excellence in Operating Budgeting for Fiscal Year 2016-2017.  The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Certificate of Award for Excellence in Capital Budgeting for Fiscal Year 2016-2017.  The Government Finance Officers Association Officers (GFOA) presented Otay Water District the Certificate of Excellence in Financial Reporting for its Comprehensive Annual Financial Report for the Fiscal Year ended June 30, 2016. Conclusion The challenges presented this year were met by the District’s Board of Directors’ resolve to keep the stability and financial strength of the District as one of its highest priorities. This budget reflects the vision of the District’s Board, its management, and its employees. The District will continue to strive to make improvements in the budget processes, including an extensive review and analysis of projections for revenues, expenditures, capital projects, and reserves. I would like to thank the staff involved in this process for the efforts put forth in the preparation of this budget to ensure a successful outcome. To the Board, we acknowledge and appreciate their continued support and direction in achieving excellence in the financial management and operations of the District. Mark Watton, General Manager x Distinguished Budget Presentation Award The Government Finance Officers Association (GFOA) presented a Distinguished Budget Presentation Award to the District for its annual budget for the fiscal year 2016- 2017. In order to receive this award, a governmental unit must publish a budget document that meets program criteria as a policy document, as an operations guide, as a financial plan, and as a communications device. This award is valid for a period of one year only. We believe our current budget continues to conform to program requirements, and we are submitting it to GFOA to determine its eligibility for another award. xi Financial Awards The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Operating Budget Excellence Award for Fiscal Year 2016-2017. The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Capital Budgeting Excellence Award for Fiscal Year 2016-2017. xii Financial Awards The Government Finance Officers Association Officers (GFOA) presented Otay Water District the Certificate of Achievement for Excellence in Financial Reporting for its Comprehensive Annual Financial Report for the Fiscal Year Ended June 30, 2016. xiii Award The Construction Management Association of America (CMAA) presented the Otay Water District with the 2017 Distinguished Owner Honoree Award. xiv RESOLUTION NO. 4336 A RESOLUTION OF THE BOARD OF DIRECTORS OF OTAY WATER DISTRICT ADOPTING THE FISCAL YEAR 2017-2018 OPERATING AND CAPITAL BUDGET; AND SALARY SCHEDULE WHEREAS, the Otay Water District Board of Directors have been presented with a budget (Exhibit A) for the operation of the Otay Water District for Fiscal Year 2017-2018; and WHEREAS, the Fiscal Year 2017-2018 Operating and Capital Budget, has been reviewed and considered by the Board; WHEREAS, it is in the interest of the District to adopt a budget for said year; WHEREAS, in connection with the adoption of the budget, the Board is also being presented with the Salary Schedule (Exhibit B) for its consideration, in order to comply with California Code of Regulations Section 570.5, NOW, THEREFORE, BE IT RESOLVED, DETERMINED AND ORDERED by the Board of Directors of the Otay Water District that the Operating and Capital Budget for the operation of the District, incorporated herein by reference, is hereby adopted as the District's budget for Fiscal Year 2017-2018. BE IT FURTHER RESOLVED that the Board hereby approves and adopts the Salary Schedule included with the budget and, consistent with his authority over employee compensation under both State law and the District's Code of Ordinances, authorizes xv the General Manager to update the Salary Schedule whenever necessary to reflect changes made within his authority. PASSED, APPROVED AND ADOPTED by the Board of Directors of Otay Water District at a board meeting held this 24th day of May 2017, by the following vote: ATTEST: Ayes: Directors Gastelum, Robak and Smith Noes: None Abstain: Director Thompson Absent: Director Croucher President xvi Overview CIP Budget Guide The District views the Capital Improvement Program (CIP) Budget as an essential tool for proper financial management of the CIP projects. The District manages growth and maintenance of assets through this program. This CIP budget is developed with input from the various project managers throughout the organization and is adopted prior to the start of each fiscal year for the current fiscal year and five subsequent years. It is designed and presented for the general needs of the District, its staff, and citizens. It is a comprehensive and balanced financial plan. This plan features the CIP budget based on demands for services and the impact on the District’s financial status and future plans. The budget book is divided into the following sections. Overview This introductory section contains overall general information about the District such as: mission statement, vision, key challenge, statement of values, District formation, organizational chart, CIP budget process, CIP budget calendar, water and sewer comparison, economic outlook, and the District’s Strategic Plan. Capital Budget The Capital Budget section consists of an overview of the District’s CIPs, including how the Water Facilities Master Plan is used to modify the CIP each year based on the latest set of assumptions and criteria. Also included are highlights of the major CIP projects that are in planning, design, construction, or completed. Additionally, this section contains a review of the CIP reserve funds and funding sources, a six-year listing of CIP project expenditures, project justification, and impact on the Operating Budget, and the project schedules. CIP Projects This section contains the project sheet description and project sheets for each CIP project. These sheets are developed by the project manager and contain critical information for the management of these projects. The projects are divided into four categories: Expansion, Betterment, Replacement, and New Water Supply. Appendix The last section consists of the Water Meter Capacity Fee Schedule, a Glossary, List of Acronyms, and an Index. 1 Overview Mission Statement To provide high quality and reliable water and wastewater services to the customers of the Otay Water District, in a professional, effective, and efficient manner. Vision A District that is innovative in providing water services at competitive rates, with a reputation for outstanding customer service. Key Challenge Our key challenge, as District staff, is to quantify and demonstrate our commitment and ability to optimize our resources, business processes, and technology to achieve the Strategic Plan goals. We, as a team, commit to regularly assess and document how our decisions and work practices accomplish our goals and objectives. Statement of Values . We take pride that our commitment to customer-centered service is our highest priority. We strive to provide the highest quality and value in all that we do. We commit ourselves to doing the right thing. Ethical behavior, trustworthiness, and accountability are the District’s foundation. We see each individual as unique and important. We value diversity and open communication to promote fairness, dignity and respect. We promote mutual trust by sharing information, knowledge and ideas to reach our common goals. 2 Overview District Formation The Otay Water District was formed in 1956 by a small group of ranchers, farmers, and other property owners concerned about the declining quality and quantity of well water. The District was established to serve as a public water and sewer agency, authorized as a California special district under the provisions of the Municipal Water District Act of 1911. In 1957, developers in south Spring Valley created the La Presa County Water District to obtain water from the San Diego County Water Authority (CWA). The CWA is the water wholesale supplier of the member agencies in San Diego County. In the fall of 1969, Otay Water District and La Presa County Water District merged into the Otay Water District. Since then, the District has provided high quality water to a semi-arid region of southeastern San Diego County. In 1971 the District constructed a small collection and treatment plant for sewer in the northern section of the District, and in 1980 the District opened the Ralph W. Chapman Water Recycling Facility (RWCWRF). Recycled water from the RWCWRF is used to irrigate golf courses, schools, public parks, roadway landscapes, and various other approved uses in eastern Chula Vista. The RWCWRF is capable of recycling wastewater at a rate of 1.3 million gallons per day (1,200 acre-feet per year). The District is also in partnership with the City of San Diego to beneficially reuse an additional 2,661 acre-feet per year of recycled water for fiscal year 2018, and ultimately up to 6,720 acre-feet per year. The District continues to be the largest retail provider of recycled water in the County of San Diego. The District also owns and operates a wastewater collection system providing public sewer service to approximately 4,677 customer accounts within the Jamacha drainage basin. The sewer service area covers approximately 8,797 acres, which is about 11% of the District’s total service area. Residential customers comprise 97% of the sewer customer base. Service Area The District's boundaries encompass an area of approximately 125.5 square miles or 80,140 acres in San Diego County, lying immediately east of the City of San Diego metropolitan area and running from the City of El Cajon south to the international border, abutting the cities of El Cajon and La Mesa and encompassing most of the City of Chula Vista and a small portion of the City of San Diego. The District purchases 100% of its treated water. Of that, about 85% is imported, which is a blend from the Colorado River and the California State Water Project. Fifteen percent of the District’s treated water comes from local supplies, including local water storage within the county and from the Pacific Ocean via seawater desalination. The District purchases its treated water from the Metropolitan Water District of Southern California’s R.A. 3 Overview Skinner Treatment Plant, the San Diego County Water Authority’s Twin Oaks Valley Water Treatment Plant, the Carlsbad Desalination Plant, and the Helix Water District’s R.M. Levy Water Treatment Plant. Organizational Structure The District has a five-member Board of Directors that serve four-year, alternating terms on the Board. Each Director is elected by voters within their respective division boundaries to represent the public’s interest with regard to rates for service, taxes, policies, ordinances and other matters related to the management and operation of the District. The Board generally meets in open public session on the first Wednesday of each month at 3:30 p.m. at the District headquarters located at 2554 Sweetwater Springs Boulevard, Spring Valley, California. Citizens and Customers Board of Directors General Manager (6) Safety and Security Administration Purchasing and Facilities Controller and Budgetary Services Treasury and Accounting Services Customer Service Meter Maintenance Water System Operations Utility Maintenance/ Construction Water Resources, Planning, Design and Environmental Si Administrative Services (23) Human Resources Information Technology and Strategic Planning Finance (29) Geographic Information System Public Services and Field Services Engineering (24) Water Operations (52) 4 Overview Budget Process The District has integrated the Capital Improvement Program (CIP) Budget and the Operating Budget. These budgets are developed based on the District’s Water Resources Master Plan, the Sewer Master Plan, and Strategic Business Plan. New initiatives and programs are categorized into the Balanced Scorecard perspectives. Appropriate budget amounts are determined by using the historical data of operations and new growth, developers’ input, SANDAG projections, and economic outlook. To assure reliable and high-quality service to the growing customer base, the District has committed to a number of long-range strategies that drive the budgeting process. The strategies and assumptions used to develop the District’s integrated budget are:  An average projected long-term growth rate of 1.4%.  Pass-through rate increases for costs imposed on the District by the wholesale water providers.  Accurate projections of capital budget needs (including replacement needs).  Reserve funding in accordance with the Reserve Policy to meet future growth demands and maintain financial stability.  Funding of the Strategic Plan initiatives as categorized into the Balanced Scorecard perspectives.  Avoid rate spikes by leveling rate increases over a six-year period. The Finance Department prepares the budget for the potable, recycled, and sewer systems. This is done using estimated changes in costs from the District’s wholesale water providers as well as estimated changes in sewer charges provided by the County and City of San Diego. Other significant factors in the budget development include estimated conservation levels, projected growth in customer accounts, and weather. Additionally, all general revenue and expense budgets are calculated using trend analysis and any external factors that may affect these items. Personnel Budget The budgeting of salaries and benefits is performed in the position budgeting module of the Enterprise Resource Planning (ERP) system. This tool allows the District to budget for each authorized position and the associated benefits in an automated fashion. Departments submit requests for new positions, reclassifications, or advancements to the General Manager. Upon their approval, the Finance Department enters these changes, as well as negotiated pay increases and benefit rate changes, into the position budget system. Position budgeting calculates the salaries and benefits to be included in the District’s budget. 5 Overview Administrative and Materials and Maintenance Budget Administrative and Materials and Maintenance expenses are entered into the budget model of the ERP system by individual requests. These requests are compared to last year’s budgeted and actual expenses to determine reasonableness by the Finance Department. All costs are justified and supported by explanations. Finance compiles the operating budget and submits it to the General Manager for review prior to presentation to the Board of Directors. Capital Improvement Plan (CIP) Budget The Engineering Department issues budget instructions for the CIP budget process. Each project manager uses the CIP Budget module system to review year-to-date project expenses and then estimates costs to the end of the fiscal year. They also project future costs to complete the project. Costs are adjusted for scope changes as well as construction cost increases. Engineering then compiles the CIP Budget and submits it to the General Manager for review prior to presentation to the Board of Directors. The District has a three-year Strategic Plan, and each year in the spring, the portion of the plan that pertains to the upcoming fiscal year is presented to the Board of Directors for review and direction. This is followed by a coordinated presentation of the budget by all departments, to the Board of Directors for their approval at a special budget workshop in May. The review of the Strategic Plan and the adoption of the budget on an annual basis give the District its direction for the following fiscal year. Year‐end  Balances Operating  Budget Input 6‐Year Rate Model Strategic  Plan Operating  Budget  Water  &  Sewer  Rates Governor’s  Mandate CIP  Budget 6‐Year CIP  Budget Input  MWD/CWA & City   Sewer Rates Assumptions  Interest Rates  Inflation  Growth  Sales Targets  Debt Coverage  Reserve Levels  6 Overview During the year, each department receives monthly budget and cost reports that are essential to monitor and control costs. As events occur or conditions change, modifications to or deviations from the original budget may be necessary. In the event the General Manager determines that an emergency exists which requires immediate action; he may transfer appropriations within the budget allocations or request that the Board of Directors increase the current budgeted funds. Due to the size of the District’s CIP, a separate budget book has been prepared outlining in detail the projects and expenditures required to ultimate build-out. A synopsis of the CIP may be found under the Capital Budget section of this report. As part of the integrated budget, capital purchases have been included within the CIP Budget. The budget report is intended as a financial guide and may be modified by the Board of Directors during the fiscal year. All approved modifications to the budget will be documented in the form of a staff report and noted in the board meeting minutes. Budget Basis The District utilizes the accrual basis for budgeting which is the same as the basis of accounting used in the audited financial statements, recognizing revenues and expenses in the period in which they are earned and incurred, regardless of the timing of cash receipts and disbursements. The District reports its activities on an enterprise fund basis, which is used to account for operations that are financed and operated in a manner similar to a private business enterprise and conforms to the guidelines of Generally Accepted Accounting Principles (GAAP). The intent of the District is that the costs (including replacement cost of existing assets) of providing goods or services to the general public on a continuing basis, be financed or recovered primarily through user charges. 7 Overview Fund Structure The District budgets services in one of the three business segments: Potable, Sewer, or Recycled. Each business segment categorizes revenue and expenditure as a function of the Operating Budget, Capital Improvement Plan Budget, or Developer Deposits. Please refer to the District’s Reserve Policy, in the Operating and Capital Budget for FY 2017-2018, which provides the detailed flow of funds. Recycle   Sewer Sewer Operating Budget Sewer CIP Budget Sewer Developer Deposits Recycle Operating Budget Recycle Developer Deposits Recycle CIP Budget Potable Potable Operating Budget Potable CIP Budget Potable Developer Deposits 8 Overview CIP Budget Calendar Each year, the Engineering Department prepares budget instructions for distribution to the departments. These instructions give direction and deadlines for each phase of the CIP budgeting process. The CIP Budget Process is explained on page 5. January March April May-June July–January 1/11/17 Budget workbooks and instructions for the Operating and Capital Budget are distributed to departments 1/11/17 - 2/17/17 Departments begin CIP Budget Process which includes:  Review existing FY 2016 CIP Projects.  Remove any CIPs that are complete or will not be budgeted in the CIP budget the next six-years.  Estimate the total project-to-date expenditures through 6/30/16 for each CIP.  Adjust the annual amount for the remaining CIPs and include justifications for each year’s changes.  Develop CIP project cost and schedules  Submit new CIP projects to Engineering for consideration. 3/6/17 Finance Preliminary Review of CIP Budget FY 2018 3/13/17 Engineering reviews and prepares CIP budget and submits to finance for review and to incorporate into rate model to determine proposed rates 3/20/17 CIP budget presented to the General Manager for review and comments 3/29/17 Review CIP Updates 4/4/17 Engineering reviews CIP Budget with Finance and General Manager 4/20/17 General Manager performs preliminary review of budget. 5/4/17 Review assumptions and rates with Chiefs and General Manager 5/15/17 FY 18 Budget: Practice Run- through 05/24/17 Board Meeting/Budget Workshop – approval of the FY 2018-2023 Capital Improvement Program Budget and the FY 2017- 2018 Operating and Capital Budget 5/24/17 Board gave direction to staff to mail rate notices to customers 7/17/17-8/15/17 Rate increase message inserted with water and sewer billing 10/04/17 Proposition 218 Hearing on water rates 1/1/18 Water and Sewer Rate Increase 9 Overview Demographics The population of the Otay Water District has grown from 114,937 in 1980 to 223,754 in 2016. At that time the average persons per household was 3.46. For 2016, SANDAG reports the City of Chula Vista’s ethnic/racial makeup with 44.6% Hispanic, 8.5% non-Hispanic white, 17.2% Asian and the remaining population are of other ethnic/racial descent. In a recent economic forecast conducted by The London Group Realty Advisors, the District’s median age is 36 and 34.6% of adults have a four-year degree or higher. The average household income is $107,876 and the median household income is $89,837. Otay Water District Demographics Population 223,754 Persons/Household 3.46 Ethnic/Racial makeup Hispanic 44.6% Non-Hispanic White 8.5% Asian 17.2% Other 15.2% Median Age 36 Percentage with 4 year degree or higher 34.6% Average Household Income $ 107,876 Median Household Income $ 89,837 Source: SANDAG, The London Group Realty Advisors, Claritas Demographics Service Area Assessed Valuation The District’s service area encompasses property with over $27.6 billion of assessed valuation. Properties are assessed at 100% of their full value less exemption from taxation under the law and homeowner’s exemptions. The District receives its portion of the 1% property tax, according to Proposition 13 and AB8. With the very recent increases in the assessed valuation, the District will benefit by receiving its proportionate share of this increase. $0 $5 $10 $15 $20 $25 $30 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 Bi l l i o n s Source: County of San Diego, Property Tax Services 10 Overview Ten Principal Taxpayers as of June 30, 2017 Organization Assessed Percent Value to Total 1. JOHN HANCOCK LIFE INSURANCE CO U S A $ 143,985,157 0.550% 2. VILLA MARINA DEL LLC 115,380,000 0.440% 3. REGULO PLACE APARTMENTS INVESTORS LLC 105,233,043 0.400% 4. HOMEFED OTAY LAND II LLC 103,148,000 0.400% 5. BRISA ACQUISITIONS LLC 102,677,670 0.390% 6. VISTA PACIFIC VILLAS LP 93,349,400 0.360% 7. B R E-F M C A LLC 77,685,406 0.300% 8. OTAY-TIJUANA VENTURE LLC 71,865,268 0.280% 9. SP LAVIDA REAL LLC 69,142,541 0.270% 10. CAMDEN USA INC. 68,096,135 0.260% Total Top 10 Principal Taxpayers $ 50,562,620 3.650% Total Service Area Assessed Valuation $ 26,057,698,553 Ten Largest Customers – Fiscal Year 2017 Customer Customer Annual % of Water Name Type Revenues Sales 1. CITY OF CHULA VISTA Publicly Owned $ 3,620,279 4.3% 2. STATE OF CALIFORNIA Publicly Owned 101,7064 1.2% 3. EASTLAKE III COMMUNITY Commercial 750,769 0.9% 4. COUNTY OF SAN DIEGO Publicly Owned 637,974 0.8% 5. HOMEFED OTAY LAND II, LLC Commercial 598,046 0.7% 6. CHULA VISTA SCHOOL DISTRICT Publicly Owned 524,968 0.6% 7. EASTLAKE COUNTRY CLUB Commercial 442,514 0.5% 8. STEELE CANYON GOLF CLUB LLC Commercial 353,981 0.4% 9. SWEETWATER SCHOOL DISTRICT Publicly Owned 335,488 0.4% 10. WINDINGWALK MASTER ASSOCIATION Commercial 306,520 0.4% Total 10 Largest Customers $ 8,587,604 10.3% Total District Customers $ 83,724,411 Source: County of San Diego, Property Tax Services 11 The District strives to remain cost effective in its rate setting by controlling operating costs, yet passing through the full cost of supply. The District conducted a survey of the water rates of its neighboring water providers within San Diego County. The following chart shows that the District has the 3rd lowest water rates in San Diego County. Overview Projected water bill for FY 2018 Based on 12 Units of water Use and 3/4 inch meter size Water Rate Comparison, Member Agency Water Rates 123.09 122.47 118.43 108.02 104.26 101.28 91.46 90.92 89.19 87.84 86.98 84.54 84.00 82.09 81.46 80.61 80.71 77.08 76.71 76.49 71.92 65.66 $- $20 $40 $60 $80 $100 $120 Yuima Padre Dam *Ramona Valley Center Rainbow Fallbrook Escondido Vista Rincon Del Mar San Diego Helix Carlsbad *Poway Vallecitos Oceanside Olivenhain Sweetwater Santa Fe Otay Water District *San Dieguito *Lakeside* *At the time of the survey, August 2017, the member agency's FY 2018 rate was unavailable. The estimated increase is equal to the District's FY 2018 average rate increase. 12 Water consumption based sewer rate Flat sewer rate Otay Water District * At the time of the survey, August 2017, the agency's FY 2018 rate was unavailable. The estimated increase is equal to the District's FY 2018 average rate increase The District conducted a survey of the rates of the sewer providers within San Diego County. Sewer rates are billed at either a fixed or variable rate. The following chart shows the various sewer providers and the type of rate that is charged to the consumers. The District has among the lowest sewer rates in the County of San Diego. Overview Sewer Rate Comparison, San Diego County 102.11 80.03 76.88 76.54 73.03 71.99 70.67 67.08 64.02 59.54 59.25 55.97 53.76 52.48 51.58 51.20 49.90 49.49 49.49 48.99 48.75 45.33 39.45 38.99 32.08 30.52 28.64 27.81 $- $20 $40 $60 $80 $100 $120 Del Mar *Rainbow Encinitas *Fallbrook Olivenhain Padre Dam *Rancho Santa Fe *Ramona Oceanside Vista Buena *Solana Beach Valley Center - MG *San Diego, City Imperial Beach *El Cajon Escondido Chula Vista La Mesa *Poway Lemon Grove Coronado, City Otay Water District Vallecitos National City San Diego, County Leucadia Carlsbad Projected sewer bill for FY 2018 Based on 9.5 units of water use and 3/4 inch residential meter size. 13 Overview San Diego Rainfall San Diego received more than normal rainfall in FY 2017, the District anticipated that San Diego's rainfall will continue to maintain the average pattern and volume for FY 2018. The 10-year average of 9.16 inches for San Diego rainfall reflects the long-term drought conditions for our area. San Diego's rainfall average over 20 years is 9.05 inches; the 30-year average is 9.55 inches; and the 40- year average is 10.42 inches. San Diego rainfall, while a contributing factor, is not the controlling factor for our potable water supply shortage. The San Diego region imports 84.0% of its potable supply, so conditions elsewhere significantly affect the actual amount of water available to the District. In the event the amount of water supplied to the District is reduced, water sales revenues would decrease. Related water purchase expenses would also be reduced, mitigating the impact of the decrease in revenues. The amount of any supply reduction would dictate the magnitude of the District's response and type of reaction. The San Diego rainfall information shown in the chart below uses data from the San Diego Airport at Lindbergh Field and is provided by the Western Regional Climate Center. More information can be obtained from their website: http://www.wrcc.dri.edu. The Western Regional Climate Center’s website data, in turn, is derived from data received from the National Climatic Data Center, the National Weather Service, the National Resource Conservation Service, the Bureau of Land Management, the U.S. Forest Service, and other federal, state, and local agencies. Although the data reflects actual rainfall at Lindbergh field, it is representative of rainfall for the area served by the District. 