HomeMy WebLinkAboutCapital Improvement Program Budget FY 2014-2019 Otay Water District Adopted Capital Improvement Program Budget Fiscal Year 2014-2019 BOARD OF DIRECTORS Jose Lopez, Division 4 President Mitchell Thompson, Division 2 Vice President David Gonzalez, Jr., Division 1 Treasurer Gary Croucher, Division 3 Mark Robak, Division 5 MANAGEMENT TEAM Mark Watton General Manager German Alvarez Assistant General Manager Joseph R. Beachem Chief Financial Officer Rom Sarno, Jr. Chief, Administrative Services Geoff Stevens Chief Information Officer Rod Posada Chief, Engineering Pedro Porras Chief, Water Operations Table of Contents Page Letter of Transmittal ii GENERAL INFORMATION CIP Budget Guide . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 At-A-Glance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 General Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 Awards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 Current Economic Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 The Future . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 Demographics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 Organization Chart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 CIP Budget Calendar . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 CIP Budget Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 Resolution No. 4210 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 CAPITAL BUDGET SUMMARY Capital Improvement Program Narrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 Major CIP Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 CIP Projects in Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 CIP Reserve Funds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 CIP Funding Source and Category . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 CIP Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28 CIP Justification and Impact on Operating Budget . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 CIP Project Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31 Capital Purchases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36 CIP PROJECTS CIP Project Sheet Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37 CIP Project Index . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40 Capital Facility Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42 Replacement/Renewal Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86 Capital Purchase Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 144 Developer Reimbursement Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 158 APPENDIX Water Meter Capacity Fees . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 168 Glossary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 169 List of Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172 Index . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 173 i September 5, 2013 Honorable Board of Directors Otay Water District I am pleased to present the Otay Water District’s Capital Improvement Program Budget for Fiscal Years 2015-2019. This year’s budget continues to support the management plan to finance all of the District’s services, programs and capital needs during the 2014 fiscal year as well as the succeeding five fiscal years. San Diego County has very limited natural supplies of water and therefore must rely on imported water from Northern California and the Colorado River. The wholesale and retail water agencies serving San Diego County have always been challenged by their dependence on imported water and continue implementing programs to create a more reliable, robust water system, one that will also increase water independence. Programs to secure more water, as well as a more reliable water supply, are expensive and represent a contributing factor to increasing costs. Not only are the regional water providers faced with the ongoing challenge of a reliable supply, but they are also challenged with significant cost increases and the need to provide high quality water. The District must find the best solutions that balance these challenges. The tool the District has used as its guide to accomplish this is the Strategic Management Performance Plan. The District’s first strategic plan was developed in 2003 and it has been updated every three years since then. The current plan covers Fiscal Years 2012-2014 and can be found on pages 7-14 of the District’s Adopted Operating and Capital Budget for Fiscal Year 2013-2014. 2012-2014 Strategic Plan We are now entering the third year of the 2012-2014 Strategic Plan. As with previous plans, the focus has been on the District’s transformation from a growth-centric to a maintenance- based organization. Where growth had been a significant focus in the early years of the ii District’s existence, today we are primarily focused on managing long-term maintenance and replacement of infrastructure. As an organization matures, fewer resources are needed to support growth, but the effort to maintain and improve infrastructure and assets increases. Over time, an organization derives income more from customer rates and less from developer fees. At this stage in its development, increased maintenance and replacement costs place pressure on customer rates. To balance the customer’s interest in minimizing rate increases while also maintaining an organization’s infrastructure investments and a strong financial position, it must place greater emphasis on internal efficiency and the development of technology assisted best practices. In effect, an organization must use investments in technology to do more with the same or even fewer resources. A goal of the District’s earlier strategic plans included capitalizing on the technology investments and utilizing those technologies to continually improve efficiency and productivity. The success of this approach is evidenced by the gains in efficiency and by the reduction in staffing, even though the customer base has grown in recent years. The following charts show that since 2007, the District has reduced its staffing by 31.75 full-time equivalents or 18.2% while the number of customer accounts has increase by 1,694 during the same time period. 17 4 . 7 5 17 2 . 7 5 16 8 . 7 5 16 6 15 9 15 6 14 8 14 3 52,615 54,309 40,000 45,000 50,000 55,000 60,000 0 20 40 60 80 100 120 140 160 180 200 2007 2008 2009 2010 2011 2012 2013 2014 Ac c o u n t s Em p l o y e e C o u n t FISCAL YEAR Employee Count and Number of Accounts iii The District has been able to continue absorbing some of the pass-through costs from our water suppliers, the San Diego County Water Authority (CWA) and Metropolitan Water District (MWD), through increased efficiency and improved productivity. This helps to address customer concerns about rising water rates. The chart below shows that since 2007, the pass-through costs have increased 87% while the District’s water rates have increased 76.6%. Based on an annual survey of water and sewer rates conducted by District staff, Otay continues to be one of the lower cost providers in San Diego County. The District has the 11th lowest water rate out of the 23 member agencies in San Diego County and the 6th lowest sewer rate out of the 29 sewer service providers in San Diego County. The results of the water and sewer surveys are shown on page 33 and 34 of the District’s Adopted Operating and Capital Budget for Fiscal Year 2013-2014. In this and coming years, the District will continue its efforts to improve business processes to further increase efficiency and productivity through adherence to the 2012-2014 Strategic Plan. Today, the District provides water service to nearly 48,911 potable and 709 recycled water customers within approximately 125.5 square miles of southeastern San Diego County. All of the potable water sold to customers is purchased from CWA. Fifty eight percent of this water is in turn purchased from the region’s primary water importer, MWD. The District has 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 2007 2008 2009 2010 2011 2012 2013 2014 87.0% 76.6% Pass-Through Costs vs. District Rate Increases Pass Through Costs Otay Water Rate Increase iv been proactive in reducing our dependence on MWD water treatment facilities. For example, in 2009, the District entered into an agreement with the CWA that allowed our neighboring Helix Water District to treat imported water on behalf of the District at their Levy Water Treatment Plant. This has brought regional water treatment closer to our customers, which reduces dependence on water treatment facilities located outside of San Diego County. The District also owns and operates a wastewater collection and recycling system to provide public sewer service to approximately 4,657 homes and businesses. Wastewater is collected and delivered to the Ralph W. Chapman Water Recycling Facility (RWCWRF), which is capable of reclaiming wastewater at a rate of 1.3 million gallons per day. In addition to the Chapman facility, the District purchases up to 6 million gallons per day of recycled water from the City of San Diego’s South Bay Water Reclamation Plant. Recycled water from these two sources is used to irrigate golf courses, schools, public parks, roadway landscapes, and other approved uses in the City of Chula Vista. The use of recycled water reduces dependence on imported supplies and provides a local supply that diversifies District resources. BUDGET SUMMARY The Otay Water District’s operating expenditures consist of three major sectors: potable water, recycled water, and sewer, budgeted at $86,101,100 for Fiscal Year 2014. Revenues from potable and recycled water are projected to be $75,373,600, about $5,916,800 (7.8%) more than the Fiscal Year 2013 budget. Water sales volumes are expected to increase slightly, by less than 1% over FY 2013 actual sales, as the economy is slowly improving, even when efforts to promote water conservation continue without significant increases in water sales, rate increases are essential to offset the higher wholesale cost of water. Sewer revenues are projected to be $2,701,600, about $146,400 more than Fiscal Year 2013. This increase from higher sewer rates is primarily to cover $18.6 million of capital projects over the next six years. The remaining budgeted revenues of $7.7 million come from various special fees, assessments, and miscellaneous income. Significant aspects of the Operating Budget are:  A balanced budget meeting the goals of the Strategic Plan.  The use of an economist to project growth for the region.  An updated six-year Rate Model to ensure sound financial planning and reserve levels. v  Ongoing water supply rate increases of 7.7% from MWD and CWA because of the high cost of supply programs, higher energy costs, and operating costs.  Implemented rate increases in potable, recycled water, and sewer. This included pass-through rate increases from CWA and the County of San Diego.  In efforts to minimize rate increases, the District has again reduced staffing levels from 148 full-time equivalent positions to 143.  Of San Diego County’s 23 water agencies, Otay’s water rates are below the county- wide average. The Fiscal Year 2013-14 Capital Improvement Program (CIP) Budget consists of 63 projects and a budget of $14 million. The total estimated capital needs for Fiscal Years 2015 through 2019 is $93 million. The CIP budget emphasizes long-term planning for ongoing programs while functioning within fiscal constraints and population growth. This year’s CIP budget decreased by $4.2 million compared to last year’s projection, due to the completion of some large projects as well as the deferral of projects to match the timing of land development. The coming years will continue to pose challenges for those in California’s water community. For instance, it is uncertain if the challenges facing the Sacramento-San Joaquin Bay Delta, the source of 30 percent of Southern California’s water supply, will be addressed and at what cost to end users. The District as a member of the CWA is well positioned for water coming from the Colorado River thanks to the QSA Agreement. As the cost of water has increased to the retail customer, sales have decreased. As one would expect, water sales reductions have impacted revenues and will continue to affect the District’s finances. This sales decrease has now ended and the District is seeing moderately increased water sales. Our success as an organization is significantly enhanced by the practices and policies put in place by the Board of Directors to ensure the strength and stability of the District. We are fully confident that with these policies and practices, supported by dedicated and talented staff, we will achieve continued success as an organization and, thus, assure the well-being of the people we serve. In adopting this budget, the challenges presented this year were met by the Otay Water District Board of Director’s resolve to keep the stability and financial strength of the District as one of its highest priorities. vi AWARDS AND ACKNOWLEDGMENTS  The Government Finance Officers Association of the United States and Canada (GFOA) presented a Distinguished Budget Presentation Award to Otay Water District, California for its annual budget for the fiscal year beginning July 1, 2012. In order to receive this award, a governmental unit must publish a budget document that meets program criteria as a policy document, as an operations guide, as a financial plan, and as a communications device.  The Government Finance Officers Association of the United States and Canada (GFOA) also presented the Otay Water District with two special recognition awards, Outstanding as a Policy Document and Outstanding as a Communication Device, for its annual budget for the fiscal year beginning July 1, 2012.  The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Certificate of Award for Excellence in Operating Budgeting for Fiscal Year 2012-2013.  The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Certificate of Award for Excellence in Capital Budgeting for Fiscal Year 2012-2013. In conclusion, this budget reflects the vision of the Board of Directors of the Otay Water District, its management, and its employees. We will continue to strive to make improvements in our budget processes, including an extensive review and analysis of projections for revenues, expenditures, capital projects, and reserves. I would like to thank all the staff involved in this process for the efforts put forth in the preparation of this budget to ensure a successful outcome. To the Board of Directors, we acknowledge and appreciate their continued support and direction in achieving excellence in financial management and District operations. Mark Watton, General Manager vii CIP Budget Guide The District views the Capital Improvement Program (CIP) Budget as an essential tool for proper financial management of the CIP projects. The District manages growth and maintenance of assets through this program. This CIP budget is developed with input from the various project managers throughout the organization and is adopted prior to the start of each fiscal year for the current fiscal year and five subsequent years. It is designed and presented for the general needs of the District, its staff, and citizens. It is a comprehensive and balanced financial plan. This plan features the CIP budget based on demands for services and the impact on the District’s financial status and future plans. The budget book is divided into the following sections. General Information The introductory section contains an overview and general information about the District including the organization chart and awards received. Also included are the budget calendar, a description of the budget process, and the resolution adopting the budget. Capital Budget Summary The Capital Budget Summary consists of an overview of the District’s CIP, including how the Water Resources Master Plan (WRMP) is used to modify the CIP each year based on the latest set of assumptions and criteria. Also included are highlights of the major CIP projects that are completed, in construction, or in design. Additionally, this section contains a review of the CIP reserve funds and funding sources, a six-year listing of CIP project expenditures, project justification and impact on the Operating Budget, project schedules, and the capital purchases budget. CIP Projects This section contains the project sheet description and project sheets for each CIP project. These sheets are developed by the project manager and contain critical information for the management of these projects. The projects are divided into four categories: Capital Facility Projects, Replacement/Renewal Projects, Capital Purchase Projects, and Developer Reimbursement Projects. Appendix The last section consists of the Water Meter Capacity Fee Schedule, a Glossary of budget and financial terms, a List of Acronyms used in this budget book, and an Index. 1 At-A-Glance Mission Statement To provide high value water and wastewater services to the customers of the Otay Water District in a professional, effective, and efficient manner. History The Otay Water District was formed in 1956 to serve as a public water and sewer agency, authorized as a California special district, under the provisions of the Municipal Water District Act of 1911. The District’s ordinances, policies, taxes, and rates for service are set by five Directors elected by voters in their respective geographic area. The District joined the San Diego County Water Authority (CWA) in September 1956 to acquire the right to purchase and distribute imported water throughout its service area. The District is also responsible for the collection, treatment, and disposal of wastewater from a portion of the northern region of the District. In 1980, the District started operation of the Ralph W. Chapman Water Recycling Facility (RWCWRF) and in May, 2007 a new source of recycled water from the City of San Diego was obtained, allowing the Otay Water District to supply 13% of total water demand with recycled water. Service Area The District's boundaries encompass an area of approximately 125 square miles in San Diego County, lying immediately east of the City of San Diego metropolitan area and running from the City of El Cajon south to the international border, abutting the cities of El Cajon and La Mesa and encompassing most of the City of Chula Vista and a small portion of the City of San Diego. Organizational Structure The General Manager reports directly to the Board of Directors. The Assistant General Manager along with District management oversees day-to-day operations. The Assistant General Manager oversees the five departments of Administrative Services; Finance; Information Technology and Strategic Planning; Water Operations; and Engineering. These and other lines of reporting are shown on the organization chart on page 11. 