7.49 9.17 11.01 12.66 8.03 6.48 5.74 7.68 10.38 12.97 0 2 4 6 8 10 12 14 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 In c h e s Annual Rainfall 10 year average 14 Overview Current Economic Conditions San Diego County Water Supply A safe, reliable water supply is crucial for the vitality of the San Diego region’s $222 billion economy and quality of life for 3.3 million residents, including Otay Water District’s more than 223,000 customers it serves. San Diego County imports approximately 85% of its water from the Colorado River and Northern California. Since these sources face legal and environmental constraints, the region has been making investments in the region’s water delivery and storage system and exploring other avenues to ensure an adequate water supply. This includes water recycling, water-use efficiency programs, water storage, groundwater desalination, and seawater desalination. Desalinated Water Supply In December 2015, the Claude “Bud” Lewis Carlsbad Desalination Plant began producing approximately 50 million gallons of water per day to CWA, enough to serve approximately 400,000 people, meeting 7% to 10% of the region’s demand. Since the production desalinated water from the Carlsbad plant, District’s customers have received an average of 10% of this highly reliable, drought-proof water supply. An acre-foot is approximately 325,900 gallons or enough to supply two typical single-family households of four for a year. Economic Outlook At the start of each budget cycle, the District enters into a contract with an economist to complete an economic outlook study for both San Diego County and the area served by the District. The following summarizes the conclusions and projections as to the growth of San Diego County and the District’s service area:  San Diego County’s economy continues to experience solid growth. The unemployment rate dropped to 4.2% in December and is lower than the national and state rates of 4.5% and 5.0%, respectively.  San Diego County added 28,900 jobs in 2016, a 2% increase for 2017. Another year of solid job gains with an additional dip in the unemployment rate. The county is expected to add another 25,000 to 30,000 jobs annually for the foreseeable future.  San Diego County’s population will continue to grow in the near future by more than 25,000 persons annually.  Housing construction is forecasted to average 10,000 to 11,000 units annually during each of the next six years, with as much as 21% of that growth in the District’s service area.  As much as 70% of the new housing in the District’s service area will be attached, both for sale and rental.  Commercial development in the District’s service area is expected to increase as office and retail space ramps up in the millenia masterplan community. The millenia project includes nearly 3,000 multi-family residential units, an office park, retail uses, parks and a hotel. 15 Overview Future Development Using the economist’s report, the District’s engineering staff projects that over the next six years the District will sell another 3,438 meters which translates to 4,309 equivalent dwelling units (EDUs). Residential Construction The following table summarizes the projected units for sale and units for rent from fiscal year 2017 through fiscal year 2023. Projected Units for Sale and Rental Otay Water District Service Area FY 2017 through FY 2023 Project 2017 2018 2019 2020 2021 2022 2023 Total Total Single-Family Units 35 266 477 591 863 656 566 3,454 Total Condominium 129 479 494 500 597 586 442 3,227 Total Rental 0 175 252 723 834 838 300 3,122 Total Units 164 920 1,223 1,814 2,294 2,080 1,308 9,803 % Multi-Family 79% 71% 61% 67% 62% 68% 57% 65% Source: The London Group Realty Advisors, March 2017 Projected Meter Sales in EDUs 34 4 62 8 77 8 1, 0 8 7 83 3 63 9 0 200 400 600 800 1,000 1,200 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 16 Overview Commercial Construction Commercial construction in the District is projected to be modest during the next six years with 3,939,190 square feet of commercial development in the planning stages and under construction. Industrial space has the most leasable space with an estimated 1,774,032 square feet, of which 123,456 square feet is currently under construction. There are also 840 total hotel rooms in five planned hotel projects with 283 rooms in two projects that are currently under construction. There is 1,643,583 square feet of space and 205 hotel rooms with an unknown delivery date since delivery expectations are typically contingent on the identification of a lessee prior to construction. Under Construction and Planned Commercial Development Expected Delivery Year Industrial (S.F.) Office (S.F.) Retail (S.F.) Total (S.F.) Hotels (Rooms) 2017 123,456 0 13,144 136,600 283 2018 356,910 318,000 145,230 820,140 2019 0 712,100 20,000 732,100 2020 0 395,000 26,767 421,767 152 2018-2021 185,000 0 0 185,000 200 Unknown 1,108,666 309,000 225,917 1,643,583 205 TOTAL 1,774,032 1,734,100 431,058 3,939,190 840 Source: The London Group Realty Advisors, CoStar The Future Rosarito Desalination and the Otay Mesa Conveyance and Disinfection System Projects In light of the growing need for new potable water supplies in Mexico and San Diego County, the proposed Rosarito plant and the District’s Otay Mesa Conveyance and Disinfection System Project would provide a new drought-proof water supply to its customers. On May 16, 2017, the U.S. Department of State granted a presidential permit to allow the Otay Water District to build a nearly four-mile long potable water pipeline that begins at the U.S.-Mexico border. This permit authorizes the District to “construct, connect, operate, and maintain cross-border water pipeline facilities for the importation of desalinated seawater at the International Boundary between the United States and Mexico in San Diego County, California.” Purchasing and transporting water from Aguas de Rosarito’s desalination plant in Rosarito, Baja California, Mexico, is a component of the District’s water supply diversification efforts. The Rosarito plant could potentially produce water to meet up to two-thirds of the District’s projected water use by 2024. The District currently provides water service to a population of more than 223,000 people, which is expected to increase to more than 308,000 by 2050. The Rosarito Desalination Project would produce 100 million gallons of water daily in two phases. The first phase, expected to be operational by late 2019 or early 2020, would make 50 million gallons or 17 Overview The Future (continued) Rosarito Desalination and the Otay Mesa Conveyance and Disinfection System Projects (continued) more of desalinated water available daily to the Tijuana/Rosarito region. The second phase, expected to be completed by 2024, would deliver up to an additional 50 million gallons daily, with 10 to 30 percent of that water available to the District. In addition to the construction of a potable water pipeline on the U.S. side of the border, the project also includes a pump station, and disinfection facility. This would be the first cross-border water supply project of its kind to import water to the U.S. from Mexico. The project has undergone environmental review as required by the California Environmental Quality Act and National Environmental Policy Act and has obtained a U.S. Fish and Wildlife biological permit. The District recognizes that such a project require rigorous safeguards and review to ensure the protection of public health and has applied for a permit from the California Water Resources Control Board’s Division of Drinking Water to ensure that water imported from Mexico meets the same water quality drinking standards as water from regional lakes, from the Claude “Bud” Lewis Carlsbad Desalination Plant, and from the City of San Diego’s Pure Water Program. 18 Strategic Plan Balanced Scorecard Perspective The Balanced Scorecard is used as a core methodology for the District’s Strategic Plan. This method aligns business activities to the vision and strategy of the organization and is designed to ensure that a company is performing consistently on a wide range of measures necessary to ensure both short-term and long-term advancements. The Balanced Scorecard emphasizes an integrated strategic approach for the development of goals and measures in four perspectives: customer, financial, business processes, and learning and growth. Major components of the Strategic Plan are the District’s strategic objectives which guide the agency’s efforts to meet and positively adapt to change. Each objective is broken down by the balanced scorecard, strategy, and the goal required to meet the specific challenge. Customer Deliver high quality services to meet and increase confidence of the customer in the value the District provides Financial Manage the financial issues that are critical to the District Business Processes Maximize efficiency and effectiveness Learning & Growth Provide leadership and management expertise Performance measures and targets are a critical element of the Strategic Plan but differ from strategic plan objectives. Objectives identify the action items that are necessary to execute the mission of the District. Performance measures are designed to ensure the day-to-day operations and services of the utility are meeting agreed upon expectations. 19 Administrative Services Objectives Goal Objective Status Improve and expand communications Regularly produce and evaluate communications tools and explore the effective use of new media options including: electronic newsletters, auto-dialer services, video streaming, social networks, or web media to ensure the District’s outreach efforts are cost-effectively reaching all stakeholders On Schedule Provide effective water services Optimize SCADA program Completed Goal Objective Status Actively manage water supply as well as support for water and sewer services Evaluate and enhance the District's water conservation programs and services On Schedule Optimize asset management program On Schedule Enhance District’s enterprise facilities physical security On Schedule Enhance District's enterprise confined space program On Schedule Advance business processes and operational efficiencies through implementation of Information Technology Completed Evaluate implementation of an on-line performance management system On Schedule Goal Objective Status Reinforce a results-oriented and accountable culture Negotiate a successor Memorandum of Understanding for represented employees for 2018 and beyond and related compensation and benefits for unrepresented employees with emphasis on making necessary updates to employee health benefits related to health care reform On Schedule Enhance District's Emergency Response Program On Schedule Evaluate opportunities to combine or transfer similar work functions Completed Evaluate training and development programs for new and existing Supervisors/Managers Completed Strategic Plan Le a r n i n g & G r o w t h Cu s t o m e r Identify and evaluate improvements to enterprise and departmental business processesBu s i n e s s P r o c e s s e s Focus on achieving a lean, flexible workforce 20 Administrative Services Objectives Administrative Services Performance Measures Balanced Scorecard:Business Processes Target:No less than 99.5% each quarter in a year Measurement Method:99.5% = 3.60 hours of downtime per month/1.83 days of downtime in a year FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 99.5% 99.5% 99.5% 99.5% Actual (1)99.9% 99.9% 99.5% 99.5% Balanced Scorecard:Learning and Growth Target:Less than 5% turnover in a year Measurement Method: FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 5.0% 5.0%5.0% 5.0% Actual (1)3.2% 0.0% 0.7% 0.0% Balanced Scorecard:Learning and Growth Target:12 hours or more per employee per year Measurement Method: FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 12.0 12.0 12.0 12.0 Actual (1)17.5 23.0 22.9 12.0 Strategic Plan Number of voluntary resignations (not including retirements) /Average number of employees Total qualified training hours for all employees/ Average number of full time employees (FTE) Enterprise Technology Services Availability Employee Voluntary Turnover Rate Training Hours per Employee (1) FY 17-18 Projected Measure 21 Balanced Scorecard:Learning and Growth Target:24 hours or more per field employee per year Measurement Method: FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 24.0 24.0 24.0 24.0 Actual (1)43.1 36.8 30.8 24.0 Balanced Scorecard:Learning and Growth Target:No more than 6.6 injury incidents per 200,000 hours worked in a year Measurement Method:[200,000 (Number of injuries and illnesses)]/Employee hours worked FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 6.6 6.6 Actual (1)4.9 6.6 Safety Training Program Administrative Services Performance Measures (1) FY 17-18 Projected Measure (2) FY 16-17 is the first year for this performance measure Strategic Plan Number of safety training hours/Number of field employees (includes mandated training) Injury Incident Rate(2) 22 Finance Objectives Goal Objective Status Increase customer confidence in the District Enhance communications with customers On Schedule Goal Objective Status Implement a cost Benefit Program On Schedule Strengthen Internal Audit Program On Schedule Goal Objective Status Identify and evaluate improvements to enterprise and departmental business processes Improve and streamline Meter Related Processes Completed Cu s t o m e r Fi n a n c i a l Bu s i n e s s Pr o c e s s e s Maintain District financial strength Strategic Plan 23 Balanced Scorecard:Customer Target:No less than 97% each quarter in a single year Measurement Method:Number of all calls answered/Number of all calls received FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 97.0% 97.0% 97.0% 97.0% Actual (1)98.3% 97.8% 98.1% 97.0% Balanced Scorecard:Financial Target:No less than 99.80% per quarter in a year Measurement Method:Number of correct bills/Number of total bills FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 99.8% 99.8% 99.8% 99.8% Actual (1)99.8% 99.9% 99.9% 99.8% Balanced Scorecard:Financial Target:In development Measurement Method:Number of customers paying bills electronically/Total number of customers FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 75.6% 75.6% Actual (1) 75.6% 75.6% Balanced Scorecard:Financial Target:Less than 100% of the budgeted overtime in a year Measurement Method:Actual overtime costs (including comp time) FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 100.0% 100.0% 100.0% 100.0% Actual (1)98.0% 129.0% 118.0% 100.0% Balanced Scorecard:Financial Target:Bottom 50 percentile for the 28 sewer service providers in San Diego Measurement Method:Otay percentage ranking for the average bill for sewer among regional agencies FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 14 14 14 14 Actual (1)8755 (2) FY 15-16 is the first year for this performance measure (1) FY 17-18 Projected Measure Finance Performance Measures Strategic Plan Answer Rate Billing Accuracy Percentage of Customers Paying Bills Electronically (2) Overtime Percentage Sewer Rate Ranking 24 Balanced Scorecard:Financial Target:Bottom 50 percentile for the 22 member agencies in San Diego Measurement Method:Otay percentage ranking among regional agencies FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 11 11 11 11 Actual (1)11 10 11 3 Balanced Scorecard:Financial Target:150% excluding growth revenue Measurement Method:Qualified net operating revenues/Debt service requirements FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 150.0% 150.0% 150.0% 150.0% Actual (1)168.0% 171.0% 200.0% 236.0% Balanced Scorecard:Financial Target:The annual average is 85.0% Measurement Method: FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 85.0% 85.0% 85.0% 85.0% Actual (1)100.0% 78.0% 85.0% 85.0% Balanced Scorecard:Financial Target:Less than 5% in a year Measurement Method:100 [Volume purchased – (volume sold + volume used) /Volume purchased] FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 5.0% 5.0% 5.0% 5.0% Actual (1)2.5% 4.0% 4.1% 5.0% Strategic Plan Number of reserve funds that meet or exceed fund target levels/Total number of reserve funds Finance Performance Measures (1) FY 17-18 Projected Measure Water Rate Ranking Debt Coverage Ratio Reserve Level Distribution System Loss 25 Balanced Scorecard:Financial Target:406 accounts per FTE Measurement Method:Potable + Recycled + Sewer Accounts/ Number of full time employees FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 406.0 412.0 Actual (1) 406.0 415.0 Balanced Scorecard:Financial Target:Less than $544.88 per account in a year Measurement Method:Total O&M costs/Number of Accounts FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target $531 $531 $544 $561 Actual (1)$511 $503 $517 $561 (2) FY 16-17 is the first year for this performance measure (1) FY 17-18 Projected Measure Strategic Plan Finance Performance Measures Accounts per Full-Time Employee (FTE) (2) O & M Cost per Account 26 Operations Objectives Goal Objective Status Improve and expand communications Evaluate requirements for future Emergency Communication system On Hold Goal Objective Status Electric power and fuel management practices On Schedule Optimize Operations Non-Inventory Management On Schedule Goal Objective Status Leak Detection and Repair Program On Schedule Pressure Vessel Maintenance Program On Schedule Operations Workflow Process Evaluation On Schedule Streamline input of operations data Behind Schedule Bu s i n e s s P r o c e s s e s Identify and evaluate improvements to enterprise and departmental business processes Actively manage water supply as well as support for water and sewer services Strategic Plan Cu s t o m e r Fi n a n c i a l Improve financial information and systems 27 Balanced Scorecard:Customer Target: Measurement Method: FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 9.00 9.00 9.00 9.00 Actual (1)3.69 5.12 3.94 4.25 Balanced Scorecard:Financial Target:66% of labor dollars spent on preventive maintenance per quarter in a year Measurement Method:Total planned maintenance cost/Total maintenance cost FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 66.0% 66.0% 66.0% 66.0% Actual (1)66.0% 75.0% 70.0% 66.0% Balanced Scorecard:Financial Target:70% of labor dollars spent on preventive maintenance per quarter in a year Measurement Method:Total planned maintenance cost/Total maintenance cost FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 70.0% 70.0% 70.0% 70.0% Actual (1)91.0% 86.0% 91.0% 70.0% Balanced Scorecard:Financial Target:77% of labor dollars spent on preventive maintenance per quarter in a year Measurement Method:Total planned maintenance cost/Total maintenance cost FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 77.0% 77.0% 77.0% 77.0% Actual (1)91.6% 91.8% 90.6% 77.0% Balanced Scorecard:Financial Target:No more than $1,050 per MG spent on wastewater treatment in a year Measurement Method:Total O&M costs directly attributable to sewer treatment /Total volume (in MGD) FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target $1,050 $1,050 $1,050 $1,050 Actual (1)$785 $913 $1,096 $1,050 Technical Quality Complaint Planned Potable Water Maintenance Ratio in $ Planned Recycled Maintenance Ratio in $ Planned Wastewater Maintenance Ratio in $ Direct Cost of Treatment per MGD Strategic Plan Operations Performance Measures No more than 9 complaints per 1,000 customer accounts in a year 1,000 (Number of technical quality complaints)]/Number of active customer accounts per reporting period (1) FY 17-18 Projected Measure 28 Balanced Scorecard:Financial Target:No more than $1,925 per MG spent on O&M for wastewater treatment in a year Measurement Method:Total O&M cost (less depreciation)/Volume in MG processed FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target $1,925 $1,925 $1,925 $1,925 Actual (1)$1,150 $1,458 $1,483 $1,925 Balanced Scorecard:Financial Target:20% by the end of the year Measurement Method:Percentage distribution system surveyed for leaks FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 20.0% 20.0% 20.0% 20.0% Actual (1)20.0% 20.0% 33.0% 20.0% Balanced Scorecard:Business Processes Target:90% each quarter in a year Measurement Method:Number of PM's completed/Number of PM's scheduled to be completed FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 90.0% 90.0% 90.0% 90.0% Actual (1)98.9% 100.0% 100.0% 90.0% Percent of Preventative Maintenance Completed – Reclamation Plant Balanced Scorecard:Business Processes Target:90% each quarter in a year Measurement Method:Number of PM's completed/Number of PM's scheduled to be completed FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 90.0% 90.0% 90.0% 90.0% Actual (1)98.0% 100.0% 99.0% 90.0% Percent of Preventative Maintenance Completed – Pump/Electric Balanced Scorecard:Business Processes Target:90% each quarter in a year Measurement Method:Number of PM's completed/Number of PM's scheduled to be completed FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 90.0% 90.0% 90.0% 90.0% Actual (1)100.0% 100.0% 100.0% 90.0% (1) FY 17-18 Projected Measure O&M Cost per MGP - Wastewater Leak Detection Program Percent of Preventative Maintenance Completed – Fleet Sho Strategic Plan Operations Performance Measures 29 System Valve Exercising Program Balanced Scorecard:Business Processes Target:770 valves per quarter/3,080 valves in a year Measurement Method:Actual number of valves exercised FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 3,080 3,080 3,080 3,080 Actual (1) 3,425 4,549 3,228 3,080 Potable Water Distribution System Integrity Balanced Scorecard:Business Processes Target:16 leaks or breaks per 100 miles of distribution piping in a year Measurement Method:[100 (Annual total number of leaks & breaks)] / Total miles of distribution pipes FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 16.0 16.0 16.0 16.0 Actual (1)17.1 11.1 10.3 16.0 Collection System Integrity Balanced Scorecard:Business Processes Target:No more than 3.6 system failures per 100 miles of collection system pipeline in a year Measurement Method:[100 (Collection system failure)] /Total miles of collection system piping FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 3.6 3.6 3.6 3.6 Actual (1)0.0 0.0 1.0 0.0 Recycled Water System Integrity Balanced Scorecard:Business Processes Target: Measurement Method:[100 (Collection system failure)] /Total miles of collection system piping FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 6.6 6.6 6.6 6.6 Actual (1)1.1 0.00 0.9 0.0 Potable Water Compliance Rate Balanced Scorecard:Business Processes Target:100% each quarter in a year Measurement Method:All primary health regulations are met FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 100.0% 100.0% 100.0% 100.0% Actual (1)100.0% 100.0% 100.0% 100.0% (1) FY 17-18 Projected Measure No more than 6.6 system failures per 100 miles of recycled distribution system in a year Strategic Plan Operations Performance Measures 30 Sewer Overflow Rate Balanced Scorecard:Business Processes Target:Overflows per quarter in a year is zero Measurement Method: FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 0000 Actual (1)0010 Emergency Facility Power Testing Balanced Scorecard:Business Processes Target:100% of the District’s facilities tested per year (34 facilities) Measurement Method:Number of facilities and generators tested/Total facilities FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 34 29 34 34 Actual (1)36 29 36 34 Main Flushing and Hydrant Maintenance (2) Balanced Scorecard:Business Processes Target:215 or more mains flushed and fire hydrants maintained in a single year Measurement Method:Number of mains flushed and fire hydrants maintained FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 215 215 215 215 Actual (1)753 463 355 215 Critical Valve Exercising Balanced Scorecard:Business Processes Target:100% of identified critical valves exercised in a year Measurement Method:Cumulative number of mains flushed plus hydrants maintained FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 520 631 631 631 Actual (1)520 631 631 631 Tank Inspection and Cleaning Balanced Scorecard:Business Processes Target:8 potable water storage tanks/reservoirs are cleaned per fiscal year Measurement Method:Number of tanks cleaned and inspected annually FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 8878 Actual (1)5118 8 (1) FY 17-18 Projected Measure (2) In FY 14-15, fire hydrant maintenance was the focus for the valve crew. For FY 15-16 and FY 16-17, main flushing was completed as needed [100 (Total number of sewer overflows)]/Total miles of pipe in the sewage collection system Strategic Plan Operations Performance Measures 31 Engineering Objectives Goal Objective Status Evaluate City of San Diego's Pure Water Program Planning/Implementation On Schedule Address dependency of imported water Completed Sewer system business evaluation Completed Evaluate the viability of implementing an Indirect Potable Reuse Program Completed Evaluate efficiencies for delivering capital assets Completed Streamline work processes in four strategic areas including departmental synergies, technology, procurements, and alignment of business practices Completed Revise business practices by modifying the master recycled water permit Completed Implement a Habitat Conservation Plan that will streamline O&M within District easements Completed Strategic Plan Identify and evaluate improvements to enterprise and departmental business processes Bu s i n e s s P r o c e s s e s Actively manage water supply as well as support for water and sewer services 32 CIP Project Expenditures vs. Budget Balanced Scorecard:Financial Target:95% of budget but not to exceed 100% Measurement Method:Actual quarterly expenditures/Annual budget FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 95.0% 95.0% 95.0% 95.0% Actual (1)92.2% 89.8% 109.1% 95.0% Construction Change Order Incidence Balanced Scorecard:Financial Target:No more than 5% per quarter in a year Measurement