2 General Information For Fiscal Year 2014, the District will have a staff of 143 full-time equivalent employees under the leadership of the General Manager. The District provides water service to approximately 53% of its expected ultimate deliveries with a population of more than 211,000 people. This percentage increases as the District's service area continues to grow to ultimate build-out. The District is projected to deliver approximately 28,985 acre-feet of potable water to 49,150 potable customer accounts and to ultimately deliver, by 2035, 56,600 acre-feet of potable water to serve 285,000 people or 69,000 accounts. The growth rate, as projected by the San Diego Association of Governments (SANDAG) for the Chula Vista area of San Diego County, is approximately 1.8% per year over the next decade. Using historical data and considering current economic conditions, staff has moderated this projection to a growth rate of 0.47% for Fiscal Year 2014. Since 1956, the District has provided high quality water to a semi-arid region of the southeastern San Diego County. In 1971, the District constructed a small collection and treatment plant for sewer in the northern section of the District, and in 1980 the District opened the Ralph W. Chapman Water Recycling Facility (RWCWRF). For over 50 years, the available supply of water has helped transform the District service area from a mostly scrub and cactus-covered backcountry into a balance of diverse environments. Recycled water from the RWCWRF is used to irrigate golf courses, schools, public parks, roadway landscapes, and various other approved uses in eastern Chula Vista. The RWCWRF is capable of recycling wastewater at a rate of 1.3 million gallons per day (1,200 acre-feet per year). The District is also in partnership with the City of San Diego to beneficially reuse an additional 2,916 acre-feet per year of recycled water for Fiscal Year 2014, and ultimately up to 6,720 acre-feet per year. The District continues to be the largest retail provider of recycled water in the County of San Diego. The District also owns and operates a wastewater collection system providing public sewer service to approximately 4,657 customer accounts within the Jamacha drainage basin. The sewer service area covers approximately 8,797 acres, which is about 11% of the District’s total service area. Residential customers comprise 97% of the sewer customer base. 1. Carlsbad Municipal Water District 2. City of Del Mar 3. City of Escondido 4. Fallbrook Public Utility District 5. Helix Water District 6. City of National City 7. City of Oceanside 8. Olivenhain Municipal Water District 9. Otay Water District 10. Padre Dam Municipal Water District 11. Camp Pendleton Marine Corps Base 12. City of Poway 13. Rainbow Municipal Water District 14. Ramona Municipal Water District 15. Rincon del Diablo Municipal Water District 16. City of San Diego 17. San Dieguito Water District 18. Santa Fe Irrigation District 19. South Bay Irrigation District 20. Vallecitos Water District 21. Valley Center Municipal Water District 22. Vista Irrigation District 23. Yuima Municipal Water District 24. Lakeside Water District San Diego County Water Agencies 3 DISTINGUISHED BUDGET PRESENTATION AWARD The Government Finance Officers Association (GFOA) presented a Distinguished Budget Presentation Award to the District for its annual budget for the fiscal year 2012-2013. In order to receive this award, a governmental unit must publish a budget document that meets program criteria as a policy document, as an operations guide, as a financial plan, and as a communications device. This award is valid for a period of one year only. We believe our current budget continues to conform to program requirements, and we are submitting it to GFOA to determine its eligibility for another award. In addition, the Finance Department received two special recognitions for the FY 2012-2013 budget: 1) Outstanding as a Policy Document, and 2) Outstanding as a Communications Device. These special recognitions are rarely given to agencies. In fiscal year 2012, 10 agencies received the special recognition for a Communications Device and 10 agencies received the special recognition for a Policy Document out of 1,376 applicants. 4 Financial Awards The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Certificate of Award for Excellence in Operating Budget for Fiscal Year 2012-2013. The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Certificate of Award for Excellence in Capital Budget for Fiscal Year 2012-2013. 5 Award Otay Water District has been awarded the 2013 Tyler Public Sector Excellence Award. The award recognizes the achievement of a high level of excellence in leadership, innovation, and excellence in the use of Tyler’s ERP system for business solutions. 6 Current Economic Conditions The District services the needs of a growing population by purchasing water from the San Diego County Water Authority (CWA). CWA purchases its water from the Metropolitan Water District of Southern California (MWD) and the Imperial Irrigation District (IID). The District takes delivery of the water through several connections of large diameter pipelines owned and operated by CWA. The District currently receives treated water from CWA and from Helix Water District (HWD) by contract with CWA. In the Southern region, in addition to the treated water deliveries from CWA, the District has an emergency agreement with the City of San Diego in the case of a shutdown of the main treated water source. Through innovative agreements like this, benefits can be achieved by both parties by using excess capacity of another agency and diversifying local supply, thereby increasing reliability. For several decades, the District has collected and recycled wastewater generated within the Jamacha drainage basin and pumped the recycled water south to the Salt Creek basin where it is used for irrigation and other non-potable uses. However, the demand for recycled water out-paced the supply, requiring the District to supplement the limited supply of recycled water with potable water. Through the agreement with the City of San Diego, the District has discontinued supplementing its recycled demand with potable water. Once again, this decreases the demand on potable water and increases reliability of the District’s supply. The District’s sewer service area is growing at a slow but steady rate of approximately 0.2% each year. Most of this growth is from small development projects or homeowners converting their septic system to sewer because of environmental issues. The District’s water service area was one of the fastest growing regions in the nation. During the past decade, the population of the service area has nearly doubled. It is estimated that the District is currently serving approximately 211,000 residents. The local and national recovery from the global recession of 2009 has been slow; however, due to San Diego County’s diverse economy, it is forecasted to do better than most of the nation. Over the past 10 years, the District has added more than 6,768 new customer connections, with 2,326 occurring in Fiscal Year 2004. In Fiscal Year 2013, the District sold 284 meters which is an average of 24 meters per month. 7 The Future The District continues to use the challenges presented by growth to create new opportunities and new organizational efficiencies. By utilizing and continuing to refine its Strategic Business Plan, it has captured the Board of Director’s vision and united its staff in a common mission. The organization has achieved a number of significant accomplishments based on its successful adherence to its Strategic Business Plan. The District is not only poised to continue successfully providing an affordable, safe, and reliable water supply for the people of its service area, but is set to reap the rewards of greater efficiencies and economies of scale. Future Development As in the previous fiscal year, the District employed an Economist to provide an Economic Outlook of the National Economy, San Diego County’s Economy, the future of South San Diego County and an overview of the Otay Water District. Projections of future development indicate that the ratio of multi-family units will increase because the remaining land is zoned for multi-family development. Projected Total For Sale and Rental Units Otay Water District Service Area FY 2014 through FY 2019 Project FY 14 FY 15 FY 16 FY 17 FY 18 FY 19 Total Total Single-Family Units 103 273 310 510 513 500 2,209 Total Condominium 140 383 383 400 500 500 2,306 Total Rental 839 691 580 250 250 250 2,860 Total Units 1,082 1,347 1,273 1,160 1,263 1,250 7,375 % Multi-Family 90% 80% 76% 56% 59% 60% 70% Source: The London Group Realty Advisors, April 2013 Using the economist report, the District’s engineering staff projects that over the next six years the District will sell another 3,424 meters which translates to 5,155 equivalent dwelling units (EDUs). These projections have been incorporated in the Five-Year Forecast on pages 52-53 of the District’s Adopted Operating and Capital Budget for Fiscal Year 2013-2014. Projected Meter Sales in EDUs 354 647 801 1,050 1,108 1,195 0 200 400 600 800 1000 1200 1400 FY 14 FY 15 FY 16 FY 17 FY 18 FY 19 Me t e r s 8 The Future San Diego County Water Supply San Diego County imports about 90 percent of its water from the Colorado River and Northern California. Since these sources face legal and environmental constraints, the region has been exploring other ways to ensure an adequate water supply, including increased water recycling, more aggressive conservation programs, increased water storage, groundwater desalination and seawater desalination. Carlsbad Desalination Project The District’s water wholesaler, the San Diego County Water Authority, voted on November 29, 2012, to approve a water purchase agreement with Poseidon Resources Corporation (Poseidon). Under the water purchase agreement, the Water Authority will purchase 48,000 to 56,000 acre-feet of water annually from the desalination plant located in Carlsbad, California. The plant is expected to produce up to 50 million gallons of water a day beginning in 2016 and will generate enough water to meet 7 percent of the region’s demand. The total price for the desalinated water, including related upgrades to the Water Authority’s pipelines and treatment plant, is projected to start between $2,041 and $2,290 per acre-foot (in 2012 dollars). An acre-foot is approximately 325,900 gallons, or enough to supply two typical single-family households of four for a year. Rosarito Desalination and the Otay Mesa Conveyance and Disinfection System Projects The Rosarito Desalination Project is comprised of a 100 million gallons per day seawater reverse osmosis desalination plant, together with a pump station and pipeline, to convey water to Tijuana and excess production water to the District. This will be the first cross-border water supply project of its kind and requires public messaging to inform key stakeholders and the public of the significance of the Project. If successful, this Project will start delivering water to District customers by early 2018. The Project includes the construction of facilities on the U.S. side to include a large diameter pipeline 3.5 miles long, a pump station, a disinfection facility and the use of the Roll Reservoir in Otay Mesa. Carlsbad Desalination Project rendering Rosarito Desalination Project rendering 9 Demographics The District boundaries shown in the map encompass an area of approximately 125.5 square miles in San Diego County, located immediately east of the City of San Diego metropolitan area and running from the City of El Cajon south to the international border. SANDAG creates and maintains a tremendous quantity of demographic, economic, land use, transportation and criminal justice information about the San Diego region. The demographic data include population characteristics like age, education, and employment. Because of the overlapping of the District’s service area with the cities of Chula Vista, La Mesa, El Cajon, and the unincorporated areas of Spring Valley and Jamul, the following demographic data is from the City of Chula Vista as it most closely represents the District. Demographics of the City of Chula Vista The population of Chula Vista has grown from 83,927 in 1980 to 249,382 in 2012. This represents an increase of 165,455 in the past 30 years or a 197.1% increase, which correlates to the District’s rapid growth for the same period. As shown in the table below, the ethnic/racial makeup of the City consists of 58% Hispanic, 20% White, 14% Asian, 4% Black, and the remaining 7% is all other groups. In a recent economic forecast conducted by the London Group Reality Advisors, the District’s median age is 35.5 and 33.0% of adults have a four-year degree or higher. The average household income is $96,791 and the median household income is $80,479. 2012 City of Chula Vista Demographics Population 249,382 Persons/Household 3.17 Ethnic/Racial makeup Hispanic 58% White 20% Asian 14% Black 4% Other 7% Median Age 35.5 Percentage with 4 year degree or higher 33.0% Average Household Income $ 96,791 Median Household Income $ 80,479 Source: SANDAG; The London Realty Group, Claritas Demographics 10 ORGANIZATION CHART District Position Count - (143 Positions) GENERAL MANAGER (5) Assistant General Manager Administrative Services (16) Finance (29) Water Operations (61) Engineering (20) Human Resources Purchasing and Facilities Safety and Risk Administration Water Conservation Controller and Budgetary Services Treasury and Accounting Services Customer Service IT Applications IT Operations GIS Water System Operations Utility Maintenance/ Construction Planning Design Environmental Water Resources Public Services Survey Inspection Construction Citizens and Customers Information Technology and Strategic Planning (12) BOARD OF DIRECTORS Meter Reading 11 CIP Budget Calendar Each year, the Engineering Department prepares budget instructions for distribution to the departments. These instructions give direction and deadlines for each phase of the CIP budgeting process. The CIP Budget Process is explained on pages 13 and 14. January-February March April May July–January 1/10/13 Budget workbooks and instructions for the Operating and Capital Budget are distributed to departments. 1/10/13-2/22/13 Departments begin CIP Budget Process which includes:  Review existing FY 2013 CIP Projects.  Remove any CIPs that are complete or will not be budgeted in the CIP budget the next six-years.  Estimate the total project-to-date expenditures through 6/30/13 for each CIP.  Adjust the annual amount for the remaining CIPs when appropriate and include justification for the changes to each year’s changes.  Develop CIP project cost and schedules, unless more specific information is available.  Submit new CIP projects for consideration. 3/5/13 Engineering Department reviews all CIP budget requests with Assistant General Manager and adjusts, if necessary. 3/13/13 Engineering reviews and prepares CIP budget and submits to finance for review and to incorporate into rate model to determine proposed rates. 3/22/13 CIP budget presented to the General Manager for review and comments. 4/2/13 Review assumptions and rates with Chiefs, Assistant General Manager, and General Manager. 4/11/13 General Manager performs preliminary review of budget. 5/7/13 Final review of proposed budget and rates is completed by the General Manager. 5/14/13 Board of Directors adopts Fiscal Year 2013-2014 Operating and Capital Budget. 7/17/13 Proposition 218 Rate Notices mailed 9/4/13 Proposition 218 Public hearing and Board approval of Rates 1/1/14 Water and Sewer Rate Increase 12 CIP Budget Process The District has integrated the Capital Improvement Program (CIP) Budget and the Operating Budget. Appropriate budget amounts are determined by using historical data of operations, growth, developers' input, SANDAG projections, and the economic outlook. Additionally, these budgets are developed based on the District's Water Resources Master Plan and the Strategic Business Plan, both long-range planning tools. To assure reliable, high-quality service to the growing customer base, the District has committed to a number of long-range strategies that drive the budgeting process. The strategies and assumptions used to develop the District's integrated budget are:  An average projected long-term growth rate of 1.7%.  Pass-through rate increases for costs imposed on the District by the wholesale water providers.  Accurate projection of capital budget needs including replacement needs.  Reserve funding in accordance with the Reserve Policy to meet future growth demands.  Funding of the Strategic Plan initiatives categorized into the Balanced Scorecard perspectives.  Avoidance of rate spikes by leveling rate increases over a six-year period. In January, the Engineering Department (Engineering) issues budget instructions for the CIP budget process. The project manager use the CIP Budget module system to review and estimate project expenditures to the end of the fiscal year. Projects may have been added, deleted or modified due to increased costs, changes in the scope of work, unanticipated events or emergencies. The CIP Budget Process ensures that all projects are reviewed and updated to reflect any changes and are included in the District’s Rate Model and Financial Forecast. Engineering reviews each project budget for accuracy, ensures that projects are categorized into the appropriate project types and funding sources, and then prioritizes projects based on need and timing. Projects are also reviewed to see if any grant funding is available and if so, estimated amounts are included as a funding source to these projects. In March, Engineering compiles the Preliminary CIP Budget and submits the consolidated CIP list to the Assistant General Manager and the General Manager for review and comments. Engineering also updates the five-year projection of CIP expenditures and provides it to the Finance Department (Finance) to incorporate into the District’s Rate Model to determine proposed rates. 