Method: FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 5.0% 5.0% 5.0% 5.0% Actual (1)1.9% 1.8% 1.5% 5.0% Mark-out Accuracy Balanced Scorecard:Business Processes Target:No less than 100% every quarter in a single year Measurement Method: FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 100.0% 100.0% 100.0% 100.0% Actual (1)100.0% 100.0% 100.0% 100.0% Project Closeout Time Balanced Scorecard:Business Processes Target:No more than a 45 day average per quarter in a year Measurement Method: FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 45.0 45.0 45.0 45.0 Actual (1)29.0 37.3 71.2 45.0 Strategic Plan Total cost of change orders (not including allowances)/Total original construction contract amount (not including allowances) Number of mark-outs performed without an at-fault hit/Total number of mark-outs performed Number of days between NOSC and NOC for all construction projects within the quarter/Number of construction projects Engineering Performance Measures (1) FY 17-18 Projected Measure 33 Annual Recycled Water Site Inspections Balanced Scorecard:Business Processes Target:100% of recycled sites inspected in a year Measurement Method: FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 100.0% 100.0% 100.0% 100.0% Actual (1)100.0% 100.0% 100.0% 100.0% Recycled Water Shutdown Testing Balanced Scorecard:Business Processes Target:90% of recycled site shut down tests in a year Measurement Method:Percentage of recycled water use sites per year compared to those scheduled FY 14-15 FY 15-16 FY 16-17 FY 17-18 Target 90.0% 90.0% 90.0% 90.0% Actual (1)100.0% 93.0% 90.0% 90.0% (1) FY 17-18 Projected Measure Percentage of recycled sites inspected per year of those required by the Department of Environmental Health (DEH) Strategic Plan Engineering Performance Measures 34 Capital Budget The District provides water service to a population of approximately 220,000 which is expected to ultimately increase to 308,000 by the year 2050. This growth, as well as the maintenance of existing assets, requires long-term capital planning. The process is dynamic, due to evolving needs of the community, water supply issues, and changing regulations. As such, capital planning is part of the District’s overall strategic planning process. The capital planning process involves identifying current needs, future needs, and prioritizing them based on certain operating assumptions. The primary objective of this planning effort is to support an orderly and efficient program of expansion, new water supply, replacement, and betterment, while maintaining a stable long-range financial plan. To accommodate growth requires that the District invest $283 million in capital assets through ultimate build-out. The Fiscal Year 2018 Capital Budget is $20.0 million and the six-year Capital Improvement Program (CIP) totals $102.3 million. The CIP is consistent with the District's Water Facilities Master Plan, Sewer System Management Plan, current capacity fees, and the District's strategic financial objectives. This CIP Budget document contains the descriptions, justifications, expenditures, and funding for all the identified projects to ultimate build-out. The District’s Capital Improvement Program (CIP) The planning, design, and construction costs of all capital facilities within three business segments (Potable Water, Recycled Water and Sewer) are allocated to four cost types and corresponding fund categories: Expansion, Betterment, Replacement and/or New Water Supply. The allocation to these four cost types is defined in the District’s Capital Improvement Program (CIP) and is determined by an engineering analysis that identifies which type of customer will benefit from each facility, planned or existing. The costs of the capital improvements are borne by either existing users or by the developing areas, or by a combination of the two, as applicable. The following are general descriptions of the four funding categories: Expansion Facilities required to support new or future users are funded from capacity fees or user rates. Betterment Facilities required because of inadequate capacity or new requirements that benefit existing users are funded from availability, betterment fees, or rates. Replacement Facilities required to renew or replace existing facilities that have deteriorated or have exceeded their useful life are funded from user rates. New Water Supply Facilities required to support new sources of water are funded from new supply fees or user rates. 35 Capital Budget Assumptions and Criteria The CIP is developed based on the District's Water Facilities Master Plan and the Sewer System Mater Plan, incorporating historical data, growth, developers' input, SANDAG projections, and long- term economic outlook. The Water Facilities Master Plan was built using several major assumptions and design criteria as follows: 1. Utilizing historical water demands for each land use type in the District to calculate future demands. 2. Using seasonal maximum day demand peaking factors. 3. Utilizing land use as planned by the City of Chula Vista, County of San Diego and City of San Diego. 4. Providing ten days of emergency water supply through a maximum of five days in covered reservoirs and a minimum of five days from interconnections with adjacent agencies. 5. Inclusion of emergency operational storage to meet the five-day covered storage requirement and the ten-day outage supply requirement. CIP Justification and Impact on Operating Budget The justification for each project is determined by whether it is required due to growth (Expansion), new water sources (New Supply), improvements or upgrades (Betterment), or to replace an existing asset (Replacement). As these projects are completed and placed into service, there may be an impact on the Operating Budget by increasing costs in the areas of maintenance, energy, or chemicals as shown on the justification and impact pages in this section. Capital Purchases and Facilities All capital expenditures are in the CIP. This includes capital facilities and capital purchases. Capital purchases are non-recurring operating expenditures for assets that cost more than $10,000 each and have an estimated useful life of two years or more. The capital purchase projects include vehicles, office equipment, furniture, and field equipment purchases (P2282 and P2286). Capital facility projects are items that exceed $10,000 or $20,000 for infrastructure related items (as defined under Capital Equipment on page 264 of the Glossary) and have a useful life of at least two years. The CIP projects are identified and are prioritized based on the following criteria:  Safety, restoration of service, immediate obligation, Board directed, or critical system need.  System upgrades or requirements to maintain system reliability in the next few fiscal years.  Need to meet the future growth of the system.  Project requirement may be reduced in capacity or may have low probability of need in the future. 36 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total Beginning Balance 48,337$ 48,391$ 39,406$ 38,731$ 41,247$ 42,731$ 48,337$ Sources Capacity Fees 3,138 5,714 7,229 10,623 8,386 6,670 41,760 Debt financing (1)- 5,500 - - - - 5,500 Grants 255 505 500 500 500 133 2,393 Interest 574 553 572 625 738 817 3,879 Temporary Meters 1,429 1,443 1,458 1,475 1,496 1,518 8,819 Availability (Betterment Portion)461 479 498 518 539 560 3,055 New Supply Fee 296 550 702 1,005 794 629 3,976 COPS 2010B Reimbursement 772 772 772 772 772 772 4,632 Transfer from General Fund 22,134 10,410 10,895 11,407 12,574 13,070 80,490 Interfund Transfers 47 51 59 63 71 75 366 Total Sources 29,106 25,977 22,685 26,988 25,870 24,244 154,870 Uses CIP Projects 20,012 25,828 14,158 15,130 14,943 12,188 102,259 Debt Service 7,527 7,613 7,666 7,791 7,876 7,864 46,337 Developer Services 1,513 1,521 1,536 1,551 1,567 1,583 9,271 Total Uses 29,052 34,962 23,360 24,472 24,386 21,635 157,867 Net Sources (Uses)54 (8,985) (675) 2,516 1,484 2,609 (2,997) Ending Balance 48,391$ 39,406$ 38,731$ 41,247$ 42,731$ 45,340$ 45,340$ (1) Proposed Funding from the Clean Water State Revolving Fund for Campo Road Sewer Main Replacement CIP Reserve Funds ($1,000s) The CIP Reserve Funds presentation, shown on the following pages, is designed to provide an understanding of how the funding of CIPs is expected to financially influence the District over the next six years.  The financial impacts are based on CIPs and their funding sources, including fund transfers in accordance with the District’s Reserve Policy, and planned debt issuances. This data is captured in the District’s Rate Model on an annual basis in order to make these projections.  $0 $10 $20 $30 $40 $50 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 CIP Reserve Fund Balances ($1,000s) Betterment Replacement Expansion New Supply 37 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total Source Expansion 150$ 411$ 1,202$ 1,737$ 27$ 199$ 3,724$ Betterment (1)2,740 3,074 1,564 655 2,317 2,240 12,590 Replacement (1)17,107 22,312 11,362 12,708 12,569 9,719 85,775 New Supply 16 31 31 31 31 31 171 Total 20,012$ 25,828$ 14,158$ 15,130$ 14,943$ 12,188$ 102,259$ FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total Fund Potable 14,132$ 19,551$ 12,150$ 12,554$ 13,703$ 10,148$ 82,238$ Recycled 801 1,039 488 1,627 160 45 4,160 Sewer (1)5,079 5,238 1,520 949 1,080 1,995 15,861 Total 20,012$ 25,828$ 14,158$ 15,130$ 14,943$ 12,188$ 102,259$ CIP Funding Source CIP by Fund Six-Year CIP Projects Summary by Source ($1,000s) Six-Year CIP Projects Summary by Fund ($1,000s) $- $5 $10 $15 $20 $25 $30 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Six-Year CIP Projects by Funding Source, in Thousands ($) Expansion Betterment Replacement New Supply $- $5 $10 $15 $20 $25 $30 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Six-Year CIP Projects by Fund, in Thousands ($) Potable Recycled Sewer (1) Includes funds from the Clean Water State Revolving Fund38 Expansion CIP No CIP Project Title FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total P2040 Res - 1655-1 Reservoir 0.5 MG 20$ 50$ 1,175$ 1,610$ 20$ 20$ 2,895$ P2430 PL - 20-inch, 980 Zone, Proctor Valley Road – Village 14 Phase 1 5 5 5 5 5 10 35 P2494 Multiple Species Conservation Plan 30 - - - - - 30 P2500 Padre Dam - Otay Interconnection Dehesa Valley 19 2 2 2 2 19 43 P2547 District Administration Vehicle Charging Stations 6 9 - - - - 16 P2595 PL - 16-inch, 624 Zone, Village 3N - Heritage Road, Main St/Energy Way - - - - - 150 150 R2077 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway 20 20 - - - - 40 R2079 RecPL - 6-Inch, 450 Zone, Otay Valley Road - Otay Valley/Entertainment 10 10 10 120 - - 150 R2084 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media 40 315 10 - - - 365 Total Expansion 150$ 411$ 1,202$ 1,737$ 27$ 199$ 3,724$ Potable 80$ 66$ 1,182$ 1,617$ 27$ 199$ 3,169$ Recylced 70 345 20 120 - - 555 Sewer - - - - - - - Total Expansion 150$ 411$ 1,202$ 1,737$ 27$ 199$ 3,724$ Betterment CIP No CIP Project Title FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total P2267 36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations 10 10 - - - - 20 P2400 PL - 20-Inch Pipeline Replacement, 711 Zone, Otay Lakes Road - at Santa Paula - - 47 109 552 - 707 P2405 PL - 624/340 PRS, Paseo Ranchero and Otay Valley Road 5 5 5 50 500 85 650 P2451 Otay Mesa Desalination Conveyance and Disinfection System 35 69 69 69 69 69 380 P2500 Padre Dam - Otay Interconnection Dehesa Valley 41 4 4 4 4 41 97 P2504 Regulatory Site Access Road and Pipeline Relocation 10 25 25 1 1 5 66 P2521 Large Meter Vault Upgrade Program 25 25 100 100 50 - 300 P2547 District Administration Vehicle Charging Stations 14 21 - - - - 35 P2578 PS - 711-2 (PS 711-1 Replacement and Expansion) - 14,000 gpm - - - 109 992 2,000 3,100 P2608 PL - 8-inch, 850 Zone, Coronado Ave, Chestnut/Apple 5 20 145 5 - - 175 P2613 PL - 12-inch, 520 Zone, Rancho San Diego Towne Center Loop 10 35 100 5 - - 150 P2619 PS - Temporary Lower Otay Pump Station Redundancy 20 80 485 50 - - 635 R2110 RecPS - 944-1 Optimization and Pressure Zone Modifications 20 45 - - - - 65 R2116 RecPL - 14-Inch, 927 Zone, Force Main Improvements 200 400 - - - - 600 R2118 Steele Canyon Sewer PS Large Solids Handling Improvements 50 3 - - - - 53 R2120 RWCWRF Filtered Water Storage Tank Improvements 25 20 400 5 - - 450 R2123 Repurpose Otay Mesa Recycled Water Lines 5 5 5 150 150 35 350 R2125 RecPRS - 927/680 PRS Improvements, Otay Lakes Road 50 145 5 - - - 200 S2024 (1)Campo Road Sewer Main Replacement 2,125 2,125 25 - - - 4,275 S2043 RWCWRF Sludge Handling System 30 - - - - 5 35 (1) Includes funds from the Clean Water State Revolving Fund Six-Year CIP Projects by Source and Fund ($1,000s) 39 Betterment, Continued CIP No CIP Project Title FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total S2047 Asset Management - Info Master Sewer Implementation 30 28 - - - - 58 S2061 RWCWRF Aeration Controls Consolidation & Optimization Upgrades (S) 30 10 150 - - - 190 Total Betterment 2,740$ 3,074$ 1,564$ 655$ 2,317$ 2,240$ 12,590$ Potable 175$ 293$ 979$ 500$ 2,167$ 2,200$ 6,314$ Recylced 350 618 410 155 150 35 1,718 Sewer 2,215 2,163 175 - - 5 4,558 Total Betterment 2,740$ 3,074$ 1,564$ 655$ 2,317$ 2,240$ 12,590$ Replacement CIP No CIP Project Title FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total P2083 PS - 870-2 Pump Station Replacement 4,000 10,550 1,850 50 50 - 16,500$ P2174 PS - 1090-1 Pump Station Replacement (400 gpm)1 150 200 1,100 1,000 45 2,496 P2282 Vehicle Capital Purchases 363 240 187 236 253 250 1,529 P2286 Field Equipment Capital Purchases 72 50 55 60 60 63 360 P2382 Safety and Security Improvements 150 325 - - - - 475 P2400 PL - 20-Inch Pipeline Replacement, 711 Zone, Otay Lakes Road - at Santa Paula - - 104 242 1,228 - 1,573 P2453 SR-11 Utility Relocations 50 50 700 1,000 452 100 2,352 P2460 I.D. 7 Trestle and Pipeline Demolition 5 40 530 20 - - 595 P2485 SCADA - Infrastructure and Communications Replacement 181 185 85 24 - - 475 P2493 624-2 Reservoir Interior/Exterior Coating 5 5 5 - - - 15 P2504 Regulatory Site Access Road and Pipeline Relocation 10 25 25 1 1 5 66 P2507 East Palomar Street Utility Relocation 5 5 - - - - 10 P2508 Pipeline Cathodic Protection Replacement Program 100 1 1 248 - - 350 P2516 PL - 12-Inch, 640 Zone, Jamacha Road - Darby/Osage - - 75 100 725 - 900 P2518 803-3 Reservoir Interior/Exterior Coating 5 5 - - - - 10 P2520 Motorola Mobile Radio Upgrade 30 - - - - - 30 P2529 711-2 Reservoir Interior & Exterior Coating 5 5 - - - - 10 P2530 711-1 Reservoir Interior & Exterior Coating 5 5 - - - - P2531 944-1 Reservoir Interior & Exterior Coating 5 5 - - - - 10 P2532 944-2 Reservoir Interior & Exterior Coating 5 10 - - - - 15 P2533 1200-1 Reservoir Interior & Exterior Coating 10 745 5 45 - - 805 P2534 978-1 Reservoir Interior & Exterior Coating 10 5 5 5 - - 25 P2535 458-2 Reservoir Interior & Exterior Coating & Upgrades 5 5 - - - - 10 P2539 South Bay Bus Rapid Transit (BRT) Utility Relocations 5 40 100 50 - - 195 P2542 850-3 Reservoir Interior Coating 5 5 - - - - 10 P2543 850-1 Reservoir Interior/Exterior Coating 5 695 125 5 40 - 870 P2544 850-2 Reservoir Interior/Exterior Coating 700 5 5 20 - - 730 P2545 980-1 Reservoir Interior Exterior Coating 5 5 - - - - 10 P2546 980-2 Reservoir Interior/Exterior Coating 1,100 340 5 5 - - 1,450 P2553 Heritage Road Bridge Replacement and Utility Relocation 50 100 100 250 755 150 1,405 P2555 Administration and Operations Parking Lot Improvements 265 215 - - - - 480 Six-Year CIP Projects by Source and Fund ($1,000s) 40 Replacement, Continued CIP No CIP Project Title FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total P2557 520 Res Recirculation Pipeline Chemical Supply and Analyzer Feed Replacement Project 35 5 - - - - 40 P2559 Pressure Vessel Repair and Replacement Program 30 45 100 100 100 100 475 P2561 Res - 711-3 Reservoir Cover/Liner Replacement 1 10 84 1,690 10 - 1,795 P2562 Res - 571-1 Reservoir Cover/Liner Replacement 2,700 145 5 - - - 2,850 P2563 Res - 870-1 Reservoir Cover/Liner Replacement 1 5 10 90 892 - 998 P2565 803-2 Reservoir Interior/Exterior Coating & Upgrades - 20 820 5 5 90 940 P2566 520-2 Reservoir Interior/Exterior Coating & Upgrades - - 10 1,240 150 100 1,500 P2567 1004-2 Reservoir Interior/Exterior Coating & Upgrades - - - 20 780 105 905 P2568 Technology Business Processes Improvement - Enterprise Content Management System 36 - - - - - 36 P2571 Datacenter Network- Data, Storage, and Infrastructure Enhancements - 100 100 - - - 200$ P2572 Enterprise Resource Planning (ERP) Replacement - - - 250 250 - 500 P2573 PL - 12-Inch Pipeline Replacement, 803 Zone, Hillsdale 1,600 610 - - - - 2,210 P2574 PL - 12-Inch Pipeline Replacement, 978 Zone, Vista Vereda 450 2,000 30 - - - 2,480 P2578 PS - 711-2 (PS 711-1 Replacement and Expansion) - 14,000 gpm - - - 242 2,208 4,451 6,900 P2584 Res - 657-1 and 657-2 Reservoir Demolitions - - - - - 35 35 P2593 458-1 Reservoir Interior/Exterior Coating & Upgrades - - - 10 730 100 840 P2594 Large Meter Replacement 150 95 - - - - 245 P2604 AMR Change Out 1,510 1,745 1,475 1,095 1,290 1,190 8,305 P2605 458/340 PRS Replacement, 1571 Melrose Ave 1 50 189 10 - - 250 P2606 803-2 Reservoir Repair/Replacement of Caulking and Tree Removal 1 55 19 - - - 75 P2607 Douglas Ave SWA and OWD Interconnection Upgrade 10 30 10 - - - 50 P2608 PL - 8-inch, 850 Zone, Coronado Ave, Chestnut/Apple 5 20 145 5 - - 175 P2609 PL - 8-inch, 1004 Zone, Eucalyptus St, Coronado/Date/La Mesa - 10 65 315 10 - 400 P2610 Valve Replacement Program - Phase 1 30 60 60 - - - 150 P2611 Quarry Road Bridge Replacement and Utility Relocation 5 10 60 425 450 50 1,000 P2612 PL - 12-inch, 711 Zone, Pas de Luz/Telegraph Canyon Rd 5 10 85 390 10 - 500 P2614 485-1 Reservoir Interior/Exterior Coating - - - - 10 885 895 P2615 PL - 12-Inch Pipeline Replacement, 803 PZ, Vista Grande - 20 130 1,030 20 - 1,200 P2616 PL - 12-Inch Pipeline Replacement, 978 Zone, Pence Dr/Vista Sierra Dr 20 180 2,280 20 - - 2,500 P2617 Lobby Security Enhancements 75 - - - - - 75 P2620 Radio and Emergency Communication System 20 - - - - - 20 P2623 Central Area to Otay Mesa Interconnection Pipelines Combination Air/Vacuum Valve Replacements 20 120 120 10 - - 270 R2121 Res - 944-1 Reservoir Cover/Liner Replacement 1 1 33 1,347 - - 1,382 R2139 RWCWRF - Filter Troughs Replacement 30 - - - - - 30 R2143 AMR Change Out 350 75 25 5 10 10 475 S2012 San Diego County Sanitation District Outfall and RSD Outfall Replacement 20 200 250 300 350 400 1,520 S2024 (1)Campo Road Sewer Main Replacement 2,125 2,125 25 - - - 4,275 (1) Includes funds from the Clean Water State Revolving Fund Six-Year CIP Projects by Source and Fund ($1,000s) 41 Replacement, Continued CIP No CIP Project Title FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total S2027 Rancho San Diego Pump Station Rehabilitation 5 5 5 444 - - 459 S2033 Sewer System Rehabilitation 10 10 - - - - 20 S2044 Trenchless Sewer Rehabilitation 75 5 - - - - 80 S2045 Fuerte Drive Sewer Relocation 50 130 - - - - 180 S2046 RWCWRF - Aeration Panels Replacement 50 100 200 - - - 350 S2048 Hillsdale Road Sewer Repairs 400 270 - - - - 670 S2049 Calavo Basin Sewer Rehabilitation - Phase 2 19 130 845 5 - - 999 S2050 Rancho San Diego Basin Sewer Rehabilitation - Phase 2 - - 20 180 550 500 1,250 S2051 RWCWRF - Headworks Improvements 50 100 - - - - 150 S2053 RWCWRF - Sedimentation Basins Weirs Replacement 60 - - - - - 60 S2054 Calavo Basin Sewer Rehabilitation - Phase 3 - - - 20 180 1,090 1,290 Total Replacement 17,107$ 22,312$ 11,362$ 12,708$ 12,569$ 9,719$ 85,775$ Potable 13,862$ 19,161$ 9,959$ 10,407$ 11,479$ 7,719$ 72,585$ Recylced 381 76 58 1,352 10 10 1,887 Sewer 2,864 3,075 1,345 949 1,080 1,990 11,303 Total Replacement 17,107$ 22,312$ 11,362$ 12,708$ 12,569$ 9,719$ 85,775$ New Supply CIP No CIP Project Title FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total P2451 Otay Mesa Desalination Conveyance and Disinfection System 16 31 31 31 31 31 171 Total New Supply 16$ 31$ 31$ 31$ 31$ 31$ 171$ Potable 16$ 31$ 31$ 31$ 31$ 31$ 171$ Recylced - - - - - - - Sewer - - - - - - - Total New Supply 16$ 31$ 31$ 31$ 31$ 31$ 171$ Summary by Source Funding Source FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total Expansion 150 411 1,202 1,737 27 199 3,724$ Betterment (1)2,740 3,074 1,564 655 2,317 2,240 12,590 Replacement (1)17,107 22,312 11,362 12,708 12,569 9,719 85,775 New Supply 16 31 31 31 31 31 171 Total CIP by Funding Source 20,012$ 25,828$ 14,158$ 15,130$ 14,943$ 12,188$ 102,089$ Summary by Fund Fund FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total Potable 14,132 19,551 12,150 12,554 13,703 10,148 82,238$ Recycled 801 1,039 488 1,627 160 45 4,160$ Sewer * 5,079 5,238 1,520 949 1,080 1,995 15,861$ Total CIP by Fund 20,012$ 25,828$ 14,158$ 15,130$ 14,943$ 12,188$ 102,259$ (1) Includes funds from the Clean Water State Revolving Fund Six-Year CIP Projects by Source and Fund ($1,000s) 42 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 P2040 P2083 P2174 P2267 P2282 P2286 P2382 P2400 P2405 P2430 P2451 P2453 P2460 P2485 P2493 P2494 P2500 P2504 P2507 P2508 P2516 P2518 P2520 P2521 P2529 P2530 P2531 P2532 P2533 P2534 Planning Design Construction Six-Year CIP Projects Schedule Warranty 978-1 Reservoir Interior & Exterior Coating 6/2/2016 9/30/2017 944-2 Reservoir Interior & Exterior Coating 5/1/2014 6/29/2018 1200-1 Reservoir Interior & Exterior Coating 6/1/2016 6/30/2020 711-1 Reservoir Interior & Exterior Coating 6/1/2015 12/31/2018 944-1 Reservoir Interior & Exterior Coating 5/1/2014 6/29/2018 Large Meter Vault Upgrade Program 8/1/2016 6/30/2022 711-2 Reservoir Interior & Exterior Coating 6/1/2015 12/31/2018 803-3 Reservoir Interior/Exterior Coating 7/1/2011 7/31/2018 Motorola Mobile Radio Upgrade 8/1/2011 6/30/2018 Pipeline Cathodic Protection Replacement Program 7/1/2010 6/30/2021 PL - 12-Inch, 640 Zone, Jamacha Road - Darby/Osage 7/1/2019 6/30/2022 Regulatory Site Access Road and Pipeline Relocation 7/1/2010 6/30/2025 East Palomar Street Utility Relocation 7/1/2010 6/30/2017 Multiple Species Conservation Plan 7/1/2009 6/30/2018 Padre Dam - Otay Interconnection Dehesa Valley 7/1/2017 6/30/2025 SCADA - Infrastructure and Communications Replacement 7/1/2009 6/30/2021 624-2 Reservoir Interior/Exterior Coating 7/1/2009 6/30/2017 SR-11 Utility Relocations 7/1/2006 6/30/2023 I.D. 7 Trestle and Pipeline Demolition 7/1/2016 6/30/2021 PL - 20-inch, 980 Zone, Proctor Valley Road – Village 14 Phase 1 1/1/2018 6/30/2026 Otay Mesa Desalination Conveyance and Disinfection System 7/1/2006 6/30/2029 PL - 20-Inch Pipeline Replacement, 711 Zone, Otay Lakes Road - at Santa Paula 7/1/2019 6/30/2022 PL - 624/340 PRS, Paseo Ranchero and Otay Valley Road 7/1/2016 6/30/2023 Safety and Security Improvements 7/1/2002 6/30/2019 FY 2021 36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations 4/1/2015 6/30/2018 Vehicle Capital Purchases 12/1/2000 6/30/2028 PS - 870-2 Pump Station Replacement 7/1/2013 5/1/2022 PS - 1090-1 Pump Station Replacement (400 gpm) 7/1/2017 6/30/2023 FY 2022 FY 2023CIP No Q1 Res - 1655-1 Reservoir 0.5 MG 7/1/2015 6/30/2023 CIP Project Title Start Finish FY 2018 FY 2019 FY 2020 Field Equipment Capital Purchases 7/1/1996 6/30/2023 43 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 P2535 P2539 P2542 P2543 P2544 P2545 P2546 P2547 P2553 P2555 P2557 P2559 P2561 P2562 P2563 P2565 P2566 P2567 P2568 P2571 P2572 P2573 P2574 P2578 P2584 P2593 P2594 P2595 P2604 P2605 Planning Design Construction Warranty FY 2022 458/340 PRS Replacement, 1571 Melrose Ave 7/1/2017 6/30/2021 PL - 16-inch, 624 Zone, Village 3N - Heritage Road, Main St/Energy Way 1/1/2006 6/30/2024 AMR Change Out 1/1/2017 6/30/2023 458-1 Reservoir Interior/Exterior Coating & Upgrades 2/1/2021 6/30/2022 Large Meter Replacement 7/1/2016 6/30/2019 PS - 711-2 (PS 711-1 Replacement and Expansion) - 14,000 gpm 7/1/2020 6/30/2023 Res - 657-1 and 657-2 Reservoir Demolitions 7/1/2022 6/30/2025 PL - 12-Inch Pipeline Replacement, 803 Zone, Hillsdale Road 7/1/2016 3/1/2019 PL - 12-Inch Pipeline Replacement, 978 Zone, Vista Vereda 7/1/2016 6/30/2020 Datacenter Network- Data, Storage, and Infrastructure Enhancements 7/1/2018 6/30/2020 Enterprise Resource Planning (ERP) Replacement 7/1/2020 6/30/2022 1004-2 Reservoir Interior/Exterior Coating & Upgrades 1/4/2021 6/30/2022 Technology Business Processes Improvement - Enterprise Content Management System 7/1/2015 6/30/2018 803-2 Reservoir Interior/Exterior Coating & Upgrades 1/1/2019 6/30/2022 520-2 Reservoir Interior/Exterior Coating & Upgrades 1/3/2020 6/30/2022 Res - 571-1 Reservoir Cover/Liner Replacement 7/1/2015 6/30/2020 Res - 870-1 Reservoir Cover/Liner Replacement 7/1/2015 6/30/2021 Pressure Vessel Repair and Replacement Program 7/1/2015 6/30/2023 Res - 711-3 Reservoir Cover/Liner Replacement 7/1/2015 6/30/2021 Administration and Operations Parking Lot Improvements 7/1/2015 6/30/2019 520 Res Recirculation Pipeline Chemical Supply and Analyzer Feed Replacement Project 7/1/2015 6/30/2019 District Administration Vehicle Charging Stations 7/1/2014 9/30/2017 Heritage Road Bridge Replacement and Utility Relocation 7/1/2014 6/30/2023 980-1 Reservoir Interior Exterior Coating 1/1/2015 12/31/2016 980-2 Reservoir Interior/Exterior Coating 1/1/2018 6/30/2021 850-1 Reservoir Interior/Exterior Coating 1/2/2017 12/31/2020 850-2 Reservoir Interior/Exterior Coating 4/1/2016 12/31/2019 South Bay Bus Rapid Transit (BRT) Utility Relocations 7/1/2013 6/30/2021 850-3 Reservoir Interior Coating 6/30/2013 12/29/2017 458-2 Reservoir Interior & Exterior Coating & Upgrades 6/1/2013 6/29/2018 Six-Year CIP Projects Schedule Continued CIP No CIP Project Title Start FY 2023 Q1 FY 2019 FY 2020 FY 2021FinishFY 2018 44 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 P2606 P2607 P2608 P2609 P2610 P2611 P2612 P2613 P2614 P2615 P2616 P2617 P2619 P2620 P2623 R2077 R2079 R2084 R2110 R2116 R2118 R2120 R2121 R2123 R2125 R2139 R2143 S2012 S2024 S2027 Planning Design Construction Warranty FY 2019 FY 2020 FY 2021 FY 2022 FY 2023CIP No CIP Project Title Start Finish FY 2018 Q1 Six-Year CIP Projects Schedule Continued Repurpose Otay Mesa Recycled Water Lines 7/1/2016 6/30/2023 RecPRS - 927/680 PRS Improvements, Otay Lakes Road 7/1/2017 6/30/2020 RWCWRF Filtered Water Storage Tank Improvements 7/1/2015 6/30/2020 Res - 944-1 Reservoir Cover/Liner Replacement 7/1/2015 6/30/2021 San Diego County Sanitation District Outfall and RSD Outfall Replacement 7/1/2003 6/30/2025 Campo Road Sewer Main Replacement 7/1/2010 6/30/2018 RWCWRF - Filter Troughs Replacement 7/1/2017 6/30/2018 AMR Change Out 1/7/2017 6/30/2023 Rancho San Diego Pump Station Rehabilitation 7/1/2011 6/30/2021 RecPL - 14-Inch, 927 Zone, Force Main Improvements 7/1/2014 6/30/2020 Steele Canyon Sewer PS Large Solids Handling Improvements 