13 CIP Budget Process Finance inputs the operating revenues and expenditures, CIP expenditures, reserve funding, and reserve levels into the District’s Rate Model. Inflators for cost and volume changes are input into the Rate Model and cost and rates are calculated for the current fiscal year plus five subsequent years. Using this comprehensive modeling tool, the District is able to smooth future rate increases, determine when debt should be issued, and maintain all of the reserve levels in accordance with its Reserve Policy. In the spring, the District presents the Strategic Plan to the Board of Directors for adoption. This is followed by a special board meeting in May where the District presents the Preliminary Operating and Capital Budget to the Board of Directors for adoption. The adoption of the Strategic Plan and Operating and Capital Budget on an annual basis gives the District its direction for the following fiscal year. The District is accounted for and budgeted as an enterprise fund and conforms to the guidelines of generally accepted accounting principles (GAAP). The General Manager has the authority to transfer appropriations within the budget allocations or may request that the Board of Directors increase the current budgeted funds. The Operating and Capital Budgets are intended as a financial guide and may be modified by the Board of Directors during the 2014 fiscal year. Water and Sewer Rates Strategic Plan MWD/CWA & Sewer Rates Year End Balances Operating Budget Input CIP Budget Input Assumptions Interest Rates Inflation Growth Sales Targets Debt Coverage Reserve Levels Rate Model Operating Budget CIP Budget 14 15 16 Capital Improvement Program The District provides water service to a population of approximately 211,000 which is expected to ultimately increase to 285,000 by the year 2035. This growth, as well as the maintenance of existing assets, requires long-term capital planning. The process is dynamic, due to the evolving needs of the community, the water supply issues, and changing regulations. As such, capital planning is a significant part of the District’s overall strategic planning. The capital planning process involves identifying current needs, future needs, and prioritizing them based on certain operating assumptions. The primary objective of this planning effort is to support an orderly and efficient program that categorizes the projects as expansion, new water supply, replacement, or betterment, while maintaining a stable long-range financial plan. The Adopted Capital Improvement Program (CIP) Budget for Fiscal Year 2013-2014 is $14 million with the six-year CIP projections totaling $107.1 million. This CIP Budget Notebook contains the project descriptions, project justifications, estimated expenditures, and estimated funding requirements for all the identified projects for fiscal years 2014 through 2019. Assumptions and Criteria The CIP is developed based on the District's Water Resources Master Plan, the District’s Waste Water Master Plan, historical data, growth, developers' input, SANDAG projections, and the long- term economic outlook as reported by the District’s Economist. The Water Resources Master Plan was built using several major assumptions and design criteria as follows: 1. Utilizing historical water demands for each land use type in the District to calculate future demands. 2. Using maximum day peaking factors that vary with demand level. 3. Utilizing land use as planned by the City of Chula Vista. 4. Providing ten days of emergency water supply through a maximum of five days in covered reservoirs and a minimum of five days from interconnections with adjacent agencies. 5. Inclusion of emergency operational storage to meet the five-day covered storage requirement into the ten-day outage supply requirement. The Wastewater Master Plan is a comprehensive plan that considers required improvements to the District’s wastewater collection system and identifies a preferred strategy for future wastewater management and recycled water generation and purchase. The scope of the plan is as follows: 1. Update of the wastewater flow projections for the Jamacha Basin. 2. Analysis of the wastewater collection system using the District’s existing wastewater system hydraulic model to identify existing system deficiencies and to identify system 17 Capital Improvement Program improvements and costs that will correct deficiencies and accommodate projected wastewater flows. 3. Analysis of existing and projected recycled water demands to determine additional recycled water supplies that are needed currently and through 2030. 4. Review of potential sources and costs of additional recycled water supplies. 5. Identification and analysis of local and regional options available to the District for future wastewater management and recycled water generation and purchase, to identify a preferred strategy or strategies. 6. Development of a capital improvement program for the recommended collection system and wastewater facility improvements. CIP Justification and Impact on Operating Budget Each year beginning in January, the engineering department reviews all CIP project budgets and evaluates whether it is required due to growth (Expansion), new water sources (New Supply), improvements or upgrades (Betterment), or to replace an existing asset (Replacement). As projects are completed and placed into service, there may be an impact on the Operating Budget by increasing costs in the areas of maintenance, energy, or chemicals. This schedule is shown on page 30 in this section. 1485-1 Reservoir 1485-2 Pump Station 18 Capital Improvement Program Capital Purchase and Facility Projects All capital expenditures, including capital facility projects and capital purchases, are accounted for in the CIP. Capital purchase projects are non-recurring operating expenditures for assets that cost more than $10,000 each and have an estimated useful life of two years or more. Capital purchases include vehicles, office equipment, furniture, and field equipment expenditures. The Fiscal Year 2014 Board approved capital purchases are detailed on page 36. Capital Facility Projects are items that exceed $10,000 or $20,000 for infrastructure related items (as defined under Capital Equipment on page 170 of the Glossary) and have a useful life of at least two years. A detailed listing of the Capital Facility Projects are detailed on page 28. The CIP projects are identified and are prioritized based on the following criteria: 1. Safety, restoration of service, immediate obligation, Board directed, or critical system need. 2. System upgrades or requirements to maintain system reliability in the next few fiscal years. 3. Need to meet the future growth of the system. 4. Project requirement may be reduced in capacity or may have low probability of need in the future. The following are the four categories of CIP projects: New Water Supply Facilities required to support new sources of water are funded from new supply fees or user rates. Expansion Facilities required to support new or future users are funded from capacity fees or user rates. Betterment Facilities required because of inadequate capacity or new requirements that benefit existing users are funded from availability, betterment fees, or rates. Replacement Facilities required to renew or replace existing facilities that have deteriorated or have exceeded their useful life are funded from user rates. 19 Major CIP Projects Capital Improvement Projects The 2014 Fiscal Year CIP Budget contains 63 projects. The cost of the work planned for Fiscal Year 2014 is $14 million. Of the 63 projects planned for Fiscal Year 2014, only five are designated as reimbursable projects with estimated costs totaling $154,000. These projects are built by developers and reimbursed by the District. The following shows how the $14 million of projects are broken down into four categories: 1. Capital facility projects $ 4.4 million 2. Replacement or renewal projects $ 7.8 million 3. Capital purchase projects $ 1.6 million 4. Developer reimbursement projects $ .2 million The Six-Year CIP and Fiscal Year 2014 Capital Budget are consistent with the District's Water Resources Master Plan, the District’s Waste Water Master Plan, current capacity fees, and the District's Strategic Management Performance Plan. 20 CIP Projects in Construction Calavo Gardens Sewer Rehabilitation (S2019, S2020, S2022, S2026)  Replacement of 4,500 linear feet of sewer  Manhole rehabilitation/replacement  Capacity upgrades  New flow control and diversion vault for Calavo Lift Station  $3.35M Budget  Start: February 2012  Projected Completed: June 2013 Final paving of private road along Avocado Boulevard Installation of grating supports in diversion vault at Rancho San Diego Shopping Center 21 CIP Projects in Construction 624-I Reservoir completed construction Reservoir 624-1 Floating Cover Replacement (P2477)  Install new reinforced polypropylene Geomembrane floating reservoir cover  $1.0M Budget  Start: November 2012  Project Completed: June 2013 22 CIP Projects in Construction Hunte Parkway 30-Inch Potable Pipeline (P2514) Final paving on Hunte Parkway  Installation of 2,250 linear feet of polyurethane coated steel pipe  $1.69M Budget  Start: April 2012  Project Completed: June 2013 23 CIP Projects in Construction Orange Avenue/I-805 12-Inch Potable Water Installation (P2513) In s t a l l a t i o n o f 1 0 -In c h h o t t a p c o n n e c t i on a t M e l r o s e .  Installation of new 12-Inch water line to replace the Palomar Avenue line during Palomar bridge replacement by Caltrans  $1.30M Budget  Start: January 2013  Estimated Completion: August 2013 24 CIP Projects in Construction  Remove and replace deteriorating reservoir coatings and structural modifications  $1.53M Budget  Start: March 2013  Estimated Completion: August 2013 803-3 and 832-2 Reservoir Interior/Exterior Coating and Upgrades (P2518/P2519) 803-3 Reservoir interior coating progress 832-2 Ventilation and interior blasting equipment 25 (Thousand $000s)FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total Beginning Balance 42,560$ 36,622$ 36,196$ 34,201$ 30,590$ 32,878$ Capacity Fees 3,114$ 5,717$ 7,225$ 10,029$ 10,931$ 12,187$ 49,202$ Debt financing - 2,875 3,575 1,570 - - 8,020 Grants 92 17 627 500 - - 1,236 Interest 150 160 249 297 538 824 2,218 Betterment Charges 866 885 903 920 936 950 5,460 Temporary Meters 416 416 417 418 421 422 2,510 Availability (Betterment Portion)513 523 533 543 552 561 3,225 New Supply Fee 322 606 773 1,043 1,134 1,259 5,136 COPS 2010B Reimbursement 3,699 6,316 9,146 759 759 759 21,437 Transfer from General Fund 8,558 11,578 10,130 9,444 11,418 9,799 60,926 Interfund Transfers 65 65 69 17 31 45 292 Total Sources 17,792 29,157 33,646 25,540 26,718 26,806 159,661 CIP Projects 13,863 19,761 25,671 18,990 14,063 14,743 107,091 Betterment Fees for Maintenance 777 783 791 802 812 824 4,789 Debt Service 7,799 7,803 7,930 8,099 8,282 8,445 48,358 Developer Services 1,291 1,237 1,247 1,260 1,272 1,286 7,593 Total Uses 23,730 29,584 35,640 29,151 24,430 25,298 167,830 Net Sources (Uses)(5,937)$ (427)$ (1,995)$ (3,611)$ 2,288$ 1,508$ (8,170)$ Ending Balance 36,622$ 36,196$ 34,201$ 30,590$ 32,878$ 34,386$ The CIP Reserve Funds presentation, shown on the following pages,is designed to provide an understanding of how the funding of CIPs is expected to financially influence the District over the next six years. The financial impacts are based on CIPs and their funding sources, including fund transfers in accordance with the District’s Reserve Policy,and planned debt issuances. This data is captured in the District’s Rate Model on an annual basis in order to make these projections. CIP Reserve Funds $0 $10,000 $20,000 $30,000 $40,000 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Reserve Fund Balances, in thousands ($) New Supply Expansion Replacement Betterment 36,622 36,195 34,201 30,590 32,878 34,386 26 CIP Funding Source (Thousands $000s)FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 TOTAL Expansion 1,882$ 1,571$ 2,758$ 949$ 3,707$ 12,381$ 23,249$ Betterment 2,219 5,478 8,925 5,725 4,010 253 26,609 Replacement 9,063 10,992 10,787 9,116 3,706 2,109 45,773 New Supply 700 1,720 3,200 3,200 2,640 - 11,460 TOTAL 13,863$ 19,761$ 25,671$ 18,990$ 14,063$ 14,743$ 107,091$ CIP Category (Thousands $000s)FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 TOTAL Capital Facility Projects 4,362$ 8,572$ 16,342$ 13,932$ 6,656$ 9,518$ 59,382$ Replacement/Renewal Projects 7,730 10,115 5,725 3,508 1,793 1,985 30,856 Capital Purchase Projects 1,617 1,049 833 743 868 428 5,538 Developer Reimbursement Projects 154 4 4 4 1,352 2,349 3,867 Subtotal 13,863 19,740 22,904 18,187 10,669 14,280 99,643 FY 2015 Through FY 2019 Projects - 21 2,767 803 3,394 463 7,448 TOTAL 13,863$ 19,761$ 25,671$ 18,990$ 14,063$ 14,743$ 107,091$ CIP Funding Source and Category $0 $10,000 $20,000 $30,000 $40,000 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Six-Year CIP by Funding Source New Supply Expansion Replacement Betterment $0 $10,000 $20,000 $30,000 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Six-Year CIP by Category Developer Reimbursement Projects Capital Purchase Projects Replacement/Renewal Projects Capital Facility Projects 27 CIP No Description FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total CAPITAL FACILITY PROJECTS P2083 PS - 870-2 Pump Station Replacement (28,000 GPM)$540 $550 $5,500 $5,381 $11,971 P2267 36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations 5 195 200 P2434 Rancho Del Rey Groundwater Well Development 100 100 P2451 Otay Mesa Desalination Conveyance and Disinfection System 1,500 4,300 8,000 8,000 6,600 28,400 P2466 Regional Training Facility 14 14 P2486 Asset Management Plan Condition Assessment and Data 75 75 75 34 259 P2511 Otay Interconnect Pipeline 600 650 500 1,750 P2514 PL - 30-Inch, 980 Zone, Hunte Parkway - Proctor Valley/Use Area 130 130 P2537 Operations Yard Property Acquisition Improvements 50 235 285 P2539 South Bay Bus Rapid Transit (BRT) Utility Relocations 80 80 160 320 P2541 624 Pressure Zone PRSs 300 100 200 600 P2542 850-3 Reservoir Interior Coating 10 380 50 440 R2048 RecPL - Otay Mesa Distribution Pipelines and Conversions 100 1 1 1 50 1,547 1,700 R2058 RecPL - 16-Inch, 860 Zone, Airway Road - Otay Mesa/Alta 100 1 1 1 1 2,046 2,150 R2077 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway 135 600 600 410 1,745 R2087 RecPL - 24-Inch, 927 Zone, Wueste Road - Olympic/Otay WTP 5 5 5 5 5 5,925 5,950 R2091 RecPS - 927-1 Pump Station Upgrade (10,000 GPM) and System Enhancements 250 250 R2107 RWCWRF Screening Compactor and Chlorine Injectors Enclosure 60 60 R2108 Res - 927-1 Reservoir Cover Replacement 100 1,300 1,400 R2110 RecPS - 927-1 Optimization and Pressure Zone modifications 150 150 S2039 Hidden Mountain Lift Station Enclosure 8 8 S2043 RWCWRF Sludge Handling System 50 100 1,250 100 1,500 22 Total Capital Facility Projects 4,362 8,572 16,342 13,932 6,656 9,518 59,382 REPLACEMENT/RENEWAL PROJECTS P2366 APCD Engine Replacements and Retrofits 5 250 225 220 243 45 988 P2382 Safety and Security Improvements 500 200 200 200 100 300 1,500 P2440 I-905 Utility Relocations 10 10 P2453 SR-11 Utility Relocations 125 700 565 700 2,090 P2477 Res - 624-1 Reservoir Cover Replacement 50 50 P2485 SCADA Communication System and Software Replacement 540 455 995 P2493 624-2 Reservoir Interior/Exterior Coating 1,550 390 1,940 P2494 Multiple Species Conservation Plan 60 60 P2495 San Miguel Habitat Management/Mitigation Area 140 180 190 200 200 200 1,110 P2496 Otay Lakes Road Utility Relocations 70 70 P2504 Regulatory Site Access Road and Pipeline Relocation 325 275 600 P2507 East Palomar Street Utility Relocation 230 375 605 P2508 Pipeline Cathodic Protection Replacement Program 60 125 100 285 P2513 East Orange Avenue Bridge Crossing 300 300 P2515 870-1 Reservoir Paving 490 490 P2518 803-3 Reservoir Interior/Exterior Coating 125 125 P2519 832-2 Reservoir Interior/Exterior Coating 335 335 P2520 Motorola Mobile Radio Upgrade 30 30 P2521 Large Meter Vault Upgrade Program 105 100 100 113 418 P2531 944-1 Reservoir Interior & Exterior Coating 5 160 10 175 P2532 944-2 Reservoir Interior & Exterior Coating 5 660 60 725 P2535 458-2 Reservoir Interior Coating 345 70 415 P2538 Administration and Operations Building Fire Sprinkler 100 300 400 R2109 Sweetwater River Wooden Trestle Improvement for the Recycled 100 100 150 350 R2111 RWCWRF - RAS Pump Replacement 100 100 S2012 San Diego County Sanitation District Outfall and RSD Outfall 450 450 450 450 450 440 2,690 S2024 Campo Road Sewer Main Replacement 275 1,975 2,375 825 5,450 S2027 Rancho San Diego Pump Station Rehabilitation 500 2,350 2,850 S2033 Sewer System Rehabilitation 800 1,000 1,300 800 800 1,000 5,700 29 Total Renewal & Replacements 7,730 10,115 5,725 3,508 1,793 1,985 30,856 CIP Projects ($1,000s) The 2014 Fiscal Year CIP Budget contains 63 projects. The cost for the work planned for Fiscal Year 2014 is $14 million. Of the 63 projects planned for Fiscal Year 2014,five are designated as reimbursable projects with an estimated cost of $154 thousand. These projects are built by a developer and reimbursed by the District. 