7/1/2015 6/30/2019 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media 7/1/2004 6/30/2020 RecPS - 944-1 Optimization and Pressure Zone Modifications 7/1/2013 6/30/2019 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway 7/1/2001 12/31/2024 RecPL - 6-Inch, 450 Zone, Otay Valley Road - Otay Valley/Entertainment 7/1/2016 6/30/2021 Radio and Emergency Communication System 8/1/2017 10/5/2017 Central Area to Otay Mesa Interconnection Pipelines Combination Air/Vacuum Valve Replacements 7/1/2017 6/30/2020 Lobby Security Enhancements 7/1/2017 6/30/2018 PS - Temporary Lower Otay Pump Station Redundancy 7/1/2017 6/30/2021 PL - 12-Inch Pipeline Replacement, 803 PZ, Vista Grande 7/1/2018 6/30/2021 PL - 12-Inch Pipeline Replacement, 978 Zone, Pence Dr/Vista Sierra Dr 7/1/2017 6/30/2021 PL - 12-inch, 520 Zone, Rancho San Diego Towne Center Loop 7/1/2017 6/30/2020 485-1 Reservoir Interior/Exterior Coating 7/1/2021 6/30/2023 Quarry Road Bridge Replacement and Utility Relocation 7/1/2017 12/31/2022 PL - 12-inch, 711 Zone, Pas de Luz/Telegraph Canyon Rd 7/1/2017 12/31/2021 PL - 8-inch, 1004 Zone, Eucalyptus St, Coronado/Date/La Mesa 7/1/2018 6/30/2022 Valve Replacement Program - Phase 1 7/1/2017 6/30/2020 Douglas Ave SWA and OWD Interconnection Upgrade 7/1/2017 6/30/2020 PL - 8-inch, 850 Zone, Coronado Ave, Chestnut/Apple 7/1/2017 6/30/2021 803-2 Reservoir Repair/Replacement of Caulking and Tree Removal 7/1/2017 6/30/2020 45 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 S2033 S2043 S2044 S2045 S2046 S2047 S2048 S2049 S2050 S2051 S2053 S2054 S2061 Planning Design Construction 87 FY 2018 Projects 16 FY 2019 through FY 2023 Projects 103 FY 2022 Six-Year CIP Projects Schedule Continued FY 2023 6/30/2019 Sewer System Rehabilitation 7/1/2011 6/30/2017 Q1 RWCWRF Sludge Handling System 7/1/2013 6/30/2026 Trenchless Sewer Rehabilitation 7/1/2016 CIP No CIP Project Title Start Finish FY 2018 FY 2019 FY 2020 FY 2021 Calavo Basin Sewer Rehabilitation - Phase 3 7/1/2020 6/30/2023 Calavo Basin Sewer Rehabilitation - Phase 2 7/1/2016 6/30/2021 Rancho San Diego Basin Sewer Rehabilitation - Phase 2 7/1/2019 6/30/2024 Asset Management - Info Master Sewer Implementation 7/1/2017 6/30/2019 RWCWRF Aeration Controls Consolidation & Optimization Upgrades (S) 7/1/2017 6/30/2020 RWCWRF - Headworks Improvements 7/1/2017 6/30/2019 RWCWRF - Sedimentation Basins Weirs Replacement 7/1/2017 6/30/2019 Hillsdale Road Sewer Repairs 7/1/2016 6/30/2019 Fuerte Drive Sewer Relocation 7/1/2016 6/30/2019 RWCWRF - Aeration Panels Replacement 7/1/2016 6/30/2020 Grand Total Warranty Total CIP Projects Major CIP Projects 46 CIP#Description Cost Cat. (2) Funding Source (3) FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total P2040 Res - 1655-1 Reservoir 0.5 MG M E $ - $ - $ - $ - $ 52 $ 52 $ 104 P2083 PS - 870-2 Pump Station Replacement M R - - - - 5,000 5,000 10,000 P2466 Regional Training Facility M B/E - 1,000 1,000 1,000 1,000 1,000 5,000 P2537 Operations Yard Property Acquisition Improvements M/E B - 725 750 776 800 800 3,851 P2547 District Administration Vehicle Charging Stations M/E B/E - 700 700 700 700 700 3,500 R2084 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media M E - - 1,900 1,900 1,900 1,900 7,600 S2043 RWCWRF Sludge Handling System M/E/C B - - - 30,000 30,000 60,000 - 2,425 4,350 4,376 39,452 39,452 90,055 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total - 1,200 3,100 3,101 18,152 18,152 43,705 - 1,225 1,250 1,275 11,300 11,300 26,350 - - - - 10,000 10,000 20,000 $ - $ 2,425 $ 4,350 $ 4,376 $ 39,452 $ 39,452 $ 90,055 (1) (2) (3) Note:See pages 39-42 for complete description of CIP projects. Projected Incremental Operating Expenditures (1) E - Expansion B - Betterment R - Replacement N - New Supply The following schedule shows anticipated operating costs associated with each project in the CIP. Below is a summary of each category of new costs that will be impacted. No additional revenues are associated with the individual projects, as revenues are linked more directly to growth in water sales and capacity fee revenues. Funding Source - Some projects have multiple funding sources as indicated by a slash (/): Cost Category - Indicates maintenance cost (M), energy cost (E), or chemical cost (C), based on the project type and Engineer's estimates. O&M cost for a pump station: Total annual operating cost divided by the number of million of gallons a day (MGD) capacity in the system = O&M cost per MGD. This rate is then multiplied by the MGD capacity of the new pump station. Similarly, power cost per MGD for transmission is calculated and applied to the MGD of the new pump station. Chemical expenses are incurred for pumping at the well sites. All estimated costs are increased annually for inflation. Projected Incremental Operating Expenditures (operating cost) or O&M includes labor, benefits, materials, and O&M cost for pipes: Total annual operating cost divided by the number of feet of pipe in the system = O&M cost to maintain a foot of pipe. This rate is then multiplied by the number of feet in new pipeline, and is increased annually for inflation. Cost Category Each of the capital purchases and other types of assets has its own unique O&M cost Maintenance (M) Energy (E) Chemical (C) Total Operating Budget Cost Impact CIP Justification and Impact on Operating Budget O&M cost for a reservoir: Total annual operating cost divided by the number of million gallons (MG) of storage capacity in the system. This rate per MG is then multiplied by the MG capacity of the new reservoir. Reservoirs require chemical treatment; therefore, the chemical cost per MG is estimated and applied to the future operating cost. Both O&M and chemical costs are increased annually for inflation. 47 This page intentionally left blank 48 CIP Project Sheet Description The following pages describe each information item on the individual CIP project sheets included in this section. CIP Number: The CIP project number for all projects is assigned by the Engineering Project Manager, and is a unique identifying code on all District records for the specified project. Project Title: Project titles follow a set format as described herein. The type of project should be identified first. For example, if a project were a 711 Pressure Zone 24-inch pipeline, the title would read “PL - 24-Inch, 711 Zone, Location - From A to B.” Pump stations and reservoirs are identified similarly with abbreviations for type and size. Director Division: All projects are located within a Board of Director’s division boundary unless they apply to the entire District or are outside of the District boundaries. The Director division where the majority of the physical project is located is listed. If it is a District-wide project it is listed as “District-wide.” If it is outside the District boundary it is listed as “None.” Project Manager: The person responsible for managing the project from inception through completion. I.D. Location: Most projects are located within one or more improvement districts. The I.D. location listed is where the majority of the physical project is located. However, projects located in portions of the District which have not yet been annexed into an improvement district are listed as “None.” Original Approved Date: The date the project was originally approved with budget expenditures for the corresponding fiscal year by the Board of Directors. Priority: The priority of the project is listed in this field as one of the following: 1. HIGH: Safety, restoration of service to customers, obligation that requires immediate action, directed by the Board of Directors, and/or critical system need. 2. MEDIUM: Upgrade of system or expansion requirement to maintain system reliability not critical. Identified through planning effort as required within next few fiscal years. 3. LOW: Identified through planning effort as required in future years to support development; not anticipated in the immediate future. 4. VERY LOW: Requirement may have low probability of need in the future. Related CIP Projects: A maximum of three CIP project numbers that affect the scheduling and/or related to the subject project and/or could provide important information. Budget Amount: The estimated budget includes all costs needed to complete a project including land, right-of-way, consultants, contractors, District staff time, etc. All prior years’ costs are part of the total cost and dollars are rounded up to the nearest $1,000. 49 CIP Project Sheet Description Description of Project: A brief description of a project which typically includes size, length, capacity, etc. Justification of Project: A brief explanation of why a project is required which addresses flexibility, reliability, water quality, safety, contractual obligation, immediate growth, etc., as appropriate. Comments: Pertinent information that should be known about a project that is not shown elsewhere on the project sheet, including details of funding sources, including grant funding or contributions from other agencies. Funding Detail: The funding sources are listed along with the percentage of distribution to expansion, betterment, and/or replacement. Expenditure Schedule: The breakdown of a project’s expenditures by fiscal year – prior years’ cost along with a six-year budget schedule. Included in each year are all costs to complete the work scheduled in that year rounded up to the nearest $1,000. Project Schedule: The schedule of the primary project phase and estimated cost by the phases of planning, design, and construction shown with the estimated start date (month/year), finish date (month/year). The schedule time frames and estimated cost for each major phase of the project, correspond with the expenditure schedule information. Projected Incremental Operation Expenditures Schedule: To determine the cost to maintain these new assets, the District looks at the cost of maintaining similar assets through the Infrastructure Management System and financial system. Costs are tracked by three main infrastructure asset groups of pipes, pump stations, and reservoirs, as well as capital purchases and other types. Pipes typically have only operation and maintenance (O&M) costs associated with them, pump stations have O&M as well as power cost, and reservoirs have O&M and chemical cost. Each of the capital purchases and other types has its own unique O&M cost. Project Location: A vicinity map is drawn in AutoCAD format using the GIS database as the foundation showing the approximate location and limits of a project within the District. Some projects do not have a specific location. In this case, a map of the entire District will then be shown as the project location. OWD Map Book: The page in the District’s facility map book where a project is primarily located. Some projects do not have a specific location in which case the words “district-wide” will be shown. Submitted By: The project manager who originally submitted or the project manager who revised the project sheet along with the date of submittal or last revision date of the CIP project sheet. 50 P2040 P2083 P2174 P2267 P2282 P2286 P2382 P2400 P2405 P2430 P2451 P2453 P2460 P2485 P2493 P2494 P2500 P2504 P2507 P2508 P2516 P2518 P2520 P2521 P2529 P2530 P2531 P2532 P2533 P2534 P2535 P2539 P2542 P2543 P2544 P2545 P2546 P2547 P2553 District Administration Vehicle Charging Stations 129 Heritage Road Bridge Replacement and Utility Relocation 131 980-1 Reservoir Interior Exterior Coating 125 980-2 Reservoir Interior/Exterior Coating 127 850-1 Reservoir Interior/Exterior Coating 121 850-2 Reservoir Interior/Exterior Coating 123 South Bay Bus Rapid Transit (BRT) Utility Relocations 117 850-3 Reservoir Interior Coating 119 458-2 Reservoir Interior & Exterior Coating & Upgrades 115 1200-1 Reservoir Interior & Exterior Coating 111 978-1 Reservoir Interior & Exterior Coating 113 944-1 Reservoir Interior & Exterior Coating 107 944-2 Reservoir Interior & Exterior Coating 109 711-2 Reservoir Interior & Exterior Coating 103 711-1 Reservoir Interior & Exterior Coating 105 Motorola Mobile Radio Upgrade 99 Large Meter Vault Upgrade Program 101 PL - 12-Inch, 640 Zone, Jamacha Road - Darby/Osage 95 803-3 Reservoir Interior/Exterior Coating 97 Pipeline Cathodic Protection Replacement Program 93 Regulatory Site Access Road and Pipeline Relocation 89 East Palomar Street Utility Relocation 91 Multiple Species Conservation Plan 85 Padre Dam - Otay Interconnection Dehesa Valley 87 SCADA - Infrastructure and Communications Replacement 81 624-2 Reservoir Interior/Exterior Coating 83 77 I.D. 7 Trestle and Pipeline Demolition 79 PL - 20-inch, 980 Zone, Proctor Valley Road – Village 14 Phase 1 73 Otay Mesa Desalination Conveyance and Disinfection System 75 PL - 20-Inch Pipeline Replacement, 711 Zone, Otay Lakes Road - at Santa Paula 69 PL - 624/340 PRS, Paseo Ranchero and Otay Valley Road 71 Res - 1655-1 Reservoir 0.5 MG 55 CIP Project Index CIP No CIP Project Title Page No Field Equipment Capital Purchases 65 Safety and Security Improvements 67 36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations 61 Vehicle Capital Purchases 63 PS - 870-2 Pump Station Replacement 57 PS - 1090-1 Pump Station Replacement (400 gpm)59 SR-11 Utility Relocations 51 P2555 P2557 P2559 P2561 P2562 P2563 P2565 P2566 P2567 P2568 P2571 P2572 P2573 P2574 P2578 P2584 P2593 P2594 P2595 P2604 P2605 P2606 P2607 P2608 P2609 P2610 P2611 P2612 P2613 P2614 P2615 P2616 P2617 P2619 P2620 P2623 R2077 R2079 R2084 R2110 CIP No CIP Project Title Page No RecPS - 944-1 Optimization and Pressure Zone Modifications 211 RecPL - 6-Inch, 450 Zone, Otay Valley Road - Otay Valley/Entertainment 207 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media 209 Central Area to Otay Mesa Interconnection Pipelines Combination Air/Vacuum Valve 203 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway 205 PS - Temporary Lower Otay Pump Station Redundancy 199 Radio and Emergency Communication System 201 PL - 12-Inch Pipeline Replacement, 978 Zone, Pence Dr/Vista Sierra Dr 195 Lobby Security Enhancements 197 485-1 Reservoir Interior/Exterior Coating 191 PL - 12-Inch Pipeline Replacement, 803 PZ, Vista Grande 193 PL - 12-inch, 711 Zone, Pas de Luz/Telegraph Canyon Rd 187 PL - 12-inch, 520 Zone, Rancho San Diego Towne Center Loop 189 Valve Replacement Program - Phase 1 183 Quarry Road Bridge Replacement and Utility Relocation 185 PL - 8-inch, 850 Zone, Coronado Ave, Chestnut/Apple 179 PL - 8-inch, 1004 Zone, Eucalyptus St, Coronado/Date/La Mesa 181 803-2 Reservoir Repair/Replacement of Caulking and Tree Removal 175 Douglas Ave SWA and OWD Interconnection Upgrade 177 458/340 PRS Replacement, 1571 Melrose Ave 173 PL - 16-inch, 624 Zone, Village 3N - Heritage Road, Main St/Energy Way 169 AMR Change Out 171 458-1 Reservoir Interior/Exterior Coating & Upgrades 165 Large Meter Replacement 167 PS - 711-2 (PS 711-1 Replacement and Expansion) - 14,000 gpm 161 Res - 657-1 and 657-2 Reservoir Demolitions 163 PL - 12-Inch Pipeline Replacement, 803 Zone, Hillsdale Road 157 PL - 12-Inch Pipeline Replacement, 978 Zone, Vista Vereda 159 Datacenter Network- Data, Storage, and Infrastructure Enhancements 153 Enterprise Resource Planning (ERP) Replacement 155 1004-2 Reservoir Interior/Exterior Coating & Upgrades 149 Technology Business Processes Improvement - Enterprise Content Management System 151 803-2 Reservoir Interior/Exterior Coating & Upgrades 145 520-2 Reservoir Interior/Exterior Coating & Upgrades 147 Res - 571-1 Reservoir Cover/Liner Replacement 141 Res - 870-1 Reservoir Cover/Liner Replacement 143 Pressure Vessel Repair and Replacement Program 137 Res - 711-3 Reservoir Cover/Liner Replacement 139 Administration and Operations Parking Lot Improvements 133 520 Res Recirculation Pipeline Chemical Supply and Analyzer Feed Replacement Project 135 CIP Project Index 52 R2116 R2118 R2120 R2121 R2123 R2125 R2139 R2143 S2012 S2024 S2027 S2033 S2043 S2044 S2045 S2046 S2047 S2048 S2049 S2050 S2051 S2053 S2054 S2061 Calavo Basin Sewer Rehabilitation - Phase 3 257 RWCWRF Aeration Controls Consolidation & Optimization Upgrades (S)259 RWCWRF - Headworks Improvements 253 RWCWRF - Sedimentation Basins Weirs Replacement 255 Calavo Basin Sewer Rehabilitation - Phase 2 249 Rancho San Diego Basin Sewer Rehabilitation - Phase 2 251 Asset Management - Info Master Sewer Implementation 245 Hillsdale Road Sewer Repairs 247 Fuerte Drive Sewer Relocation 241 RWCWRF - Aeration Panels Replacement 243 RWCWRF Sludge Handling System 237 Trenchless Sewer Rehabilitation 239 Sewer System Rehabilitation 235 Campo Road Sewer Main Replacement 231 Rancho San Diego Pump Station Rehabilitation 233 AMR Change Out 227 San Diego County Sanitation District Outfall and RSD Outfall Replacement 229 RecPRS - 927/680 PRS Improvements, Otay Lakes Road 223 RWCWRF - Filter Troughs Replacement 225 Res - 944-1 Reservoir Cover/Liner Replacement 219 Repurpose Otay Mesa Recycled Water Lines 221 Steele Canyon Sewer PS Large Solids Handling Improvements 215 RWCWRF Filtered Water Storage Tank Improvements 217 RecPL - 14-Inch, 927 Zone, Force Main Improvements 213 CIP Project Index CIP No CIP Project Title Page No 53 This page intentionally left blank 54 P2040Res - 1655-1 Reservoir 0.5 MG Kevin Cameron 8/19/1992 5 22 3 $3,400,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for construction of a 0.5 million gallon reservoir and approximately 1,500 feet of 12-inch pipeline to connect to the existing system at Prisilla Drive. These improvements are located within the Rancho Jamul Estates area. JUSTIFICATION OF PROJECT: The project will increase both system reliability and service capabilities, and provide adequate fire protection for the Rancho Jamul Estates area within the 1655 Pressure Zone. The existing system is currently served with a hydropneumatic pump station. COMMENTS: In early 2000, the project was designed to 90%, and due to the economy, the project was put on hold. The overall budget was increased to account for the spending done prior to FY 2015. The project budget increased $1.2 Million after receiving a preliminary cost estimate from a concrete tank manufacturer and updating cost estimates from the estimate done in 2000. The concrete tank will have to be a Type I due to location and steep grades. Also, added updated costs for Reservoir security items. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $20 $50 $1,175 $1,610 $20 $20 $3,400 PRIOR YEARS: TOTAL $505 OTAY WATER DISTRICT CAPITAL IMPROVEMENT PROGRAM 55 P2040 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2015 9/30/2018 10/1/2018 2/7/2020 $160 $870 PROJECT PHASE: 2/10/2020 6/30/2023 $2,370 PROJECT LOCATION:OWD Map Book:310 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 56 P2083PS - 870-2 Pump Station Replacement Jeff Marchioro 5/17/1995 P2451 2 22 1 $18,750,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the construction of a new pump station to replace the existing Low Head and High Head Pump Stations. JUSTIFICATION OF PROJECT: The two existing Pump Stations have reached the end of their useful lives. COMMENTS: Increased overall CIP budget from $17M to $18.75M for FY2018 budget cycle to add reservoir recirculation system piping modification, updated Carollo construction cost estimate, and construction contract allowances. Additionally, wetlands mitigation was determined to be required. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $4,000 $10,550 $1,850 $50 $50 $0 $18,750 PRIOR YEARS: TOTAL $2,250 OTAY WATER DISTRICT CAPITAL IMPROVEMENT PROGRAM 57 P2083 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2013 9/1/2013 9/1/2013 5/1/2017 $700 $1,550 PROJECT PHASE: 5/1/2017 5/1/2022 $16,500 PROJECT LOCATION:OWD Map Book:055 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $5,000 $5,000 $10,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:5/4/2017Steve Beppler 58 P2174PS - 1090-1 Pump Station Replacement (400 gpm) Jeff Marchioro 5/23/2016 P2176 5 22 2 $2,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the construction of a new Pump Station to replace the existing Pump Station. Improve Pump Station to include fire pump (1,500 gpm) and closed zone capability to eliminate the need for redundant 1090 Pressure Zone Reservoir (CIP P2176). JUSTIFICATION OF PROJECT: The existing Pump Station, originally constructed in 1962, has reached the end of its useful life. COMMENTS: Overall budget increased to match 2015 Water Facilities Master Plan Update. Implementation delayed to match prioritization with other projects. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $1 $150 $200 $1,100 $1,000 $45 $2,500 PRIOR YEARS: TOTAL $4 59 P2174 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 4/30/2019 5/1/2019 4/30/2020 $150 $300 PROJECT PHASE: 5/1/2020 6/30/2023 $2,050 PROJECT LOCATION:OWD Map Book:320 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 60 P226736-Inch Main Pumpouts and Air/Vacuum Ventilation Installations Jeff Marchioro 6/3/1996 3 22 2 $700,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the installation of ventilation equipment on the existing pumpout and air/vacuum vaults on the 36-inch transmission main from the San Diego County Water Authority Otay FCF No. 11 to the Regulatory Site. This project also includes upsizing the existing 2-inch air/vacuum valves to 6-inch. JUSTIFICATION OF PROJECT: The vault openings do not stay in place when refilling because they lack ventilation. By installing vents in these vaults, the lids will stay in place, thus eliminating a safety hazard. Draining and filling the 36-inch main at higher flow rates is required to return the system to service in shorter periods of time. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $10 $10 $0 $0 $0 $0 $700 PRIOR YEARS: TOTAL $680 61 P2267 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 4/1/2015 9/7/2016 $0 $60 PROJECT PHASE: 9/7/2016 6/30/2018 $640 PROJECT LOCATION:OWD Map Book:198 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:2/17/2017Jeff Marchioro 62 P2282Vehicle Capital Purchases Doug Rahders 6/3/1996 0 District Wide 1 $5,491,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the capital purchase of various vehicles for daily Otay Water District functions. JUSTIFICATION OF PROJECT: Replacements or newly acquired vehicles will be used for operational and administrative functions throughout the entire Otay Water District. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $363 $240 $187 $236 $253 $250 $5,175 PRIOR YEARS: TOTAL $3,646 63 P2282 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 12/1/2000 6/30/2028 $5,491 $0 PROJECT PHASE: $0 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 64 P2286Field Equipment Capital Purchases Doug Rahders 6/3/1996 0 District Wide 1 $1,746,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for capital purchases of various pieces of field equipment used for daily Otay Water District functions. JUSTIFICATION OF PROJECT: Replacements or new acquisitions of field equipment will be used for operational functions throughout the entire Otay Water District. COMMENTS: Budget increased from $1,634,000 to $1,746,000 to include purchases through FY2023. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $72 $50 $55 $60 $60 $63 $1,746 PRIOR YEARS: TOTAL $1,386 OTAY WATER DISTRICT CAPITAL IMPROVEMENT PROGRAM 65 P2286 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/1996 6/30/2023 $1,746 $0 PROJECT PHASE: $0 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 66 P2382Safety and Security Improvements Kent Payne 6/5/2002 0 District Wide 1 $3,251,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the installation and replacement of the physical security burglar alarm systems to Digital Monitoring Systems (DMP) and associated security components at 23 District facilities. This is to ready sites for enterprise security and access control management software "ENTRE." JUSTIFICATION OF PROJECT: This project is to improve the security of the Otay Water District facilities by installing and upgrading the hardware and software required to provide access control management, intrusion detection and response, and to ready the facilities for future evaluation of video camera verification systems. Although existing facilities are relatively safe and secure, the federal government has recommended that security to water systems be improved. COMMENTS: Increased budget for FY 2019 by $175K to reflect addition of security improvements at RWCWRF for new laser scan security system with cameras and alarms. FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $150 $325 $0 $0 $0 $0 $3,251 PRIOR YEARS: TOTAL $2,776 67 P2382 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2002 6/30/2019 9/1/2003 6/30/2019 $62 $231 PROJECT PHASE: 1/1/2004 6/30/2019 $2,958 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 68 P2400PL - 20-Inch Pipeline Replacement, 711 Zone, Otay Lakes Road - at Santa Paula Jeff Marchioro 1 22 2 $2,280,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to replace 3,700 feet of 16-inch asbestos concrete water main in Otay Lakes Road at Santa Paula. JUSTIFICATION OF PROJECT: The existing water main bottlenecks from 20-inch down to 16-inch. The existing 16-inch pipe causes high head loss at peak flow. COMMENTS: Overall budget increased in FY 2018 to match 2015 Water Facilities Master Plan (WFMP) Update. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %69 %0 %69 % Betterment ID 22 0 %31 %0 %0 %31 % TOTAL:0 %31 %69 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $150 $350 $1,780 $0 $2,280 PRIOR YEARS: TOTAL $0 69 P2400 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2019 6/30/2020 7/1/2020 6/30/2021 $150 $350 PROJECT PHASE: 7/1/2021 6/30/2022 $1,780 PROJECT LOCATION:OWD Map Book:130 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 70 P2405PL - 624/340 PRS, Paseo Ranchero and Otay Valley Road Kevin Cameron 5/23/2016 2 22 2 $650,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the construction of approximately 1,200 feet of 12-inch pipeline in the 340 Pressure Zone in Otay Valley Road and the 16-inch pipeline in Otay Valley Road. Construction of a pressure reducing station between the 624/340 Pressure Zone near the intersection of Otay Valley Road/Main Street and Heritage Road. JUSTIFICATION OF PROJECT: This will provide a redundant service connection to the 340 Pressure Zone. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $5 $50 $500 $85 $650 PRIOR YEARS: TOTAL $0 71 P2405 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 6/30/2017 7/1/2017 10/31/2021 $5 $100 PROJECT PHASE: 11/1/2021 6/30/2023 $545 PROJECT LOCATION:OWD Map Book:51 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 72 P2430PL - 20-inch, 980 Zone, Proctor Valley Road ±Village 14 Phase 1 Kevin Cameron 5/23/2005 5 22 2 $2,040,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 12,400 feet of pipeline oversize from 16-inch to 20-inch pipeline within the 980 Pressure Zone in Proctor Valley Road. Project to be constructed by developer, with reimbursement at actual cost of oversize portion per Board policy. JUSTIFICATION OF PROJECT: Project is an identified CIP in the Water Facilities Master Plan. COMMENTS: Reimbursements will be phased with the construction of Proctor Valley Road. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $5 $5 $5 $10 $35 PRIOR YEARS: TOTAL $0 73 P2430 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 1/1/2018 6/30/2023 7/1/2023 6/30/2024 $40 $100 PROJECT PHASE: 7/1/2024 6/30/2026 $1,900 PROJECT LOCATION:OWD Map Book:146 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 74 P2451Otay Mesa Desalination Conveyance and Disinfection System Bob Kennedy 5/23/2006 P2083 2 22 2 $30,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: The Otay Water District could potentially receive a potable water supply source from the planned Rosarito Desalination Facility via a conveyance system, pumping facilities, and disinfection system. JUSTIFICATION OF PROJECT: The concept could provide for an independent water source to the Otay Water District. COMMENTS: Original Budget amount approved 5/23/2006 for $1,000,000. Budget increase approved 6/25/2008 to $5,000,000. On 5/21/2009, the Budget was increased to $30,000,000 ($1,000,000 for UV Treatment, $9,000,000 for Pump Station, and $20,000,000 for Conveyance Pipeline). FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %69 %0 %0 %69 % New Water Supply Fee Projects 0 %0 %0 %31 %31 % TOTAL:0 %69 %0 %31 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $50 $100 $100 $100 $100 $100 $4,300 PRIOR YEARS: TOTAL $3,750 75 P2451 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2006 6/30/2024 7/1/2024 6/30/2026 $4,100 $4,000 PROJECT PHASE: 7/1/2026 6/30/2029 $21,900 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 76 P2453 SR-11 Utility Relocations Jeff Marchioro 5/23/2006 2 22 1 $4,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for all utility relocations required due to construction of the SR-11 on the Otay Mesa. Facility relocations vary in size from 8-inch to 24-inch. Both the potable and recycled water systems are impacted. JUSTIFICATION OF PROJECT: Caltrans will construct the SR-11, which will result in utility conflicts with existing Otay Water District facilities at various locations. In most cases, the Otay Water District does have prior and superior rights. The facilities must be relocated prior to Caltrans' construction of the SR-11. The cost of the facilities relocations that have prior rights will be reimbursed by Caltrans. COMMENTS: Timing of projects adjusted in FY 2017 budget, no change to overall project cost. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $50 $50 $700 $1,000 $452 $100 $4,000 PRIOR YEARS: TOTAL $1,648 77 P2453 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2006 6/1/2016 7/1/2009 6/30/2022 $50 $500 PROJECT PHASE: 1/8/2014 6/30/2023 $3,450 PROJECT LOCATION:OWD Map Book:5 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 78 P2460I.D. 7 Trestle and Pipeline Demolition Stephen Beppler 1 22 2 $600,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the steel trestle demolition and removal of a pipeline. The 1960's steel trestle 24-inch pipeline crossing of Otay River was replaced by the Central Area and Otay Mesa Interconnection pipeline in 2001. The trestle also carries a high pressure gas line that supplies the 870-1 Pump Station that prevented the trestle from being demolished previously. SDG&E is proposing to abandon this gas line in 2017 and replacing it with a feed from the south. JUSTIFICATION OF PROJECT: The existing pipeline is no longer in service and should be removed to address liability concerns. The Central Area - Otay Mesa Interconnection Pipeline supplies water to the Otay Mesa System. COMMENTS: FY 2017 scope is to identify the project constraints that will drive the demolition costs, including environmental factors, access limitations, and demolition alternatives. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $40 $530 $20 $0 $0 $600 PRIOR YEARS: TOTAL $5 79 P2460 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 1/31/2017 2/1/2017 8/31/2019 $25 $25 PROJECT PHASE: 9/1/2019 6/30/2021 $550 PROJECT LOCATION:OWD Map Book:71 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 80 P2485SCADA - Infrastructure and Communications Replacement Michael Kerr 5/21/2009 0 District Wide 1 $2,328,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will replace the existing SCADA software and radio communication system and install fuel level transmitters on all diesel fuel tanks. A battery backup system will be installed at remote SCADA/radio sites without emergency power generators. JUSTIFICATION OF PROJECT: Beginning in 2012, the vendor no longer upgrades or supports the existing system. The radio equipment needs replacement to allow for increased bandwidth capability to increase security systems functionality. The fuel level transmitters on all diesel fuel tanks and remote SCADA monitoring will provide supervisors with real-time fuel levels to monitor available runtime on stand-by engines during extended power outages. The battery backup system will provide continuous communications and SCADA monitoring and control for 3 days if the District lost power at sites without emergency power generators. COMMENTS: Going into FY 2018 and beyond, the anticipated expenditures are for the following: Work also includes completing the installation of new UPS and cooling system for the support of the District¶s SCADA technology infrastructure - $120K Staff also are including sites that were unanticipated during initial recommended list of sites in support of the SCADA systems data and security communications services. Staff identified 3 sites that required extensive work (power panel, conduits, circuits, and cabinet installation) - $55K Emergency Operations Center ±$22K Replacement of PLC¶s (facility-wide) throughout FY 2021:FY 2018 ($85K)FY 2019 ($84K)FY 2020 ($85K)FY 2021 ($24K) FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $181 $185 $85 $24 $0 $0 $2,328 PRIOR YEARS: TOTAL $1,853 81 P2485 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2009 6/30/2021 $2,328 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 82 P2493624-2 Reservoir Interior/Exterior Coating Kevin Cameron 5/21/2009 4 22 1 $1,580,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 624-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the most recent reservoir assessment report dated August 8, 2008, the 624-2 Reservoir interior coating is in relatively poor condition and is in need of replacement. Based on the FY 2012 Corrosion Report for Reservoir Coatings, the exterior was scheduled to be replaced in FY 2013. COMMENTS: Project budget reduced $30K in FY 2018 budget. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $5 $0 $0 $0 $1,580 PRIOR YEARS: TOTAL $1,565 83 P2493 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 8/1/2010 9/1/2010 12/31/2013 $5 $95 PROJECT PHASE: 1/8/2014 6/30/2017 $1,480 PROJECT LOCATION:OWD Map Book:130 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 84 P2494Multiple Species Conservation Plan Lisa Coburn-Boyd 5/21/2009 P2495 0 District Wide 1 $950,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to develop a plan to streamline the environmental permitting processes for the Capital Improvement Program projects to be constructed. JUSTIFICATION OF PROJECT: The project will save time and money when compared to environmental permitting each Capital Improvement Program project individually. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $30 $0 $0 $0 $0 $0 $950 PRIOR YEARS: TOTAL $920 85 P2494 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 6/30/2018 $950 $0 PROJECT PHASE: $0 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:2/16/2017Lisa Coburn-Boyd 86 P2500Padre Dam - Otay Interconnection Dehesa Valley Stephen Beppler 5 22 1 $240,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Add an interconnection of the potable water system with Padre Dam MWD to provide a redundant supply to the District's most northeastern areas in the event of an emergency. The facility will include a meter, vault, telemetry, and other interconnection appurtenances. JUSTIFICATION OF PROJECT: Adds a redundant water supply to the District in the event of an emergency. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %69 %0 %0 %69 % Expansion 31 %0 %0 %0 %31 % TOTAL:31 %69 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $60 $5 $5 $5 $5 $60 $140 PRIOR YEARS: TOTAL $0 87 P2500 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2022 7/1/2017 6/30/2022 $10 $60 PROJECT PHASE: 7/1/2022 6/30/2025 $170 PROJECT LOCATION:OWD Map Book:381 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 88 P2504Regulatory Site Access Road and Pipeline Relocation Kevin Cameron 5/17/2010 P2466 5 22 1 $900,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to improve the existing access road from the proposed sheriff substation site to the Regulatory Reservoir Site. JUSTIFICATION OF PROJECT: Improving the existing access road will provide for increased safety and all weather permanent access to the Regulatory Reservoir Site. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %50 %0 %50 % Betterment ID 22 0 %50 %0 %0 %50 % TOTAL:0 %50 %50 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $20 $50 $50 $1 $1 $10 $462 PRIOR YEARS: TOTAL $330 OTAY WATER DISTRICT CAPITAL IMPROVEMENT PROGRAM 89 P2504 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 9/1/2010 10/1/2010 12/31/2017 $85 $275 PROJECT PHASE: 1/1/2018 6/30/2025 $540 PROJECT LOCATION:OWD Map Book:331 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/28/2017Bob Kennedy 90 P2507East Palomar Street Utility Relocation Kevin Cameron 5/17/2010 2 22 2 $735,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the utility relocations due to construction improvements to I-805 near East Palomar Street. Both the existing potable and recycled water systems will be impacted. JUSTIFICATION OF PROJECT: Caltrans will be making improvements to I-805 that will result in conflicts with existing pipelines. Project funds reimbursement to Caltrans. COMMENTS: Project budget reduced $150K in FY 2018. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $0 $0 $0 $0 $735 PRIOR YEARS: TOTAL $725 91 P2507 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 12/1/2010 1/1/2011 12/1/2012 $5 $245 PROJECT PHASE: 1/1/2013 6/30/2017 $485 PROJECT LOCATION:OWD Map Book:80 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 92 P2508Pipeline Cathodic Protection Replacement Program Jeff Marchioro 5/17/2010 0 District Wide 1 $725,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement and repairs of existing cathodic protection systems on various pipelines. JUSTIFICATION OF PROJECT: The ongoing cathodic protection program efforts have identified various pipelines for anode replacement, cathodic test station repairs, installation of isolation kits, and repair of existing anode beds. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $100 $1 $1 $248 $0 $0 $725 PRIOR YEARS: TOTAL $375 93 P2508 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 6/30/2016 7/1/2014 6/30/2018 $50 $100 PROJECT PHASE: 10/1/2014 6/30/2021 $575 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:2/27/2017Jeff Marchioro 94 P2516PL - 12-Inch, 640 Zone, Jamacha Road - Darby/Osage Jeff Marchioro 5/23/2016 3 22 3 $900,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for construction of approximately 1,250 feet of 12-inch pipeline in Jamacha Road and Osage Drive in the 640 Pressure Zone. JUSTIFICATION OF PROJECT: The existing pipelines are located in easements in the side yards of homes. The pipelines are a risk and liability to the District if they were to fail. COMMENTS: Overall project budget increased in FY 2018 to match 2015 Water Facilities Master Plan. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $75 $100 $725 $0 $900 PRIOR YEARS: TOTAL $0 95 P2516 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2019 6/30/2020 7/1/2020 6/30/2021 $75 $100 PROJECT PHASE: 7/1/2021 6/30/2022 $725 PROJECT LOCATION:OWD Map Book:301 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 96 P2518803-3 Reservoir Interior/Exterior Coating Kevin Cameron 5/15/2012 5 22 2 $685,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior and exterior coating of the 803-3 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2010 Cathodic Assessment Report, the 803-3 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: Project complete. Project to be suspended until warranty inspection in 2017. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $0 $0 $0 $0 $685 PRIOR YEARS: TOTAL $675 97 P2518 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 9/1/2012 10/1/2012 12/1/2013 $10 $65 PROJECT PHASE: 1/1/2013 7/31/2018 $610 PROJECT LOCATION:OWD Map Book:370 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 98 P2520Motorola Mobile Radio Upgrade Jose Martinez 5/16/2011 0 District Wide 1 $120,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for Motorola radio upgrades which involves three components: radio repeater upgrade, portable and base unit upgrades, and vehicle mobile radio upgrades. JUSTIFICATION OF PROJECT: The existing Motorola radio equipment is an essential part of the District's Emergency Response Program. A recent assessment of the radio equipment has determined that the equipment has reached the end of its useful life and needs upgrades. COMMENTS: The remaining work includes adding some additional VHF radios at pump stations that are not able to have a copper telephone (red phone) as well as augment the EOC and some management with RCS 800 MHZ radios. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $30 $0 $0 $0 $0 $0 $120 PRIOR YEARS: TOTAL $90 99 P2520 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 8/1/2011 6/30/2018 $120 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 100 P2521Large Meter Vault Upgrade Program Andrea Carey 5/16/2011 0 District Wide 1 $620,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the retrofit and upgrade of approximately 50 large meter vaults to either above ground conditions or eliminate the confined space depth. JUSTIFICATION OF PROJECT: The existing large meters are installed in below grade vaults which create increased costs and safety issues due to confined space requirements. Some of the existing below grade systems are subject to flooding and create corrosive environments. COMMENTS: This is a re-activation of a previous CIP that incurred about $220K in costs through FY 2014. Current scope of work cost is $400K over 4 years, starting in FY 2017. Staff will be looking at vaults again to see if additional meters can be brought above ground or retrofits done to eliminate the confined space requirement. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $25 $25 $100 $100 $50 $0 $620 PRIOR YEARS: TOTAL $320 101 P2521 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $220 $0 PROJECT PHASE: 8/1/2016 6/30/2022 $400 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 102 P2529711-2 Reservoir Interior & Exterior Coating Kevin Cameron 6/3/2015 P2530 1 22 2 $820,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 711-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2011 Cathodic Assessment Report, the 711-2 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: Budget decreased from $840K to $820K in FY 2018. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $0 $0 $0 $0 $820 PRIOR YEARS: TOTAL $810 103 P2529 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/1/2015 8/31/2015 9/1/2015 12/31/2015 $10 $65 PROJECT PHASE: 1/1/2016 12/31/2018 $745 PROJECT LOCATION:OWD Map Book:131 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 104 P2530711-1 Reservoir Interior & Exterior Coating Kevin Cameron 6/3/2015 P2529 1 22 2 $980,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 711-1 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2011 Cathodic Assessment Report, the 711-1 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $0 $0 $0 $0 $980 PRIOR YEARS: TOTAL $970 105 P2530 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/1/2015 8/31/2015 9/1/2015 12/31/2015 $10 $65 PROJECT PHASE: 1/1/2016 12/31/2018 $905 PROJECT LOCATION:OWD Map Book:131 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:3/24/2017Bob Kennedy 106 P2531944-1 Reservoir Interior & Exterior Coating Kevin Cameron 5/19/2014 P2532 5 22 1 $345,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 944-1 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2011 Cathodic Assessment Report, the 944-1 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: Budget decreased from $410K to $345K in FY 2018. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $0 $0 $0 $0 $345 PRIOR YEARS: TOTAL $335 107 P2531 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 5/1/2014 6/30/2014 7/1/2014 12/30/2014 $10 $30 PROJECT PHASE: 12/31/2014 6/29/2018 $305 PROJECT LOCATION:OWD Map Book:322 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 108 P2532944-2 Reservoir Interior & Exterior Coating Kevin Cameron 5/19/2014 P2531 5 22 2 $960,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 944-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2011 Cathodic Assessment Report, the 944-2 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: Budget decreased from $1.05M to $960K in FY 2018. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $10 $0 $0 $0 $0 $960 PRIOR YEARS: TOTAL $945 109 P2532 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 5/1/2014 6/30/2014 7/1/2014 10/31/2014 $10 $45 PROJECT PHASE: 12/31/2014 6/29/2018 $905 PROJECT LOCATION:OWD Map Book:322 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 110 P25331200-1 Reservoir Interior & Exterior Coating Kevin Cameron 6/3/2015 5 22 2 $810,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 1200-1 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2011 Cathodic Assessment Report, the 1200-1 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: Budget increased from $565K to $810K in FY 2018 to reflect latest bid results and include structural improvements required on many tanks recently recoated. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $10 $745 $5 $45 $0 $0 $810 PRIOR YEARS: TOTAL $5 111 P2533 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/1/2016 7/31/2017 8/3/2017 3/2/2018 $20 $60 PROJECT PHASE: 3/5/2018 6/30/2020 $730 PROJECT LOCATION:OWD Map Book:369 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 112 P2534978-1 Reservoir Interior & Exterior Coating Kevin Cameron 6/3/2015 5 22 2 $650,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 978-1 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2011 Cathodic Assessment Report, the 978-1 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: Budget decreased from $715K to $650K in FY 2018. The tank was built in 1959. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $10 $5 $5 $5 $0 $0 $650 PRIOR YEARS: TOTAL $625 113 P2534 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/2/2016 7/29/2016 8/1/2016 10/5/2016 $10 $60 PROJECT PHASE: 10/6/2016 9/30/2017 $580 PROJECT LOCATION:OWD Map Book:378 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 114 P2535458-2 Reservoir Interior & Exterior Coating & Upgrades Kevin Cameron 5/15/2012 2 22 2 $810,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 458-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2011 Cathodic Assessment Report, the 458-2 Reservoir interior coating is in relatively poor condition and is in need of replacement. The exterior coating on the roof is failing and in need of replacement. COMMENTS: Budget decreased from $885K to $810K in FY 2018. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $0 $0 $0 $0 $810 PRIOR YEARS: TOTAL $800 115 P2535 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/1/2013 9/30/2013 10/1/2013 12/31/2014 $10 $65 PROJECT PHASE: 1/1/2015 6/29/2018 $735 PROJECT LOCATION:OWD Map Book:66 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 116 P2539South Bay Bus Rapid Transit (BRT) Utility Relocations Kevin Cameron 5/19/2014 1 22 1 $1,090,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for all utility relocations required due to construction of South Bay BRT. Facility relocations vary in size and they impact both the potable and recycled water systems. JUSTIFICATION OF PROJECT: Project improvements will affect the locations of some OWD facilities in streets in Chula Vista. Engineering/staff time will be needed to review the design drawings and identify any OWD facilities which will need relocation or vertical adjustment. A construction budget is also needed for the work in relocating and adjusting these facilities. COMMENTS: Budget increased from $940K to $1.09M in FY 2018 to reflect actual costs encountered to date and remaining work to be completed. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $40 $100 $50 $0 $0 $1,090 PRIOR YEARS: TOTAL $895 117 P2539 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2013 6/30/2014 7/1/2014 4/30/2016 $40 $80 PROJECT PHASE: 5/1/2016 6/30/2021 $970 PROJECT LOCATION:OWD Map Book:80-82, 97-99, 113 & 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 118 P2542850-3 Reservoir Interior Coating Kevin Cameron 5/19/2014 5 22 2 $540,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior coating of the 850-3 Reservoir. JUSTIFICATION OF PROJECT: The interior coating is in poor condition and in need of replacement. COMMENTS: Budget decreased from $630K to $540K in FY 2018. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $0 $0 $0 $0 $540 PRIOR YEARS: TOTAL $530 119 P2542 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/30/2013 7/31/2014 8/1/2014 4/30/2015 $20 $60 PROJECT PHASE: 5/1/2015 12/29/2017 $460 PROJECT LOCATION:OWD Map Book:355 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 120 P2543850-1 Reservoir Interior/Exterior Coating Kevin Cameron 6/3/2015 3 22 2 $875,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 850-1 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the current Cathodic Assessment Report, the interior and exterior coatings on the 850-1 Reservoir are nearing the end of their useful life and are in need of replacement. COMMENTS: Budget increased from $575K to $875K in FY 2018 to reflect recent bid prices and anticipated structural repairs that have been encountered on many of the tanks recently recoated. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $695 $125 $5 $40 $0 $875 PRIOR YEARS: TOTAL $5 121 P2543 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 1/2/2017 7/28/2017 7/31/2017 10/31/2017 $20 $65 PROJECT PHASE: 11/1/2017 12/31/2020 $790 PROJECT LOCATION:OWD Map Book:304 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 122 P2544850-2 Reservoir Interior/Exterior Coating Kevin Cameron 6/3/2015 3 22 1 $980,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 850-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the current Cathodic Assessment Report, the interior and exterior coatings on the 850-2 Reservoir are nearing the end of their useful life and are in need of replacement. COMMENTS: Budget decreased from $1.07M to $980K in FY 2018 to reflect bid results, and keep enough budget for unanticipated structural repairs encountered on many tanks recently recoated. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $700 $5 $5 $20 $0 $0 $980 PRIOR YEARS: TOTAL $250 123 P2544 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 4/1/2016 7/29/2016 8/1/2016 10/5/2016 $20 $65 PROJECT PHASE: 10/6/2016 12/31/2019 $895 PROJECT LOCATION:OWD Map Book:317 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 124 P2545980-1 Reservoir Interior Exterior Coating Kevin Cameron 6/3/2015 P2546 5 22 2 $1,190,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 980-1 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2013 Cathodic Assessment Report, the 980-1 Reservoir interior and exterior coatings are nearing the end of their useful life and are in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $0 $0 $0 $0 $1,190 PRIOR YEARS: TOTAL $1,180 125 P2545 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 1/1/2015 6/30/2015 7/1/2015 2/29/2016 $10 $85 PROJECT PHASE: 3/1/2016 12/31/2016 $1,095 PROJECT LOCATION:OWD Map Book:172 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:3/24/2017Bob Kennedy 126 P2546980-2 Reservoir Interior/Exterior Coating Kevin Cameron 6/3/2015 P2545 5 22 2 $1,450,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 980-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the current Cathodic Assessment Report, the interior and exterior coatings on the 980-2 Reservoir are nearing the end of their useful life and are in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $1,100 $340 $5 $5 $0 $0 $1,450 PRIOR YEARS: TOTAL $0 127 P2546 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 1/1/2018 6/30/2018 7/1/2018 10/3/2018 $20 $60 PROJECT PHASE: 10/4/2018 6/30/2021 $1,370 PROJECT LOCATION:OWD Map Book:172 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:3/24/2017Bob Kennedy 128 P2547District Administration Vehicle Charging Stations Kevin Cameron 5/19/2014 3 22 1 $125,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the construction of four (4) electric vehicle charging stations at the lower Administration parking lot. JUSTIFICATION OF PROJECT: Alternative fueled vehicles are becoming more common, with electric only vehicles making up a significant portion of these. To support the needs of these vehicles and their limited driving range, the District proposes installing vehicle charging stations to allow employees to consider using for their commute. COMMENTS: $1K Permit$81K Engineer's Estimate$14K Design Fee$29K Staff time, inspection and contingency FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 31 %0 %0 %0 %31 % Betterment ID 22 0 %69 %0 %0 %69 % TOTAL:31 %69 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $20 $30 $0 $0 $0 $0 $125 PRIOR YEARS: TOTAL $75 129 P2547 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2014 6/30/2015 7/1/2015 12/31/2016 $10 $15 PROJECT PHASE: 1/1/2017 9/30/2017 $100 PROJECT LOCATION:OWD Map Book:318 2018 2019 2020 2021 2022 2023 Total $200 $200 $200 $200 $200 $200 $1,200 $500 $500 $500 $500 $500 $500 $3,000 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 130 P2553Heritage Road Bridge Replacement and Utility Relocation Kevin Cameron 6/3/2015 2 22 2 $1,430,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: The existing 16-Inch potable water pipeline to Sleep-Train Amphitheatre and Aquatica SeaWorld¶s Waterpark was built under the Otay River. The City of Chula Vista is planning to replace the Heritage Road Bridge (Project No. STM-364). The District has requested the City reserve room in the bridge for a 16-inch steel pipeline for potable water use and an 8-inch pipeline for future recycled water use. In addition to the bridge crossing, approximately 1,600 linear feet of 16-inch potable water pipeline is required. An existing 16-inch ACP pipeline in Otay River will be abandoned or converted to recycled water use. JUSTIFICATION OF PROJECT: A new bridge crossing of the Otay River at Heritage Road provides an opportunity for the District to relocate a pipeline out of the river into a more secure location and also provides an economical way to build a recycled water pipeline to these commercial customers. COMMENTS: Budget increased from $1.2M to $1.43M to reflect latest projected costs and scope of work. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $50 $100 $100 $250 $755 $150 $1,430 PRIOR YEARS: TOTAL $25 131 P2553 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2014 12/30/2016 1/2/2017 3/7/2020 $50 $385 PROJECT PHASE: 3/8/2020 6/30/2023 $995 PROJECT LOCATION:OWD Map Book:50 & 51 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/12/2017Bob Kennedy 132 P2555Administration and Operations Parking Lot Improvements Kevin Cameron 6/3/2015 3 22 2 $775,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for AC pavement repairs, slurry seal, re-striping and update area lighting improvements to existing Administration and Operations parking lots. JUSTIFICATION OF PROJECT: Parking lot needs to be re-striped and AC pavement needs to be resealed. Area lighting will be updated to more energy efficient fixtures. COMMENTS: Increased FY 2018 budget by $225,000 for repaving, striping, motorized gate, and canopies for the operations yard. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $265 $215 $0 $0 $0 $0 $775 PRIOR YEARS: TOTAL $295 133 P2555 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2015 12/31/2015 1/1/2016 12/31/2016 $20 $75 PROJECT PHASE: 1/1/2017 6/30/2019 $680 PROJECT LOCATION:OWD Map Book:318 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 134 P2557520 Res Recirculation Pipeline Chemical Supply and Analyzer Feed Replacement Project Stephen Beppler 6/3/2015 5 22 1 $100,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the existing chemical feed lines that are cast/black iron and need to be replaced with new dual wall CPVC chemical feed lines. Other miscellaneous improvements needed. Length approximately 150 feet. JUSTIFICATION OF PROJECT: The existing chemical feed lines for the 520 Reservoir are experiencing deterioration and not designed to current code for providing chemical containment. COMMENTS: Planning and start of design in FY 2016. Complete design and construction of replacement ammonia feed lines proposed in FY 2019. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $35 $5 $0 $0 $0 $0 $100 PRIOR YEARS: TOTAL $60 135 P2557 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2015 6/30/2016 4/1/2016 12/30/2016 $5 $25 PROJECT PHASE: 1/2/2017 6/30/2019 $70 PROJECT LOCATION:OWD Map Book:343 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 136 P2559Pressure Vessel Repair and Replacement Program Jeff Marchioro 6/3/2015 0 District Wide 2 $650,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will repair, coat, and/or replace entirely the pressure vessel interiors and exteriors and appurtenances for the District's potable and recycled water distribution systems including five (5) hydropneumatic and eight (8) surge tanks of various ages. Pressure vessel interiors and exteriors and appurtenances will be repaired, coated, and/or replaced entirely. Permanent or portable stairs or ladders will be provided as well. JUSTIFICATION OF PROJECT: Pressure vessels are a key component of thirteen (13) existing District pump stations. Routine inspection by qualified professionals, and follow up repair and/or replacement, are needed to extend the life expectancy of each pressure vessel and associated pump station facility. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $30 $45 $100 $100 $100 $100 $650 PRIOR YEARS: TOTAL $175 137 P2559 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2015 12/31/2016 1/1/2016 12/31/2022 $10 $50 PROJECT PHASE: 3/1/2016 6/30/2023 $590 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:3/24/2017Bob Kennedy 138 P2561Res - 711-3 Reservoir Cover/Liner Replacement Jeff Marchioro 6/3/2015 5 22 2 $1,800,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of the existing membrane floating cover and liner with new membrane system. JUSTIFICATION OF PROJECT: The existing membrane floating cover and liner have reached the end of their useful lives and require replacement to meet regulatory requirements. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $1 $10 $84 $1,690 $10 $0 $1,800 PRIOR YEARS: TOTAL $5 139 P2561 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2015 9/30/2018 10/1/2018 6/30/2020 $10 $90 PROJECT PHASE: 7/1/2020 6/30/2021 $1,700 PROJECT LOCATION:OWD Map Book:159 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 140 P2562Res - 571-1 Reservoir Cover/Liner Replacement Jeff Marchioro 6/3/2015 P2083 2 22 1 $2,900,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of the existing membrane floating cover and liner with new membrane system. JUSTIFICATION OF PROJECT: The existing membrane floating cover and liner have reached the end of their useful lives and require replacement to meet regulatory requirements. COMMENTS: Project budget revised from $2.6M to $2.9M during FY2018 budget process to reflect actual bid results. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $2,700 $145 $5 $0 $0 $0 $2,900 PRIOR YEARS: TOTAL $50 OTAY WATER DISTRICT CAPITAL IMPROVEMENT PROGRAM 141 P2562 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2015 8/31/2016 9/1/2016 7/31/2017 $10 $40 PROJECT PHASE: 8/1/2017 6/30/2020 $2,850 PROJECT LOCATION:OWD Map Book:55 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/26/2017Steve Beppler 142 P2563Res - 870-1 Reservoir Cover/Liner Replacement Jeff Marchioro 6/3/2015 2 22 3 $1,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of the existing membrane floating cover and liner with a new membrane system. JUSTIFICATION OF PROJECT: The existing membrane floating cover and liner have reached the end of their useful lives and require replacement to meet regulatory requirements. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $1 $5 $10 $90 $892 $0 $1,000 PRIOR YEARS: TOTAL $2 143 P2563 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2015 4/30/2019 5/1/2019 9/30/2020 $10 $100 PROJECT PHASE: 10/1/2020 6/30/2021 $890 PROJECT LOCATION:OWD Map Book:55 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:3/24/2017Bob Kennedy 144 P2565803-2 Reservoir Interior/Exterior Coating & Upgrades Kevin Cameron 6/3/2015 5 22 2 $940,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 803-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2013 Cathodic Assessment Report, the 803-2 Reservoir interior and exterior coatings are near the end of their useful life and in need of replacement. COMMENTS: Budget increased in FY 2018 from $725K to $940K to reflect recent bid prices and anticipated structural repairs that have been encountered on many of the tanks recently recoated. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $20 $820 $5 $5 $90 $940 PRIOR YEARS: TOTAL $0 145 P2565 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 1/1/2019 6/30/2019 7/1/2019 10/2/2019 $20 $70 PROJECT PHASE: 10/3/2019 6/30/2022 $850 PROJECT LOCATION:OWD Map Book:357 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 146 P2566520-2 Reservoir Interior/Exterior Coating & Upgrades Kevin Cameron 6/3/2015 5 22 3 $1,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 520-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2013 Cathodic Assessment Report, the 520-2 Reservoir interior and exterior coatings are at the end of their useful life and in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $10 $1,240 $150 $100 $1,500 PRIOR YEARS: TOTAL $0 147 P2566 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 1/3/2020 6/30/2020 7/1/2020 10/7/2020 $20 $70 PROJECT PHASE: 10/8/2020 6/30/2022 $1,410 PROJECT LOCATION:OWD Map Book:343 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:3/24/2017Bob Kennedy 148 P25671004-2 Reservoir Interior/Exterior Coating & Upgrades Kevin Cameron 6/3/2015 3 22 3 $905,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 1004-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2013 Cathodic Assessment Report, the 1004-2 Reservoir interior and exterior coatings are at the end of their useful life and in need of replacement. COMMENTS: Budget increased from $565K to $905K in FY 2018 to reflect recent bid prices and anticipated structural repairs that have been encountered on many of the tanks recently recoated. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $20 $780 $105 $905 PRIOR YEARS: TOTAL $0 149 P2567 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 1/4/2021 6/30/2021 7/1/2021 10/5/2021 $20 $60 PROJECT PHASE: 10/6/2021 6/30/2022 $825 PROJECT LOCATION:OWD Map Book:316 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 150 P2568Technology Business Processes Improvement - Enterprise Content Management System Michael Kerr 6/3/2015 0 District Wide 1 $245,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to advance business processes and operational efficiencies through effective implementation of information technology with assistance from integrated workflow tools, document management solutions, and standardization. JUSTIFICATION OF PROJECT: FY 2018 - Complete Enterprise Content Management and Document Management Solution. The District's current content management solution requires adaptation and new features in keeping abreast with current technologies to include content strategies and a standard taxonomy. The current solution also does not integrate well with SharePoint, the District's current Intranet back-end technology solution, and other possible integration solutions. - $36K COMMENTS: 2/2/2017±With the newly Board approved purchase of a replacement of the District¶s ECMS (Enterprise Content Management. System) staff identified a new technology to compliment the system. Staff received information that will enable the District to capture, arrange, and store any document type into the new EMCS. The new technology will also be able to recognize OCR (Optical Character Recognition), focusing on facilitating the conversion of captured documents into searchable files. This new module did not exist during staff¶s discovery of a new ECMS solution. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $36 $0 $0 $0 $0 $0 $245 PRIOR YEARS: TOTAL $209 151 P2568 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2015 6/30/2018 $245 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 152 P2571Datacenter Network- Data, Storage, and Infrastructure Enhancements Michael Kerr 6/3/2015 0 District Wide 2 $200,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement and enhancement of the infrastructure components for the Data Center Network. JUSTIFICATION OF PROJECT: Data Center Network infrastructure is reaching the end of its service life. This project plans for enhancement and replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $100 $100 $0 $0 $0 $200 PRIOR YEARS: TOTAL $0 153 P2571 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2018 6/30/2020 $200 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:3/24/2017Bob Kennedy 154 P2572Enterprise Resource Planning (ERP) Replacement Michael Kerr 6/3/2015 0 District Wide 3 $500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of the Enterprise Resource Planning system. JUSTIFICATION OF PROJECT: Based on preliminary road maps from the current vendor, staff anticipates that the current ERP system, Eden, will become inflexible and constricted with new systems on the horizon. Staff is presently identifying key core business processes in achieving improvements in productivity and quality. Staff also anticipates that the outcome of the workshops will recognize that Eden will lack the necessary functionality, business agility, flexibility, and technology necessary for the District's overall growth. COMMENTS: Staff will start the discovery process in FY 2020 to identify possible alternatives for a new system. Given the history of the current solution, Eden, staff anticipates that FY 2021 will be appropriate for a replacement. In FY 2021, the District will have been utilizing Eden Financials for over 15 years. In the interim, staff will conduct research based on the District¶s current technology infrastructure for best fit for conversion of historical data, proper workflow and security, and templates for utility billing and invoicing. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $250 $250 $0 $500 PRIOR YEARS: TOTAL $0 155 P2572 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2020 6/30/2022 $500 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:3/24/2017Bob Kennedy 156 P2573PL - 12-Inch Pipeline Replacement, 803 Zone, Hillsdale Road Stephen Beppler 5/23/2016 P2574 5 22 1 $2,450,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of approximately 4,000 feet of 12-inch potable water main within the 803 Pressure Zones in Hillsdale Road. The County has a CIP to repave Hillsdale Road after the pipeline replacement project is complete. JUSTIFICATION OF PROJECT: This project will replace thin wall, 1959 era, steel pipe originally constructed under as-built number 01-03. Two of the original four miles of thin wall steel pipe have been already replaced through separate CIP and developer projects. The remaining 2.1 miles of pipe has developed several water main breaks, including catastrophic failures due to semi-localized coating failures and severe corrosion of the thin wall steel can. COMMENTS: Design to be completed in FY 2017 and constructed in FY 2018. Construction of S2048 to be completed at the same time. Revision to water main alignment and updated cost opinion increased the project budget from $1.75M to $2.45M to also reflect jump in bid prices experienced in early 2017. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $1,600 $610 $0 $0 $0 $0 $2,450 PRIOR YEARS: TOTAL $240 OTAY WATER DISTRICT CAPITAL IMPROVEMENT PROGRAM 157 P2573 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 10/15/2016 10/1/2016 6/30/2017 $90 $150 PROJECT PHASE: 7/1/2017 3/1/2019 $2,210 PROJECT LOCATION:OWD Map Book:356 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/26/2017Steve Beppler 158 P2574PL - 12-Inch Pipeline Replacement, 978 Zone, Vista Vereda Stephen Beppler 5/23/2016 P2573 5 22 2 $2,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of approximately 0.5 miles of 12-inch potable water main within the 978 Pressure Zones in Vista Vereda and easements on private property. Replacement length of water lines could potentially increase to 4,500 feet to relocate lines outside of hard to access easements. JUSTIFICATION OF PROJECT: This project will replace thin wall, 1959-60 era, steel pipe originally constructed under as-built number 01-03. Two of the original four miles of thin wall steel pipe have been already replaced through separate CIP and developer projects. COMMENTS: Budget decreased from $2.75M to $2.5M. Changed scope of work to just include the water line along Vista Vereda from Vista Grande to Hidden Mesa Trail. Created separate CIPs for 1960s era steel water lines in Vista Grande and Pence Dr. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $450 $2,000 $30 $0 $0 $0 $2,500 PRIOR YEARS: TOTAL $20 159 P2574 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 4/30/2017 5/1/2017 12/31/2017 $20 $180 PROJECT PHASE: 1/1/2018 6/30/2020 $2,300 PROJECT LOCATION:OWD Map Book:368, 369, 378 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 160 P2578PS - 711-2 (PS 711-1 Replacement and Expansion) - 14,000 gpm Jeff Marchioro 5/23/2016 P2473 1 22 2 $10,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the construction of a new Pump Station to replace the existing Pump Station. JUSTIFICATION OF PROJECT: The existing Pump Station was derated in 2010 to resolve vibration and cavitation issues. COMMENTS: Overall project budget increased to match 2015 Water Facilities Master Plan Update. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %69 %0 %69 % Betterment ID 22 0 %31 %0 %0 %31 % TOTAL:0 %31 %69 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $350 $3,200 $6,450 $10,000 PRIOR YEARS: TOTAL $0 161 P2578 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2020 9/30/2020 10/1/2020 9/30/2021 $100 $900 PROJECT PHASE: 10/1/2021 6/30/2023 $9,000 PROJECT LOCATION:OWD Map Book:114 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 162 P2584Res - 657-1 and 657-2 Reservoir Demolitions Jeff Marchioro 5/23/2016 3 22 2 $720,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to incorporate the existing 657 Pressure Zone into the 640 Pressure Zone, abandon and demolish the two (2) 657 Reservoirs, and modify associated 657 Zone Pressure Reducing Stations. JUSTIFICATION OF PROJECT: Eliminating the existing 657 Pressure Zone will simplify operations, reduce operating cost, and improve reliability. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $35 $35 PRIOR YEARS: TOTAL $0 163 P2584 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2022 12/31/2022 1/1/2023 6/30/2024 $35 $35 PROJECT PHASE: 7/1/2024 6/30/2025 $650 PROJECT LOCATION:OWD Map Book:303 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 164 P2593458-1 Reservoir Interior/Exterior Coating & Upgrades Kevin Cameron 5/23/2016 2 22 2 $840,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 458-1 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2013 Cathodic Assessment Report, the 458-1 Reservoir interior and exterior coatings are at the end of their useful life and in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $10 $730 $100 $840 PRIOR YEARS: TOTAL $0 165 P2593 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 2/1/2021 6/30/2021 7/1/2021 10/29/2021 $10 $50 PROJECT PHASE: 11/1/2021 6/30/2022 $780 PROJECT LOCATION:OWD Map Book:66 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:3/27/2017Bob Kennedy 166 P2594Large Meter Replacement Andrea Carey 0 22 1 $485,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of water meters 3-inch or larger. JUSTIFICATION OF PROJECT: Of the 219 large meters in the ground, 105 are no longer repairable and must be replaced. Staff anticipates 97 of these meters will need to replaced in the next three years. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $150 $95 $0 $0 $0 $0 $485 PRIOR YEARS: TOTAL $240 167 P2594 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 6/1/2019 $0 $0 PROJECT PHASE: 7/1/2016 6/30/2019 $485 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 168 P2595 PL - 16-inch, 624 Zone, Village 3N - Heritage Road, Main St/Energy Way Stephen Beppler 5/23/2005 P2403 2 22 2 $150,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for construction of approximately 1,200 feet of 16-inch pipeline within the 624 Pressure Zone (PZ) in Heritage Road between Main Street to Energy Way. This project will be constructed by the developer and is subject to reimbursement per Board policy. The budget reflects the upsizing of the developer required 12-inch water line to a 16-inch water line requested by the District for transmission capabilities within the 624 PZ. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for development of Otay Ranch and other areas within the 624 Pressure Zone. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $150 $150 PRIOR YEARS: TOTAL $0 OTAY WATER DISTRICT CAPITAL IMPROVEMENT PROGRAM 169 P2595 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 1/1/2006 6/1/2021 7/1/2006 6/30/2022 $0 $0 PROJECT PHASE: 7/1/2021 6/30/2024 $150 PROJECT LOCATION:OWD Map Book:82 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 170 P2604AMR Change Out Andrea Carey 1/7/2017 0 22 1 $9,605,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Change-out of existing Master Meter 3G registers to Master Meter Allegro register and complete meter change-out of District's highest users of 3/4-2". In addition, implement cellular reading technology for District's temporary meters. JUSTIFICATION OF PROJECT: Current technology is failing at a high percentage at year 11. Final FY 2017 budget approved was $1.35M. Total program budget is estimated at $10.1M (recycled (R2143) and potable), projected to be spent over 6 years. Also, implement cellular reading technology for District's temporary meters and any large users requesting hourly data on a regular basis. Will pilot cell technology in FY 2018 with 20 endpoints and, if all works well, implement to all temp meters in FY 2019. The temporary cellular technology cost is estimated to be $75,000. COMMENTS: In FY 2025, program will resume replacing all meters and registers. Plan to expand the program to a 10 year change-out program for registers and 20 year program for meters (with exception of high users which will have full meter change-out every 10 years) at that time. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $1,510 $1,745 $1,475 $1,095 $1,290 $1,190 $9,605 PRIOR YEARS: TOTAL $1,300 171 P2604 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 1/1/2017 6/30/2023 $0 $0 PROJECT PHASE: 1/1/2017 6/30/2023 $9,605,000 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 172 P2605458/340 PRS Replacement, 1571 Melrose Ave Jeff Marchioro 2 22 2 $250,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Replace existing Pressure Reducing Station (PRS) with new facility. JUSTIFICATION OF PROJECT: Existing PRS is old with excessive leaking and vault flooding issues. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $1 $50 $189 $10 $0 $0 $250 PRIOR YEARS: TOTAL $0 173 P2605 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2018 7/1/2018 6/30/2019 $15 $50 PROJECT PHASE: 7/1/2019 6/30/2021 $185 PROJECT LOCATION:OWD Map Book:065 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 174 P2606803-2 Reservoir Repair/Replacement of Caulking and Tree Removal Jeff Marchioro 5 22 1 $75,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Repair or replacement of caulking reservoir and remove trees from tank property. JUSTIFICATION OF PROJECT: Roots from trees are penetrating the tank at the base caulking. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $1 $55 $19 $0 $0 $0 $75 PRIOR YEARS: TOTAL $0 175 P2606 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2018 7/1/2017 6/30/2018 $2 $8 PROJECT PHASE: 7/1/2018 6/30/2020 $65 PROJECT LOCATION:OWD Map Book:357 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 176 P2607Douglas Ave SWA and OWD Interconnection Upgrade Stephen Beppler 2 22 1 $50,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Replace existing 3-inch PRV at interconnection between Sweetwater Authority (SWA) and Otay with a new 8-inch PRV. Interconnection is a one-way feed from Otay to SWA so SWA will cover a majority of the costs. JUSTIFICATION OF PROJECT: SWA requested this replacement and upgrade in PRV size to better supply their system in the event of an emergency. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $10 $30 $10 $0 $0 $0 $50 PRIOR YEARS: TOTAL $0 177 P2607 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2018 7/1/2017 6/30/2018 $3 $7 PROJECT PHASE: 7/1/2018 6/30/2020 $40 PROJECT LOCATION:OWD Map Book:095 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 178 P2608PL - 8-inch, 850 Zone, Coronado Ave, Chestnut/Apple Kevin Cameron 3 22 2 $350,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Fire flows on this section of water line are below recommended rates. Preferred alternative to resolve this is to replace existing water line with about 1,300 feet of a higher pressure rated 8-inch pipeline and provide individual residential PRVs. JUSTIFICATION OF PROJECT: Existing water line is on the 657 Pressure Zone (PZ) and does not provide adequate fire protection. Moving this portion of the water system to a higher pressure zone will resolve this issue. COMMENTS: Issue discovered during modeling of moving the 657 PZ to the 640 PZ. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %50 %0 %0 %50 % Replacement 0 %0 %50 %0 %50 % TOTAL:0 %50 %50 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $10 $40 $290 $10 $0 $0 $350 PRIOR YEARS: TOTAL $0 179 P2608 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2018 7/1/2018 6/30/2019 $10 $40 PROJECT PHASE: 7/1/2019 6/30/2021 $300 PROJECT LOCATION:OWD Map Book:303 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 180 P2609PL - 8-inch, 1004 Zone, Eucalyptus St, Coronado/Date/La Mesa Kevin Cameron 3 22 2 $400,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Replace existing water line through easement along Eucalyptus Street with 1,600 feet of new 8-inch water line along Coronado Avenue, Date Street, and La Mesa Avenue. JUSTIFICATION OF PROJECT: Existing water line through easement along Eucalyptus Street is inaccessible, old, and has experienced leaks. Without this water line, fire flows in the area are below recommended rates. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $10 $65 $315 $10 $0 $400 PRIOR YEARS: TOTAL $0 181 P2609 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2018 6/30/2019 7/1/2019 6/30/2020 $10 $65 PROJECT PHASE: 7/1/2020 6/30/2022 $325 PROJECT LOCATION:OWD Map Book:317 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 182 P2610Valve Replacement Program - Phase 1 Kevin Cameron 0 22 1 $150,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Replacement of non-functioning isolation valves on the potable water system. Phase 1 is expected to replace up to 20 valves. JUSTIFICATION OF PROJECT: Working isolation valves are vital to the efficient operation of the water system. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $30 $60 $60 $0 $0 $0 $150 PRIOR YEARS: TOTAL $0 183 P2610 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2018 7/1/2017 6/30/2019 $5 $10 PROJECT PHASE: 7/1/2017 6/30/2020 $135 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2017Jolene Fielding 184 P2611Quarry Road Bridge Replacement and Utility Relocation Kevin Cameron 3 22 2 $1,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Replace existing water main crossing with new bridge construction. JUSTIFICATION OF PROJECT: New bridge construction requires replacement of the water main. COMMENTS: FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $10 $60 $425 $450 $50 $1,000 PRIOR YEARS: TOTAL $0 185 P2611 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2019 7/1/2019 6/30/2020 $5 $70 PROJECT PHASE: 7/1/2020 12/31/2022 $925 PROJECT LOCATION:OWD Map Book:197 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 186 P2612PL - 12-inch, 711 Zone, Pas de Luz/Telegraph Canyon Rd Kevin Cameron 4 22 2 $500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Replacement of existing 12-inch water line located in a steep slope easement with a new water line located within right-of-way. JUSTIFICATION OF PROJECT: COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $10 $85 $390 $10 $0 $500 PRIOR YEARS: TOTAL $0 187 P2612 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2018 7/1/2018 6/30/2019 $5 $95 PROJECT PHASE: 7/1/2019 12/31/2021 $400 PROJECT LOCATION:OWD Map Book:096 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 188 P2613PL - 12-inch, 520 Zone, Rancho San Diego Towne Center Loop Kevin Cameron 5 22 2 $150,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Provide a second feed to the Rancho San Diego Towne Center Shopping Center from Jamacha Road. JUSTIFICATION OF PROJECT: Single feed for this large complex does not provide desired redundancy. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $10 $35 $100 $5 $0 $0 $150 PRIOR YEARS: TOTAL $0 189 P2613 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2018 7/1/2018 6/30/2019 $10 $35 PROJECT PHASE: 7/1/2019 6/30/2020 $105 PROJECT LOCATION:OWD Map Book:331 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 190 P2614485-1 Reservoir Interior/Exterior Coating Kevin Cameron 4 22 3 $895,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the interior and exterior coating of the 485-1 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the current Cathodic Assessment Report, the interior and exterior coatings on the 485-1 Reservoir are nearing the end of their useful life and are in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $10 $885 $895 PRIOR YEARS: TOTAL $0 191 P2614 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2021 12/31/2021 1/1/2022 6/30/2022 $2 $8 PROJECT PHASE: 7/1/2022 6/30/2023 $885 PROJECT LOCATION:OWD Map Book:112 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/12/2017Bob Kennedy 192 P2615PL - 12-Inch Pipeline Replacement, 803 PZ, Vista Grande Stephen Beppler 5 22 2 $1,200,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of approximately 0.5 miles of 12-inch and 14-inch potable water main within the 803 Pressure Zones in Vista Grande. JUSTIFICATION OF PROJECT: This project will replace thin wall, 1959-60 era, steel pipe originally constructed under as-built number 01-03. Two of the original four miles of thin wall steel pipe have been already replaced through separate CIP and developer projects. The remaining 2.1 miles of pipe has developed several water main breaks including catastrophic failures due to semi-localized coating failures and severe corrosion of the thin wall steel can. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $20 $130 $1,030 $20 $0 $1,200 PRIOR YEARS: TOTAL $0 193 P2615 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2018 6/30/2019 7/1/2019 6/30/2020 $20 $130 PROJECT PHASE: 7/1/2020 6/30/2021 $1,050 PROJECT LOCATION:OWD Map Book:368 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 194 P2616PL - 12-Inch Pipeline Replacement, 978 Zone, Pence Dr/Vista Sierra Dr Stephen Beppler 5 22 2 $2,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of approximately 0.4 miles of 14-inch potable water main within the 978 Pressure Zones in Pence Drive, Vista Sierra Drive and easements on private property east of Vista Grande. Replacement length of water lines could potentially increase to 5,000 feet to relocate lines outside of easements. JUSTIFICATION OF PROJECT: This project will replace thin wall, 1959-60 era, steel pipe originally constructed under as-built number 01-03. Two of the original four miles of thin wall steel pipe have been already replaced through separate CIP and developer projects. The remaining 2.1 miles of pipe has developed several water main breaks including catastrophic failures due to semi-localized coating failures and severe corrosion of the thin wall steel can. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $20 $180 $2,280 $20 $0 $0 $2,500 PRIOR YEARS: TOTAL $0 195 P2616 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2018 7/1/2018 6/30/2019 $20 $180 PROJECT PHASE: 7/1/2019 6/30/2021 $2,300 PROJECT LOCATION:OWD Map Book:378 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 196 P2617Lobby Security Enhancements Kent Payne 3 22 1 $75,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Redesign and install new customer service counter with enhanced security features; reconfigure the public service desk to include security enhancements along with an enlarged and secured adjoining conference room; replace finance and engineering double doors with new secured glass doors. JUSTIFICATION OF PROJECT: This project will add security features to the District¶s public lobby in the form of bullet resistant barriers, glass and work areas with sufficient protection to allow staff to retreat to a safe location should a dangerous encounter present itself. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $75 $0 $0 $0 $0 $0 $75 PRIOR YEARS: TOTAL $0 197 P2617 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2018 7/1/2017 6/30/2018 $5 $5 PROJECT PHASE: 7/1/2017 6/30/2018 $65 PROJECT LOCATION:OWD Map Book:318 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/12/2017Bob Kennedy 198 P2619PS - Temporary Lower Otay Pump Station Redundancy Jeff Marchioro 1 22 1 $635,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Add a second pump to LOPS to provide system redundancy to this vital station. Project involves site work, yard piping, replacement of a 30-inch flow meter and adjoining piping due to internal deterioration, instrumentation, and controls additions along with security improvements. JUSTIFICATION OF PROJECT: LOPS is the sole water supply to the south potable water system during annual SDCWA aqueduct shutdowns and needs to have redundancies and remote access controls to ensure reliable operation. COMMENTS: Scope of work from CIP P2579 included in CIP P2619. CIP P2579 will be closed to avoid duplication. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $20 $80 $485 $50 $0 $0 $635 PRIOR YEARS: TOTAL $0 199 P2619 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2018 7/1/2018 6/30/2019 $20 $80 PROJECT PHASE: 7/1/2019 6/30/2021 $535 PROJECT LOCATION:OWD Map Book:070 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 200 P2620Radio and Emergency Communication System Michael Kerr P2520 0 District Wide 2 $20,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will be to conduct an assessment of the District's critical communications and information systems infrastructure and evaluate the technical feasibility of the creation of a back-up communications systems that complements existing communications resources (Metro-E) and next generation and advanced communications technologies. Where CIP P2520 made updates to the existing radio system that is dated and has a limited remaining life of about 6 years, this CIP will evaluate the latest generation of radio communications for replacement of the existing system. JUSTIFICATION OF PROJECT: In the event of a natural disaster and unavailable power and data coverage, staff requests this initial report conducted for potential solutions for back-up emergency communications systems. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $20 $0 $0 $0 $0 $0 $20 PRIOR YEARS: TOTAL $0 201 P2620 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 8/1/2017 10/5/2017 $0 $20 PROJECT PHASE: $0 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/12/2017Bob Kennedy 202 P2623Central Area to Otay Mesa Interconnection Pipelines Combination Air/Vacuum Valve Replacements Jeff Marchioro P2083 2 22 2 $270,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Replace approximately sixty (60) existing 4-inch combination air/vacuum valves with surge type (slow closing) combination air/vacuum valves on the Central Area to Otay Mesa Interconnection Pipelines. Replace existing valve enclosures as needed. JUSTIFICATION OF PROJECT: A transient surge analysis for the new 870-2 Pump Station project identified existing combination air/vacuum valves which need to be replaced with surge type (slow closing) valves. Existing air/vacuum valve enclosures will need to be replaced since some are severely corroded and others are too short for the taller replacement valves. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $20 $120 $120 $10 $0 $0 $270 PRIOR YEARS: TOTAL $0 203 P2623 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 9/30/2017 10/1/2017 6/30/2018 $5 $15 PROJECT PHASE: 7/1/2018 6/30/2020 $250 PROJECT LOCATION:OWD Map Book:055 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 204 R2077RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway Stephen Beppler 5/23/2006 R2048, R2058, R2087 2 22 4 $2,852,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for construction of approximately 9,300 feet of 24-inch pipeline within the 860 Pressure Zone in Alta Road from the Alta Gate location to Airway Road. Portions of this project are being built by developers through reimbursement agreements. The balance of this project will be constructed as part of the Otay Mesa recycled water system. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for development of Otay Mesa and link the planned 860-1 Reservoir with the recycled water transmission system in Otay Mesa. Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102-575. COMMENTS: Temporary moratorium enacted for Otay Mesa recycled water in July 2014 will be revisited in the future. In the meanwhile, putting a hold on all recycled water projects in Otay Mesa. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $20 $20 $0 $0 $0 $0 $2,852 PRIOR YEARS: TOTAL $2,812 OTAY WATER DISTRICT CAPITAL IMPROVEMENT PROGRAM 205 R2077 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2001 12/1/2009 1/1/2010 6/30/2019 $164 $451 PROJECT PHASE: 7/1/2019 12/31/2024 $2,237 PROJECT LOCATION:OWD Map Book:39 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:5/5/2017Bob Kennedy 206 R2079RecPL - 6-Inch, 450 Zone, Otay Valley Road - Otay Valley/Entertainment Stephen Beppler R2028 1 22 2 $150,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to construct the pipeline across the river and the pressure reducing station to reduce the pressure from the 680 Pressure Zone to a new 450 Pressure Zone to serve the amphitheater and water park. JUSTIFICATION OF PROJECT: The City is replacing the Heritage Road Bridge south of Main Street. Village 3 will construct recycled water to the intersection of Heritage Road and Main Street. COMMENTS: The pipeline is estimated to cost $450K and a pressure reducing station $200K. Current CIP does not reflect this work; will be updated upon acceptance of new Master Plan. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $10 $10 $10 $120 $0 $0 $150 PRIOR YEARS: TOTAL $0 207 R2079 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 6/30/2017 7/1/2017 12/31/2018 $10 $20 PROJECT PHASE: 1/1/2019 6/30/2021 $120 PROJECT LOCATION:OWD Map Book:51 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 208 R2084RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media Stephen Beppler 6/2/2004 R2083, R2085 1 22 2 $365,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for construction of approximately 2,000 feet of 20-inch pipeline within the 680 Pressure Zone in Village 2 in Santa Victoria Road from Santa Carolina Road to Santa Alexia Avenue. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for the recycled water supply pumped from the 680-1 Pump Station to the 680 and higher pressure zones. Significant energy savings will occur due to lower total dynamic head requirements for the 680-1 Pump Station. Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102-575. COMMENTS: This is a developer driven project. A reimbursement agreement is expected to be considered by the Board in FY 2017. Developer budget is 2,000 LF at a cost of $150 per foot for a total of $300K.Inspection and staff budget is $65K.This CIP budget was reduced from $970K to $365K for the FY 2017 CIP budget. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $40 $315 $10 $0 $0 $0 $365 PRIOR YEARS: TOTAL $0 209 R2084 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2004 6/30/2017 7/1/2017 6/30/2018 $10 $40 PROJECT PHASE: 7/1/2018 6/30/2020 $315 PROJECT LOCATION:OWD Map Book:82 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $1,900 $1,900 $1,900 $5,700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 210 R2110RecPS - 944-1 Optimization and Pressure Zone Modifications Jeff Marchioro R2091 1 22 1 $200,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to improve the control strategy to increase pumping capacity and streamline operation of the pump station. As a result of this effort, replacement of five (5) service saddles on Clubhouse Drive will need to be replaced with higher pressure class saddles. Add a sump pump to an existing pressure reducing station vault located east of the intersection of Otay Lakes Road and Hunte Parkway. JUSTIFICATION OF PROJECT: Revising the control strategy will increase pumping capacity and improve the District's ability to operate the pump station during off-peak hours when electricity rates are low. Retrofitting the Pressure Reducing Station (PRS) vault with a sump pump will prolong the life expectancy of existing pressure reducing station components. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $20 $45 $0 $0 $0 $0 $200 PRIOR YEARS: TOTAL $135 211 R2110 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2013 10/1/2013 10/1/2013 9/30/2015 $60 $25 PROJECT PHASE: 9/30/2015 6/30/2019 $115 PROJECT LOCATION:OWD Map Book:115 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 212 R2116RecPL - 14-Inch, 927 Zone, Force Main Improvements Jeff Marchioro 3 22 1 $2,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the repair of the existing 16,000 L.F. 14-Inch force main, built in 1978, and the replacement of fifteen (15) blow-offs. JUSTIFICATION OF PROJECT: Active leaks and significant localized corrosion have been spot repaired. Additional spot repairs and replacement of the existing blow-offs are needed to extend the remaining useful life of the facility. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $200 $400 $0 $0 $0 $0 $2,500 PRIOR YEARS: TOTAL $1,900 213 R2116 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2014 3/31/2017 1/1/2015 6/30/2017 $500 $200 PROJECT PHASE: 1/1/2015 6/30/2020 $1,800 PROJECT LOCATION:OWD Map Book:186, 200, 304, 318, 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:3/16/2017Bob Kennedy 214 R2118Steele Canyon Sewer PS Large Solids Handling Improvements Stephen Beppler 6/3/2015 3 22 1 $75,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for installation of measures in the Steele Bridge Sewer Pump Station wet well to protect the sewage pumps from assorted debris. The existing pumps have been requiring a high frequency of repairs and replacement of parts due to rags, construction materials, and other non-typical wastewater solids entering the pump station. Assessment of installing either a new chopper pump or bar screen to handle these types of materials is needed. JUSTIFICATION OF PROJECT: The prevention of large debris from reaching the existing pumps will result in reduced maintenance repairs and extend the life of the sewage pumps. Based upon the current frequency and cost of maintenance of the sewage pumps, the proposed improvement should pay for itself within a few years. Improvements may trigger safety upgrades to also be included. COMMENTS: Design completed in FY 2017 with construction in FY 2018 to coincide with next scheduled treatment plant shutdown. CIP is based upon recommendations from RWCWRF Master Plan (Item 3.1). FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 18 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $50 $3 $0 $0 $0 $0 $75 PRIOR YEARS: TOTAL $22 215 R2118 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2015 7/31/2015 8/3/2015 9/30/2015 $2 $18 PROJECT PHASE: 10/1/2015 6/30/2019 $55 PROJECT LOCATION:OWD Map Book:331 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 216 R2120RWCWRF Filtered Water Storage Tank Improvements Stephen Beppler 6/3/2015 R2096 3 22 1 $500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to seal and recoat the interior and exterior of steel tank walls and concrete floor. Construct improvements to facilitate operation and maintenance activities and compliance with all applicable codes and OSHA standards. Salvage or replace and improve existing floating cover while incorporating a support structure to permit tank entry below the cover when the tank is drained. JUSTIFICATION OF PROJECT: HDR Engineering Inspection and Condition Assessment Report dated May 2015 recommends structural improvements, replacement of the exterior coatings, and replacement of the cathodic protection system. This improvement was included in the Ralph W. Chapman Water Reclamation Facility (RWCWRF) Master Plan (Item 7.9). The report prepared by HDR in 2015 stated that the interior coating has exceeded its life cycle due to deterioration. The report also states that the exterior coating is in fair condition and as one of their recommendations it can be power washed and scrubbed with a mild biodegradable cleaner to remove all of the chalking. A spot paint can then be applied on the exterior. COMMENTS: Construction delayed until FY 2019 in response to other priorities at the plant. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $25 $20 $400 $5 $0 $0 $500 PRIOR YEARS: TOTAL $50 217 R2120 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2015 2/1/2016 2/2/2016 6/30/2017 $10 $40 PROJECT PHASE: 7/1/2017 6/30/2020 $450 PROJECT LOCATION:OWD Map Book:319 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 218 R2121Res - 944-1 Reservoir Cover/Liner Replacement Jeff Marchioro 6/3/2015 5 22 2 $1,400,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of the existing membrane floating cover and liner with a new membrane system. JUSTIFICATION OF PROJECT: The existing membrane floating cover and liner have reached the end of their useful lives and require replacement to meet regulatory requirements. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $1 $1 $33 $1,347 $0 $0 $1,400 PRIOR YEARS: TOTAL $18 219 R2121 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2015 6/30/2016 7/1/2016 9/30/2020 $10 $100 PROJECT PHASE: 10/1/2020 6/30/2021 $1,290 PROJECT LOCATION:OWD Map Book:172 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:3/24/2017Bob Kennedy 220 R2123Repurpose Otay Mesa Recycled Water Lines Stephen Beppler 5/23/2016 2 22 2 $350,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will access the alternative use potential for the Otay Mesa recycled waterlines utilizing hydraulic modeling. JUSTIFICATION OF PROJECT: Determining alternative uses for these waterlines will allow for these assets to be used rather than lie dormant. With the moratorium on extending recycled water to Otay Mesa, the recycled waterlines already installed throughout the area will be evaluated for potential uses. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $5 $150 $150 $35 $350 PRIOR YEARS: TOTAL $0 221 R2123 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 6/30/2017 $35 $0 PROJECT PHASE: 7/1/2017 6/30/2023 $315 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 222 R2125RecPRS - 927/680 PRS Improvements, Otay Lakes Road Stephen Beppler 1 22 2 $200,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Add equipment and controls to allow for the operation of the 927/680 Pressure Reducing Station (PRS) to function in coordination with the 944-1 Recycled Water Pump Station (RWPS). JUSTIFICATION OF PROJECT: Storage in the 680 Recycled Water Pressure Zone (PZ) is limited while the 927 PZ has excess storage. During peak electrical periods when the distribution pumps are not typically operated, the proposed improvements will allow for high water demands to be supplied from the 927 PZ storage. The controls would prevent the PRV from opening when the 944-1 RWPS is in operation. COMMENTS: New CIP based upon 2015 Water Facilities Master Plan update. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $50 $145 $5 $0 $0 $0 $200 PRIOR YEARS: TOTAL $0 223 R2125 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 12/31/2017 1/1/2018 12/31/2018 $15 $35 PROJECT PHASE: 1/1/2019 6/30/2020 $150 PROJECT LOCATION:OWD Map Book:130 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 224 R2139RWCWRF - Filter Troughs Replacement Stephen Beppler 3 22 2 $30,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Replace existing fiberglass reinforced plastic (FRP) weir troughs that supply flow to the filters as well as bypass the filters during plant operations that do not meet discharge requirements. JUSTIFICATION OF PROJECT: Existing FRP weir troughs are from original 1992 construction and are at the end of their useful life. Fibers are exposed and can become waterlogged with trough breakage a risk. Weight is causing trough to sag, resulting in leakage and disproportional feed through the filters. COMMENTS: CIP is based upon recommendations from Ralph W. Chapman Water Reclamation Facility (RWCWRF) Master Plan (Item 7.5). FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $30 $0 $0 $0 $0 $0 $30 PRIOR YEARS: TOTAL $0 225 R2139 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2018 7/1/2017 6/30/2018 $1 $4 PROJECT PHASE: 7/1/2017 6/30/2018 $25 PROJECT LOCATION:OWD Map Book:319 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 226 R2143AMR Change Out Andrea Carey 1/7/2017 0 22 1 $525,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Change-out of existing Master Meter 3G registers to Master Meter Allegro register and complete meter change-out of District's highest users of 3/4-2". JUSTIFICATION OF PROJECT: Current technology is failing at a high percentage at year 11. Final FY 2017 budget approved was $1.35M. Total program budget is estimated at $10.1M (recycled and potable (P2604)), projected to be spent over 6 years. COMMENTS: In FY 2025, program will resume replacing all meters and registers. Plan to expand the program to a 10 year change-out program for registers and 20 year program for meters (with exception of high users which will have full meter change-out every 10 years) at that time. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $350 $75 $25 $5 $10 $10 $525 PRIOR YEARS: TOTAL $50 227 R2143 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 1/7/2017 6/30/2023 $525 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 228 S2012 San Diego County Sanitation District Outfall and RSD Outfall Replacement Stephen Beppler 6/4/2003 3 18 1 $3,550,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the Otay Water District proportionate share of the San Diego County Sanitation District total costs for replacement of various system components of the existing Spring Valley and Rancho San Diego Outfall Systems, per terms of an existing agreement with the County of San Diego Sanitation District. The reimbursement also includes a proportionate share of operating and maintenance costs. JUSTIFICATION OF PROJECT: Various components of the San Diego County Sanitation District Spring Valley Outfall and the Rancho San Diego Outfall are in very bad condition and are in need of repair and/or replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $20 $200 $250 $300 $350 $400 $2,540 PRIOR YEARS: TOTAL $1,020 229 S2012 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2003 6/30/2025 $3,550 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 230 S2024Campo Road Sewer Main Replacement Stephen Beppler 5/17/2010 3 18 1 $10,100,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to upgrade the sewer main capacity of approximately 11,050 feet of existing 10-inch PVC sewer main, 450 feet of 10-inch reinforced polymer mortar pipe sewer main, and 50 feet of 15-inch sewer main. The project location begins at the south end of Avocado Blvd, through the Rancho San Diego Village Shopping Center, paralleling the SR-94/Campo Road in the adjacent open space. JUSTIFICATION OF PROJECT: The existing sewer main is under-sized and must be replaced to increase capacity. Portions of the sewer main are located in areas of sensitive habitat making it difficult to access for maintenance. COMMENTS: Project design completed in FY 2016. Easement costs increased from $150K to $350K Construction costs increased with delay from easement acquisition, apparent low bid is $7.82M, with additional costs for administration, inspection, and construction management bringing the project total estimate to $10.1M. This project is funded by the Clean Water State Loan Fund. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 18 0 %50 %0 %0 %50 % Replacement 0 %0 %50 %0 %50 % TOTAL:0 %50 %50 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $4,250 $4,250 $50 $0 $0 $0 $10,100 PRIOR YEARS: TOTAL $1,550 OTAY WATER DISTRICT CAPITAL IMPROVEMENT PROGRAM 231 S2024 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 12/31/2014 1/1/2015 6/30/2016 $160 $1,390 PROJECT PHASE: 7/1/2016 6/30/2018 $8,550 PROJECT LOCATION:OWD Map Book:330 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:9/7/2017Jolene Fielding 232 S2027Rancho San Diego Pump Station Rehabilitation Stephen Beppler 5/16/2011 3 18 1 $3,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the rehabilitation of the Rancho San Diego Pump Station located near Singer Lane. The project is being designed and constructed by the County of San Diego, with the District sharing the costs. The County invoices the District once a year. JUSTIFICATION OF PROJECT: The existing sewer pump station is over 20 years old and the pumps have reached the end of their useful lives. The pump station also needs improvements to bring the station up to current OSHA requirements. COMMENTS: Project design is complete and construction is in progress. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $5 $5 $5 $444 $0 $0 $3,500 PRIOR YEARS: TOTAL $3,041 233 S2027 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 7/1/2013 7/1/2013 9/30/2016 $50 $500 PROJECT PHASE: 10/1/2016 6/30/2021 $2,950 PROJECT LOCATION:OWD Map Book:331 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/18/2017Bob Kennedy 234 S2033Sewer System Rehabilitation Stephen Beppler 5/16/2011 5 18 1 $3,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for sewer system rehabilitation efforts that have been identified. These efforts involve replacement of approximately 13,000 linear-feet of failing or damaged pipe segments, separated pipe joints, etc. JUSTIFICATION OF PROJECT: The closed circuit television sewer assessment program process has assisted in the identification of sewer mains containing sags, which has allowed debris to form, and/or are damaged and in need of repair. COMMENTS: Project to be closed after FY 2018. Construction of the Rancho San Diego (RSD) Basin Phase 1 project will remain under this project. FY 2019 costs are to cover warranty period of RSD Phase 1. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $10 $10 $0 $0 $0 $0 $3,000 PRIOR YEARS: TOTAL $2,980 235 S2033 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 1/1/2016 3/1/2013 1/1/2017 $225 $775 PROJECT PHASE: 6/30/2014 6/30/2017 $2,000 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 236 S2043RWCWRF Sludge Handling System Stephen Beppler 5/14/2013 R2096 3 18 3 $1,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for a Sludge Handling System at the Ralph W. Chapman Water Recycling Facility (RWCWRF) to reduce the amount of solids the District sends to Metro. JUSTIFICATION OF PROJECT: The District currently sends all sludge produced at RWCWRF to Metro for treatment. The District's Wastewater Management Plan provided a preliminary estimate of the cost of handling sludge at the RWCWRF that is close to the cost Metro charges the District for treatment of solids. COMMENTS: City of San Diego is in the process of determining future sewer rates related to the implementation of the Pure Water Program. Once these rates are established, the feasibility of handling solids at the RWCWRF can be fully assessed. This CIP is as indicated in the RWCWRF Master Plan under item 11.2. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 18 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $30 $0 $0 $0 $0 $5 $76 PRIOR YEARS: TOTAL $41 237 S2043 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2013 6/30/2023 7/1/2023 6/30/2024 $75 $200 PROJECT PHASE: 7/1/2024 6/30/2026 $1,225 PROJECT LOCATION:OWD Map Book:319 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 238 S2044Trenchless Sewer Rehabilitation Stephen Beppler 5/23/2016 5 18 1 $550,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to repair sewer damage by trenchless repair methods at over 50 identified sewer sites. The planning and design for this project was begun under S2033 and is now separated out into its own project entity. JUSTIFICATION OF PROJECT: The closed circuit television sewer assessment program process has assisted in the identification of sewer mains containing sags, which has allowed debris to form, and/or are damaged and need to be repaired. COMMENTS: Project to be bid and constructed in FY 2017. Budget reduced from $650K to $550K to reflect bid results. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $75 $5 $0 $0 $0 $0 $550 PRIOR YEARS: TOTAL $470 239 S2044 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 2/28/2017 $0 $50 PROJECT PHASE: 3/1/2017 6/30/2019 $500 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 240 S2045Fuerte Drive Sewer Relocation Stephen Beppler 5/23/2016 5 18 1 $200,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the relocation of the Fuerte Drive Sewer Main. The County of San Diego is realigning a portion of Fuerte Drive in an area where the District has identified sewer Site 34 for rehabilitation. This design will be accelerated to enable the work to be completed in coordination with the County road work. JUSTIFICATION OF PROJECT: The closed circuit television sewer assessment program process has assisted in the identification of sewer mains containing sags, which has allowed debris to form, and/or are damaged and need to be repaired. COMMENTS: Planning work started under the S2033 project. County has delayed construction until FY 2018. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $50 $130 $0 $0 $0 $0 $200 PRIOR YEARS: TOTAL $20 241 S2045 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 7/29/2016 8/1/2016 7/31/2017 $5 $65 PROJECT PHASE: 8/3/2017 6/30/2019 $130 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 242 S2046RWCWRF - Aeration Panels Replacement Stephen Beppler 3 18 1 $450,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of 39 aeration panels. The existing aeration diffuser panels installed in the aeration basins are no longer being produced by the manufacturer and have failed in less than half the expected life indicated from the manufacturer's literature. Options include manufacturer's retrofit with their currently offered panels or explore other alternative manufacturers. Depending upon the replacement aeration system selected, completion of the aeration header loop may also be included to provide better air distribution at equal pressure. CIP is based upon recommendations from Ralph W. Chapman Water Reclamation Facility (RWCWRF) Master Plan (Items 5.1 and 5.3). JUSTIFICATION OF PROJECT: Failures of existing aeration diffuser panels required replacement immediately. Ultimate replacement of the system is required within the expected life of the replacement diffusers - within four years. COMMENTS: A study of aeration systems and their costs will be performed during FY 2018 and a decision made on the replacement system. If possible, recommend panel replacement be performed in a two-step process to enable assessment of the new system. Retrofit of one basin at first as this will allow for assessment of the operation of the new panels prior to implementing in all basins. If the replacement system and existing system are not compatible, than all three basins will need to be replaced at once. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $50 $100 $200 $0 $0 $0 $450 PRIOR YEARS: TOTAL $100 243 S2046 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 12/31/2017 11/1/2016 6/30/2018 $20 $80 PROJECT PHASE: 10/1/2016 6/30/2020 $350 PROJECT LOCATION:OWD Map Book:319 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 244 S2047Asset Management - Info Master Sewer Implementation Ming Zhao 5/23/2016 5 18 2 $58,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the purchase and implementation of sewer asset management decision making software, Info Master Sewer. JUSTIFICATION OF PROJECT: Allows for asset management of sewer system. COMMENTS: This was originally part of the P2486 Asset Management CIP. As this portion is for sewer, a separate CIP was created to reflect the different funding resource. The overall CIP amount does not change. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 18 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $30 $28 $0 $0 $0 $0 $58 PRIOR YEARS: TOTAL $0 245 S2047 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2019 $58 $0 PROJECT PHASE: $0 PROJECT LOCATION:OWD Map Book: 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 246 S2048Hillsdale Road Sewer Repairs Stephen Beppler 5/23/2016 5 18 1 $720,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to repair two (2) areas of sewer mains, Sites 790 and 878, will be designed and constructed in coordination with the proposed waterline improvements in Hillsdale Road. This work was originally included in S2033. JUSTIFICATION OF PROJECT: The closed circuit television sewer assessment program process has assisted in the identification of sewer mains containing sags, which has allowed debris to form, and/or are damaged and need to be repaired. COMMENTS: Coordination with the waterline project is necessary. Budget increased for FY 2018 from $500K to $720K to reflect updated project cost estimate, additional MH repair, and jump in recent bids in early 2017. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $400 $270 $0 $0 $0 $0 $720 PRIOR YEARS: TOTAL $50 OTAY WATER DISTRICT CAPITAL IMPROVEMENT PROGRAM 247 S2048 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 6/30/2017 $0 $50 PROJECT PHASE: 7/1/2017 6/30/2019 $670 PROJECT LOCATION:OWD Map Book:356 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/26/2017Steve Beppler 248 S2049Calavo Basin Sewer Rehabilitation - Phase 2 Stephen Beppler 5/23/2016 5 18 2 $1,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for repairs to the gravity sanitary sewer system to repair areas with potential for sewer backups and spills. This project addresses the following nine (9) sewer sites, primarily in the Calavo area: 25, 27, 56, 65, 78, 230, 310, 452, and 1460. JUSTIFICATION OF PROJECT: The closed circuit television sewer assessment program process has assisted in the identification of sewer mains containing sags, which has allowed debris to accumulate, and/or are damaged and need to be repaired. COMMENTS: This project is taken from S2033 and is the next highest priority areas after the Rancho San Diego Phase 1 project for open cut repairs. Construction to be after completion of Campo Road Sewer project. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $19 $130 $845 $5 $0 $0 $1,000 PRIOR YEARS: TOTAL $1 249 S2049 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2016 6/30/2018 7/1/2018 6/30/2019 $20 $130 PROJECT PHASE: 7/1/2019 6/30/2021 $850 PROJECT LOCATION:OWD Map Book:353, 354, 365 & 366 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 250 S2050Rancho San Diego Basin Sewer Rehabilitation - Phase 2 Stephen Beppler 5/23/2016 5 18 2 $1,300,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the repairs to gravity sanitary sewer system to repair areas with potential for sewer backups and spills. This project addresses the following eight (8) sewer sites: 705, 724, 735, 747, 750, 772, 775, and 847. JUSTIFICATION OF PROJECT: The closed circuit television sewer assessment program process has assisted in the identification of sewer mains containing sags, which has allowed debris to form, and/or are damaged and need to be repaired. COMMENTS: This project is taken from S2033 and is the next highest priority area for open cut repairs after the Calavo Phase 2 project. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $20 $180 $550 $500 $1,250 PRIOR YEARS: TOTAL $0 251 S2050 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2019 6/30/2020 7/1/2020 6/30/2021 $20 $180 PROJECT PHASE: 7/1/2021 6/30/2024 $1,100 PROJECT LOCATION:OWD Map Book:355, 356, 357, 368, 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 252 S2051RWCWRF - Headworks Improvements Stephen Beppler 5/23/2016 3 18 1 $150,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the refurbishment of the treatment plant headworks, notably the rotary screen concrete channel. JUSTIFICATION OF PROJECT: Existing channel wall is greatly deteriorated by H2S and supports the rotary screen. Repair will fix channel ventilation which contributed to the wall deterioration. CIP is based upon recommendations from Ralph W. Chapman Water Reclamation Facility (RWCWRF) Master Plan (Item 4.1). COMMENTS: Alternative channel wall and support structure for the rotary screen is required. Design to performed in FY 2018. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $50 $100 $0 $0 $0 $0 $150 PRIOR YEARS: TOTAL $0 253 S2051 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 12/31/2017 1/1/2018 6/30/2018 $20 $30 PROJECT PHASE: 7/1/2018 6/30/2019 $100 PROJECT LOCATION:OWD Map Book:319 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2017Jolene Fielding 254 S2053RWCWRF - Sedimentation Basins Weirs Replacement Stephen Beppler 5/23/2016 3 18 1 $60,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to replace on each of the three (3) sedimentation basins the effluent weirs. Additional items identified in the Ralph W. Chapman Water Reclamation Facility (RWCWRF) Master Plan for scum weir actuators, and sludge collector drives will be evaluated at a later date and added as necessary including installing new motor actuated valves on the solids collection piping to complete the automation of this system. JUSTIFICATION OF PROJECT: The fiberglass reinforced plastic (FRP) effluent weirs installed in 1992, are at the end of their useful life and need replacement, with the weirs having exposed fibers that increases their chance of failure. CIP is based upon recommendations from RWCWRF Master Plan (Item 6.1). COMMENTS: Project will be done in one year, replacing elements of one basin at a time. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $60 $0 $0 $0 $0 $0 $60 PRIOR YEARS: TOTAL $0 255 S2053 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2019 7/1/2017 6/30/2019 $2 $3 PROJECT PHASE: 7/1/2017 6/30/2019 $55 PROJECT LOCATION:OWD Map Book:319 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/24/2017Jolene Fielding 256 S2054Calavo Basin Sewer Rehabilitation - Phase 3 Stephen Beppler 5/23/2016 5 18 2 $1,300,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the repairs to gravity sanitary sewer system to repair areas with potential for sewer backups and spills. This project addresses the following nine sewer sites in the Calavo area: 5.1, 93, 126, 150.1, 150.2, 186, 200, 436, and 1000. JUSTIFICATION OF PROJECT: The closed circuit television sewer assessment program process has assisted in the identification of sewer mains containing sags, which has allowed debris to form, and/or are damaged and need to be repaired. COMMENTS: This project is taken from S2033 and is the next highest priority areas after the Rancho San Diego Phase 2 project for open cut repairs. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $20 $180 $1,090 $1,290 PRIOR YEARS: TOTAL $0 257 S2054 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2020 11/30/2020 12/1/2020 10/31/2021 $20 $180 PROJECT PHASE: 11/1/2021 6/30/2023 $1,100 PROJECT LOCATION:OWD Map Book:353, 354, 365, 366 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/19/2017Jolene Fielding 258 S2061RWCWRF Aeration Controls Consolidation & Optimization Upgrades (S) Stephen Beppler R2119 3 18 1 $190,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will consolidate the aeration controls for the biological treatment process of the Ralph W. Chapman Water Reclamation Facility (RWCWRF) to fully integrate the aeration system controls and allow for automated adjustments. Also included are studies for plant optimization and long-term cost effectiveness of the facility considering proposed Pure Water/Point Loma Secondary Equivalency on sewer rates. JUSTIFICATION OF PROJECT: Implementation of the Aeration Controls Consolidation task will eliminate operational risks that include: - dealing with shock loads on the plant that upset the biological process. Plant can take a week to recover, which results in returning some or all flows to Metro during this recovery time. These events can occur 2-3 times a year. - allow for automatic adjustment of air flow level. Plant can't automatically adjust air levels that need twice daily manual entry at this time, weekends see reductions in nitrogen removal that can lead to a permit violation. COMMENTS: Budget set at $190K to reflect identified scope of work from the Treatment Plant Master Plan under 5.2 Aeration Controls Consolidation ($157,800) [Note that 12.1 Automation/SCADA Upgrades that are not operational costs are covered in CIP P2485 and that 13.7 Security Improvements are covered in CIP P2382], plus $30K for proposed optimization planning studies. Recycled CIP R2119 to be closed out at end of FY 2017. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 18 0 %100 %0 %0 %100 % Replacement 0 %0 %0 %0 %0 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2018 2019 2020 2021 2022 2023 Total $30 $10 $150 $0 $0 $0 $190 PRIOR YEARS: TOTAL $0 259 S2061 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2017 6/30/2019 7/1/2017 12/31/2019 $30 $30 PROJECT PHASE: 1/1/2020 6/30/2020 $130 PROJECT LOCATION:OWD Map Book:319 2018 2019 2020 2021 2022 2023 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/20/2017Jolene Fielding 260 Annual CIP Development Policy No. 6 Purpose To define the policy on the preparation and approval of the annual Capital Improvement Program. Background District staff develops and maintains a Water Resources Master Plan (WRMP), an Integrated Water Resources Plan (IRP), and Strategic Plan that collectively are used to prepare the annual Capital Improvement Program (CIP) and to identify the CIP projects required for ultimate build out. The WRMP is revised every five years and adopted by the Board. Annually, staff prepares a six-year moving window CIP that provides information on budget assumptions, source of funds, allocation of funds, project costs, project location, description, justification, scheduling, etc. The six-year CIP is submitted and presented to the Board of Directors to obtain approval for staff to proceed with implementation to plan, design, and construct facilities and programs necessary to meet the needs of the District. Policy The General Manager, or his designee, shall prepare a proposed six-year CIP for submission to the Board of Directors for their review prior to and approval by June 30 of each fiscal year. The CIP projects shall be reviewed and updated annually to consider appropriate revisions based on the most recent WRMP, IRP, Strategic Plan, and market condition information. The timing of projects shall be based on necessity and availability of financing. The intent is that new CIP projects will be installed as development requires the facilities. With regard to all CIP projects, it is acknowledged that compliance with the California Environmental Quality Act adds a measure of unpredictability with regard to the timing of CIP projects. The WRMP, IRP, and the CIP projects shall be divided into two phases: Phase I - one to six years; and Phase II - seven to ultimate buildout. CIP project sheets for projects in Phase I shall be prepared and identify estimated total cost, cash expenditure timing, location, description, justification, funding allocation, and schedule. For the Phase II CIP projects, the CIP shall identify the need for the projects, along with their estimated total cost and funding allocation. Upon approval by the Board of Directors of the annual six-year CIP, staff is authorized to proceed with planning, design, construction, etc. of those projects that have budgets within the current fiscal year. The General Manager is authorized to redistribute funds between approved CIP projects as long as the total fiscal year budget is not exceeded. In addition, the General Manager is authorized to exceed the budget for specific CIP projects under the following conditions: a. For CIP projects less than or equal to $50,000, the cumulative amount of the specific CIP project expenditures does not exceed that authorized under Code of Ordinances Section 2.01, Authority of the General Manager. b. For CIP projects more than $50,000, the amount being authorized does not exceed the lessor of 25% of the specific CIP project budget amount or that authorized under Code of Ordinances Section 2.01, Authority of the General Manager. c. The total fiscal year CIP budget is not exceeded. 261 Capacity Name Fee (1) Capacity Fee Section 28.01 $7,411.09 Triad Capacity Fee $5,559.80 New Water Supply Fee $804.47 (1) This is based on a 3/4 inch water meter effective 7/1/17. Note: For a full listing of fees per meter size visit the District's website at: www.otaywater.gov/engineering/public-services. Then select "Fees and Deposits". Water Meter Capacity Fees 262 Glossary The Capital Budget contains terminology that is unique to public finance and budgeting. The following budget glossary provides assistance in understanding these terms. Acre-Foot: The volume of water that will cover one acre to a depth of one foot. One acre-foot equals 435.6 units or 325,850 gallons. Annexation Fees: When water service is requested for land outside the boundaries of the District, the land to be serviced must first be annexed. For sewer service the land must be annexed into an improvement district within the District. Assets: Resources owned or held by the District that have monetary value. Availability Fees: The District levies charges each year in developed areas to be used for general purposes for construction of facilities. This fee is levied in undeveloped areas to provide a source of funding for planning, mapping, and preliminary design of facilities to meet future development. Current legislation provides that any availability charge in excess of $10.00 per acre shall be restricted only for the purpose of constructing facilities in the improvement district in which it was assessed. Capacity Fee: A connection fee is charged when a new water meter is placed into service. This fee is a contribution of capital to either reimburse existing customers for the available capacity in the existing system, or to help finance planned future growth-related capacity improvements. Capacity Fee Revenues: These fees are earned by the Operating Budget as the Engineering Department supports expansion functions. Capital Budget: The portion of the annual budget that appropriates funds for the purchase of capital equipment items and capital improvements. These expenditures are separated from regular operating items, such as salaries, utilities, and office supplies. The Capital Budget includes funds for capital equipment purchases over $10,000, such as vehicles, furniture, machinery, computer systems, and special tools. The capital budget also includes funds for infrastructure related items over $20,000 (as explained below) which are distinguished from operating items according to their value and projected useful life. Capital Equipment: Fixed assets such as vehicles, marine equipment, computers, furniture, technical instruments, etc. which have a life expectancy of more than two years and a value over $10,000. Capital Expenditure: Capital expenditure or capital expense ("capex") is an expense where the benefit continues over a long period, rather than being exhausted in a short period. Such expenditure is of a non-recurring nature and results in acquisition of permanent assets. 263 Glossary Capital Improvement Program: A long-range plan of the District for the construction, rehabilitation and modernization of the District-owned and operated infrastructure. CWA: The County Water Authority was organized in 1944 under the State County Water Authority Act for the primary purpose of importing Colorado River water to augment the local water supplies of the Authority's member agencies. The Authority purchases water from MWD which imports water from the Colorado River and the State Water Project. Debt Service: The District's obligation to pay the principal and interest of bonds and other debt instruments according to a predetermined payment schedule. Desalination: The removal of dissolved minerals (including salts) from seawater or brackish water. Engineered water desalination processes, which produce potable water from seawater or brackish water, have become important because many regions throughout the world suffer from water shortages. Expenditures/Expenses: These terms refer to the outflow of funds paid or to be paid for an asset, goods or services obtained regardless of when actually paid for. (Note: An encumbrance is not an expenditure). An encumbrance reserves funds to be expended in a future period. Fiscal Year: Twelve-month term designating the beginning and ending period for recording financial transactions. The District has specified July 1 to June 30 as its fiscal year. Grants: Contributions or gifts of cash or other assets from another governmental agency to be used or expended for a specified purpose, activity, or facility. Capital grants are restricted by the grantor for the acquisition and/or construction of fixed assets. Operating grants are restricted by the grantor for operating purposes or may be used for either capital or operating purposes at the discretion of the grantee. Interest Income: Earnings from the investment portfolio. Per District Policy Number 25, interest income will be allocated to improvement districts each month based upon each fund’s prior month- ending balance. MWD and CWA Fixed Fees: These pass-through charges are calculated to recover the MWD’s and CWA’s fixed annual costs including the construction, operation and maintenance of aqueducts, and emergency storage projects. These fixed charge are based on the size of the meter. Reserve Fund: The District maintains Reserve Funds per the District’s policy for both designated and restricted balances. Designated Reserve Funds are “general use” funds designated by the Board. Restricted reserves are those that are legally set aside for a particular purpose and cannot be used for any other purpose. 264 Glossary Water Capacity Fees: Charges paid by customers to connect to a District water system for potable or recycled water service. Fees are determined by multiplying the demand factor for the meter size by the total of the District-wide capacity fee and applicable zone charge. 265 AF Acre-Foot/Feet AMR Automated Meter Reader/Reading APCD Air Pollution Control District ASCE American Society of Civil Engineers AWWA American Water Works Association CEQA California Environmental Quality Act CIP Capital Improvement Program CMAA Construction Management Association of America CSI California Solar Initiative CWA County Water Authority (San Diego) FCF Flow Control Facility FY Fiscal Year GAAP Generally Accepted Accounting Principles GIS Geographic Information System GPS Global Positioning System HWD Helix Water District ID Improvement District IID Imperial Irrigation District IMS Infrastructure Management System IRP Integrated Water Resources Plan LOPS Lower Otay Pump Station MBR Membrane Bioreactor MG Million Gallons MGD Million Gallons per Day MWD Metropolitan Water District O&M or O/M Operations and Maintenance OIS Otay Information System PB Pacific Bay PL Pipeline PS Pump Station RWCWRF Ralph W. Chapman Water Recycling Facility SANDAG San Diego Association of Governments SCADA Supervisory Control and Data Acquisition SDCWA San Diego County Water Authority SVSD Spring Valley Sanitation District VCP Vitrified Clay Pipe WD Water District WRMP Water Resources Master Plan WTP Water Treatment Plant List of Acronyms 266 Index Annual CIP Development Policy No. 6 261 Awards x-xiv Capital Budget Narrative 35-37 CIP Budget Basis 7 CIP Budget Calendar 9 CIP Budget Guide 1 CIP Budget Process 5-7 CIP Justification and Impact on Operating Budget 47 CIP Project Index 51-53 CIP Project Sheet Description 49-50 CIP Projects 55-260 CIP Reserve Funds 37 Current Economic Conditions 15 Demographics 10 District Formation 3 Economic Outlook 15 Fund Structure 8 Glossary 263-265 Index 267 Letter of Transmittal iii-x List of Acronyms 266 Mission Statement, Vision, Key Challenge, Statement of Values 2 Organizational Structure 4 Resolution No. 4336 xv-xvi San Diego Rainfall 14 Service Area 3 Service Area Assessed Valuation 10 Sewer Rate Comparison 13 Six-Year CIP Projects Summary by Source ($1,000s) 38 Six-Year CIP Projects Summary by Fund ($1,000s) 38 Six-Year CIP Projects by Source and Fund ($1,000s) 39-42 Six-Year CIP Projects Schedule 43-46 Strategic Plan Balanced Scorecard 19 Administrative Services 20-22 Finance 23-26 Water Operations 27-31 Engineering 32-34 Table of Contents i Ten Principal Taxpayers 11 Ten Largest Customers 11 267 The Future 17-18 Water Meter Capacity Fees 262 Water Comparison – Member Agency Water Rates 12 268