28 CIP Projects ($1,000s) CIP No Description FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total CAPITAL PURCHASE PROJECTS P2282 Vehicle Capital Purchases 266 450 450 475 500 2,141 P2285 Office Equipment and Furniture Capital Purchases 55 15 15 85 P2286 Field Equipment Capital Purchases 149 84 68 68 68 67 504 P2469 Information Technology Network and Hardware 350 100 100 100 200 200 1,050 P2470 Financial System Enhancements 130 100 100 100 100 161 691 P2540 Work Management System Replacement 300 300 100 700 S2042 Sewer Vehicle Capital Purchases 367 367 7 Total Capital Purchase 1,617 1,049 833 743 868 428 5,538 DEVELOPER REIMBURSEMENT PROJECTS R2082 RecPL - 24-Inch, 680 Zone, Olympic Parkway - Village 2/Heritage 1 1 1 1 1,000 742 1,746 R2083 RecPL - 20-Inch, 680 Zone, Heritage Road - Village 2/Olympic 1 1 1 1 1 395 400 R2084 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media 1 1 1 1 350 617 971 R2085 RecPL - 20-Inch, 680 Zone, La Media - State/Olympic 1 1 1 1 1 595 600 R2094 Potable Irrigation Meters to Recycled Water Conversions 150 150 5 Total Reimbursement Projects 154 4 4 4 1,352 2,349 3,867 63 Total- FY2014 Projects 13,863 19,740 22,904 18,187 10,669 14,280 99,643 14 Total- FY2015 Through FY 2019 Projects - 21 2,767 803 3,394 463 7,448 77 Grand Totals $ 13,863 $ 19,761 $ 25,671 $ 18,990 $ 14,063 $ 14,743 $ 107,091 29 CIP #Description Cost Cat. (2) Funding Source (3) FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 TOTAL P2451 Otay Mesa Desalination Conveyance and Disinfection System M/E/C N/B $ - $ - $ - $ 4,000 $ 33,500 $ 38,500 $ 76,000 P2466 Regional Training Facility M E/B - - 1,000 1,000 1,000 1,000 4,000 P2514 PL - 30-Inch, 980 Zone, Hunte Parkway - Proctor Valley/Use Area M E 700 700 700 700 700 700 4,200 R2082 RecPL - 24-Inch, 680 Zone, Olympic Parkway - Village 2/Heritage M E - - - - - 1,200 1,200 R2083 RecPL - 20-Inch, 680 Zone, Heritage Road - Village 2/Olympic M E - - - - - 700 700 R2084 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media M E - - - - - 1,900 1,900 R2085 RecPL - 20-Inch, 680 Zone, La Media - State/Olympic M E - - 1,300 1,300 - - 2,600 R2109 Sweetwater River Wooden Trestle Improvement for the Recycled Water Forcemain M R - - - 3,000 3,100 3,200 9,300 700 700 3,000 10,000 38,300 47,200 99,900 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 TOTAL $ 700 $ 700 $ 3,000 $ 6,000 $ 9,800 $ 18,700 $ 38,900 - - - 3,000 25,000 25,000 53,000 - - - 1,000 3,500 3,500 8,000 $ 700 $ 700 $ 3,000 $ 10,000 $ 38,300 $ 47,200 $ 99,900 (1) (2) (3) Total Operating Budget Cost Impact Projected Incremental Operating Expenditures (1) E - Expansion B - Betterment R - Replacement N - New Supply The following schedule shows anticipated operating costs associated with each project in the CIP. Below is a summary of each category of new costs that will be impacted. No additional revenues are associated with the individual projects, as revenues are linked more directly to growth in water sales and capacity fee revenues. Cost Category Maintenance (M) Energy (E) Chemical (C) Funding Source - Some projects have multiple funding sources as indicated by a slash (/): CIP Justification and Impact on Operating Budget O&M cost for a reservoir: Total annual operating cost divided by the number of million gallons (MG) of storage capacity in the system. This rate per MG is then multiplied by the MG capacity of the new reservoir. Reservoirs require chemical treatment; therefore, the chemical cost per MG is estimated and applied to the future operating cost. Both O&M and chemical costs are increased annually for inflation. Each of the capital purchases and other types of assets has its own unique O&M cost. Cost Category - Indicates maintenance cost, energy cost, or chemical cost, based on the project type and Engineer's estimates. O&M cost for a pump station: Total annual operating cost divided by the number of million of gallons a day (MGD) capacity in the system = O&M cost per MGD. This rate is then multiplied by the MGD capacity of the new pump station. Similarly, power cost per MGD for transmission is calculated and applied to the MGD of the new pump station. Chemical expenses are incurred for pumping at the well sites. All estimated costs are increased annually for inflation. Projected Incremental Operating Expenditures (operating cost) or O&M includes labor, benefits, materials, and overhead. O&M cost for pipes: Total annual operating cost divided by the number of feet of pipe in the system = O&M cost to maintain a foot of pipe. This rate is then multiplied by the number of feet in new pipeline, and is increased annually for inflation. Total Operating Budget Cost Impact 30 CIP No.Project Name Start Finish CIP Number Wed 7/10/13 Wed 7/10/13 Capital Facilities Projects Wed 7/10/13 Wed 7/10/13 P2083 PS - 870-2 Pump Station Replacement (28,000 GPM) Wed 7/10/13 Wed 7/10/13 Planning Wed 7/10/13 Sun 9/1/13 Design Mon 9/2/13 Fri 1/30/15 Construction Mon 2/2/15 Wed 11/2/16 P2267 36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations Wed 7/10/13 Wed 7/10/13 Construction Tue 7/1/97 Tue 5/31/16 P2434 Rancho Del Rey Groundwater Well Development Wed 7/10/13 Wed 7/10/13 Design Mon 1/3/11 Fri 6/28/19 Construction Wed 7/10/13 Wed 7/10/13 P2451 Otay Mesa Desalination Conveyance and Disinfection System Wed 7/10/13 Wed 7/10/13 Planning Mon 7/3/06 Fri 6/27/14 Design Tue 7/1/14 Tue 6/30/15 Construction Wed 7/1/15 Mon 7/31/17 P2466 Regional Training Facility Wed 7/10/13 Wed 7/10/13 Planning Mon 7/2/07 Fri 6/27/14 P2486 Asset Management Plan Condition Assessment and Data Acquisition Wed 7/10/13 Wed 7/10/13 Planning Wed 7/1/09 Thu 6/29/17 P2511 Otay Interconnect Pipeline Wed 7/10/13 Wed 7/10/13 Design Mon 6/3/13 Wed 12/31/14 Construction Mon 7/1/19 Wed 6/30/21 P2514 PL - 30-Inch, 980 Zone, Hunte Parkway - Proctor Valley/Use Area Wed 7/10/13 Wed 7/10/13 Construction Tue 1/1/13 Fri 11/29/13 P2537 Operations Yard Property Acquisition Improvements Wed 7/10/13 Wed 7/10/13 Design Fri 2/1/13 Thu 7/31/14 Construction Fri 8/1/14 Wed 7/1/15 P2539 South Bay Bus Rapid Transit (BRT) Utility Relocations Wed 7/10/13 Wed 7/10/13 Planning Mon 7/1/13 Mon 6/30/14 Design Tue 7/1/14 Wed 12/31/14 Construction Thu 1/1/15 Wed 6/29/16 P2541 624 Pressure Zone PRSs Wed 7/10/13 Wed 7/10/13 Planning Tue 4/23/13 Fri 8/23/13 Design Mon 8/26/13 Tue 2/25/14 Construction Wed 2/26/14 Fri 2/13/15 P2542 850-3 Reservoir Interior Coating Wed 7/10/13 Wed 7/10/13 Planning Mon 5/5/14 Wed 7/30/14 Design Fri 8/1/14 Thu 10/30/14 Construction Mon 11/3/14 Fri 7/31/15 R2048 RecPL - Otay Mesa Distribution Pipelines and Conversions Wed 7/10/13 Wed 7/10/13 Design Fri 1/1/10 Mon 6/1/15 2Q3Q4 Q2Q3Q4 Q2Q3Q4Q1Q2Q3Q4 Q2Q3Q4 Q2Q3Q4 Q2 13 2014 2015 2016 2017 2018 2019 Otay Water DistrictFY 2014 - FY 2019CIP Project Schedule 31 CIP No.Project Name Start Finish Construction Wed 7/1/15 Fri 6/28/19 R2058 RecPL - 16-Inch, 860 Zone, Airway Road - Otay Mesa/Alta Wed 7/10/13 Wed 7/10/13 Design Fri 1/1/10 Fri 5/30/14 Construction Mon 7/2/18 Fri 5/31/19 R2077 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway Wed 7/10/13 Wed 7/10/13 Construction Fri 7/1/11 Wed 5/31/17 R2087 RecPL - 24-Inch, 927 Zone, Wueste Road - Olympic/Otay WTP Wed 7/10/13 Wed 7/10/13 Construction Fri 7/1/16 Fri 5/31/19 R2091 RecPS - 927-1 Pump Station Upgrade (10,000 GPM) and System Enhancements Wed 7/10/13 Wed 7/10/13 Construction Wed 6/1/11 Fri 11/29/13 R2107 RWCWRF Screening Compactor and Chlorine Injectors Enclosure Wed 7/10/13 Wed 7/10/13 Construction Mon 7/2/12 Fri 5/30/14 R2108 Res - 927-1 Reservoir Cover Replacement Wed 7/10/13 Wed 7/10/13 Planning Mon 4/1/13 Mon 7/1/13 Design Tue 7/2/13 Mon 8/26/13 Construction Mon 9/2/13 Fri 5/30/14 R2110 RecPS - 927-1 Optimization and Pressure Zone modifications Wed 7/10/13 Wed 7/10/13 Planning Mon 7/1/13 Mon 9/30/13 Design Tue 10/1/13 Fri 11/29/13 Construction Mon 12/2/13 Mon 12/2/13 S2039 Hidden Mountain Lift Station Enclosure Wed 7/10/13 Wed 7/10/13 Construction Mon 7/2/12 Fri 11/29/13 S2043 RWCWRF Sludge Handling System Wed 7/10/13 Wed 7/10/13 Planning Mon 7/1/13 Fri 11/28/14 Design Mon 12/1/14 Mon 11/30/15 Construction Tue 12/1/15 Wed 11/30/16 Replacement /Renewal Wed 7/10/13 Wed 7/10/13 P2366 APCD Engine Replacements and Retrofits Wed 7/10/13 Wed 7/10/13 Planning Fri 12/1/00 Thu 5/31/01 Design Mon 7/2/01 Mon 5/31/10 Construction Thu 7/1/10 Fri 5/31/19 P2382 Safety and Security Improvements Wed 7/10/13 Wed 7/10/13 Planning Mon 7/1/02 Thu 7/31/03 Design Mon 9/1/03 Mon 5/31/10 Construction Mon 8/2/04 Wed 5/31/17 P2440 I-905 Utility Relocations Wed 7/10/13 Wed 7/10/13 Construction Mon 10/2/06 Fri 11/29/13 P2453 SR-11 Utility Relocations Wed 7/10/13 Wed 7/10/13 2Q3Q4 Q2Q3Q4 Q2Q3Q4Q1Q2Q3Q4 Q2Q3Q4 Q2Q3Q4 Q2 13 2014 2015 2016 2017 2018 2019 Otay Water DistrictFY 2014 - FY 2019CIP Project Schedule 32 CIP No.Project Name Start Finish Design Mon 1/5/09 Wed 1/1/14 Construction Wed 1/1/14 Thu 9/22/16 P2477 Res - 624-1 Reservoir Cover Replacement Wed 7/10/13 Wed 7/10/13 Construction Wed 10/10/12 Fri 8/30/13 P2485 SCADA Communication System and Software Replacement Wed 7/10/13 Wed 7/10/13 Construction Wed 7/1/09 Fri 5/29/15 P2493 624-2 Reservoir Interior/Exterior Coating Wed 7/10/13 Wed 7/10/13 Design Tue 7/6/10 Fri 11/1/13 Construction Fri 11/1/13 Thu 4/17/14 P2494 Multiple Species Conservation Plan Wed 7/10/13 Wed 7/10/13 Planning Wed 7/1/09 Fri 6/27/14 P2495 San Miguel Habitat Management/Mitigation Area Wed 7/10/13 Wed 7/10/13 Planning Wed 7/1/09 Fri 6/28/19 P2496 Otay Lakes Road Utility Relocations Wed 7/10/13 Wed 7/10/13 Construction Fri 1/1/10 Mon 12/30/13 P2504 Regulatory Site Access Road and Pipeline Relocation Wed 7/10/13 Wed 7/10/13 Design Mon 4/1/13 Wed 10/1/14 Construction Thu 10/2/14 Tue 5/31/16 P2507 East Palomar Street Utility Relocation Wed 7/10/13 Wed 7/10/13 Construction Mon 1/2/12 Fri 5/29/15 P2508 Pipeline Cathodic Protection Replacement Program Wed 7/10/13 Wed 7/10/13 Planning Wed 11/3/10 Thu 10/3/13 Design Fri 10/4/13 Wed 4/2/14 Construction Thu 4/3/14 Thu 9/29/16 P2513 East Orange Avenue Bridge Crossing Wed 7/10/13 Wed 7/10/13 Construction Mon 6/3/13 Fri 5/30/14 P2515 870-1 Reservoir Paving Wed 7/10/13 Wed 7/10/13 Planning Thu 10/4/12 Tue 3/5/13 Design Wed 3/6/13 Tue 9/2/14 Construction Wed 9/3/14 Wed 3/4/15 P2518 803-3 Reservoir Interior/Exterior Coating Wed 7/10/13 Wed 7/10/13 Construction Tue 1/1/13 Fri 8/30/13 P2519 832-2 Reservoir Interior/Exterior Coating Wed 7/10/13 Wed 7/10/13 Construction Tue 1/1/13 Fri 8/30/13 P2520 Motorola Mobile Radio Upgrade Wed 7/10/13 Wed 7/10/13 Construction Mon 8/1/11 Fri 6/27/14 P2521 Large Meter Vault Upgrade Program Wed 7/10/13 Wed 7/10/13 2Q3Q4 Q2Q3Q4 Q2Q3Q4Q1Q2Q3Q4 Q2Q3Q4 Q2Q3Q4 Q2 13 2014 2015 2016 2017 2018 2019 Otay Water DistrictFY 2014 - FY 2019CIP Project Schedule 33 CIP No.Project Name Start Finish Construction Mon 8/1/11 Tue 5/31/16 P2531 944-1 Reservoir Interior & Exterior Coating Wed 7/10/13 Wed 7/10/13 Planning Mon 6/2/14 Fri 8/29/14 Design Mon 9/1/14 Tue 12/30/14 Construction Thu 1/1/15 Fri 7/31/15 P2532 944-2 Reservoir Interior & Exterior Coating Wed 7/10/13 Wed 7/10/13 Planning Mon 6/2/14 Fri 8/29/14 Design Mon 9/1/14 Tue 12/30/14 Construction Thu 1/1/15 Fri 7/31/15 P2535 458-2 Reservoir Interior Coating Wed 7/10/13 Wed 7/10/13 Planning Mon 6/3/13 Fri 9/27/13 Design Tue 10/1/13 Mon 11/11/13 Construction Fri 11/1/13 Thu 4/17/14 P2538 Administration and Operations Building Fire Sprinkler Replacement Program Wed 7/10/13 Wed 7/10/13 Design Mon 7/1/13 Fri 3/21/14 Construction Mon 3/24/14 Fri 12/19/14 R2109 Sweetwater River Wooden Trestle Improvement for the Recycled Water Forcemain Wed 7/10/13 Wed 7/10/13 Planning Mon 7/1/13 Fri 5/30/14 Design Tue 7/1/14 Fri 5/29/15 Construction Wed 7/1/15 Tue 5/31/16 R2111 RWCWRF - RAS Pump Replacement Wed 7/10/13 Wed 7/10/13 Construction Wed 7/10/13 Wed 7/10/13 S2012 San Diego County Sanitation District Outfall and RSD Outfall Replacement Wed 7/10/13 Wed 7/10/13 Planning Tue 7/1/03 Fri 5/31/19 S2024 Campo Road Sewer Main Replacement Wed 7/10/13 Wed 7/10/13 Planning Thu 7/1/10 Fri 5/30/14 Design Thu 5/1/14 Fri 1/30/15 Construction Thu 1/1/15 Tue 3/1/16 S2027 Rancho San Diego Pump Station Rehabilitation Wed 7/10/13 Wed 7/10/13 Design Mon 7/2/12 Mon 6/30/14 Construction Tue 7/1/14 Mon 4/25/16 S2033 Sewer System Rehabilitation Wed 7/10/13 Wed 7/10/13 Planning Fri 7/1/11 Thu 12/31/15 Design Fri 3/1/13 Fri 12/30/16 Construction Wed 1/1/14 Mon 12/31/18 Capital Purchases Wed 7/10/13 Wed 7/10/13 P2282 Vehicle Capital Purchases Wed 7/10/13 Wed 7/10/13 Planning Fri 12/1/00 Thu 5/31/18 2Q3Q4 Q2Q3Q4 Q2Q3Q4Q1Q2Q3Q4 Q2Q3Q4 Q2Q3Q4 Q2 13 2014 2015 2016 2017 2018 2019 Otay Water DistrictFY 2014 - FY 2019CIP Project Schedule 34 CIP No.Project Name Start Finish P2285 Office Equipment and Furniture Capital Purchases Wed 7/10/13 Wed 7/10/13 Planning Fri 12/1/00 Thu 5/31/18 P2286 Field Equipment Capital Purchases Wed 7/10/13 Wed 7/10/13 Planning Mon 7/1/96 Fri 5/31/19 P2469 Information Technology Network and Hardware Wed 7/10/13 Wed 7/10/13 Planning Tue 7/1/08 Fri 6/28/19 P2470 Financial System Enhancements Wed 7/10/13 Wed 7/10/13 Planning Tue 7/1/08 Fri 5/31/19 P2540 Work Order Management System Replacement Wed 7/10/13 Wed 7/10/13 Construction Mon 7/1/13 Wed 6/29/16 S2042 Sewer Vehicle Capital Purchases Wed 7/10/13 Wed 7/10/13 Planning Mon 7/2/12 Fri 5/31/13 Developer Reimbursements Wed 7/10/13 Wed 7/10/13 R2082 RecPL - 24-Inch, 680 Zone, Olympic Parkway - Village 2/Heritage Wed 7/10/13 Wed 7/10/13 Design Mon 7/2/12 Fri 5/29/15 Construction Wed 7/1/15 Tue 5/30/17 R2083 RecPL - 20-Inch, 680 Zone, Heritage Road - Village 2/Olympic Wed 7/10/13 Wed 7/10/13 Planning Thu 7/1/04 Thu 11/30/17 Design Fri 12/1/17 Tue 7/31/18 Construction Wed 8/1/18 Tue 7/2/19 R2084 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media Wed 7/10/13 Wed 7/10/13 Planning Fri 7/1/05 Mon 6/1/15 Design Wed 7/1/15 Wed 5/31/17 Construction Mon 7/3/17 Fri 5/31/19 R2085 RecPL - 20-Inch, 680 Zone, La Media - State/Olympic Wed 7/10/13 Wed 7/10/13 Design Mon 7/1/13 Fri 5/30/14 Construction Tue 7/1/14 Fri 5/31/19 R2094 Potable Irrigation Meters to Recycled Water Conversions Wed 7/10/13 Wed 7/10/13 Construction Fri 7/1/11 Fri 6/27/14 2Q3Q4 Q2Q3Q4 Q2Q3Q4Q1Q2Q3Q4 Q2Q3Q4 Q2Q3Q4 Q2 13 2014 2015 2016 2017 2018 2019 Otay Water DistrictFY 2014 - FY 2019CIP Project Schedule 35 Item#Amount Grand Total : P2282 Vehicle 266,000$ P2285 Office Equipment 55,000$ P2286 Field 149,000$ S2042 Sewer Vehicle 366,200$ 836,200$ 836,200$ 4 Replace SUV, to be purchased from P2282 Vehicle Capital Purchase. 33,000 1 Replace F150 pick-up truck, to be purchased out of P2282 Vehicle Capital Purchases. 7 Replace vactor model 2110 plus jet rodder. S2042 366,200 Total of Vehicles 632,200 Vehicles Finance 5 Replace compact pick-up truck to be purchased from P2282 Vehicle Capital Purchases. 25,000 38,000 Operations 6 Replace crew truck, vehicle to be purchased from P2282 Vehicle Capital Purchase. 170,000 Information Technology 10 Replace GIS plotter located in Engineering P2285 25,000 Total of Office Equipment 55,000 Finance 8 Replace Finance Printer/Copier. P2285 15,000 General Manager 9 Replace GM Printer/Copier P2285 15,000 Replace equipment trailer, to be purchased out of P2286 field equipment. 32,000 Total of Field Equipment 149,000 Office Equipment FY 2014 Capital Purchases Summary by Project Capital purchases are non-recurring operating expense items for District-wide use that cost more than $10,000 each and have an estimated useful life of two years or more. The Capital Purchase Projects include Field Equipment, Office Equipment and Furniture, and Vehicle purchases. Description Field Equipment Operations 2 Replace backhoe, to be purchased from P2286 field equipment. 117,000$ 3 36 CIP Project Sheet Description The following pages describe each information item on the individual CIP project sheets included in this section. CIP Number: The CIP project number for all projects is assigned by the Engineering Project Manager, and is a unique identifying code on all District records for the specified project. Project Title: Project titles follow a set format as described herein. The type of project should be identified first. For example, if a project were a 711 Pressure Zone 24-inch pipeline, the title would read “PL - 24-Inch, 711 Zone, Location - From A to B.” Pump stations and reservoirs are identified similarly with abbreviations for type and size. Director Division: All projects are located within a Board of Director’s division boundary unless they apply to the entire District or are outside of the District boundaries. The Director division where the majority of the physical project is located is listed. If it is a District-wide project it is listed as “District-wide.” If it is outside the District boundary it is listed as “None.” Project Manager: The person responsible for managing the project from inception through completion. I.D. Location: Most projects are located within one or more improvement districts. The I.D. location listed is where the majority of the physical project is located. However, projects located in portions of the District which have not yet been annexed into an improvement district are listed as “None.”. Original Approved Date: The date the project was originally approved with budget expenditures for the corresponding fiscal year by the Board of Directors. Priority: The priority of the project is listed in this field as one of the following: 1. HIGH: Safety, restoration of service to customers, obligation that requires immediate action, directed by the Board of Directors, and/or critical system need. 2. MEDIUM: Upgrade of system or expansion requirement to maintain system reliability not critical. Identified through planning effort as required within next few fiscal years. 3. LOW: Identified through planning effort as required in future years to support development; not anticipated in the immediate future. 4. VERY LOW: Requirement may have low probability of need in the future. Related CIP Projects: A maximum of three CIP project numbers that affect the scheduling and/or is related to the subject project and/or could provide important information. 37 Budget Amount: The estimated budget includes all costs needed to complete a project including land, right-of-way, consultants, contractors, District staff time, etc. All prior years’ costs are part of the total cost and dollars are rounded up to the nearest $1,000. Description of Project: A brief description of a project which typically includes size, length, capacity, etc. Justification of Project: A brief explanation of why a project is required which addresses flexibility, reliability, water quality, safety, contractual obligation, immediate growth, etc., as appropriate. Comments: Pertinent information that should be known about a project that is not shown elsewhere on the project sheet, including details of funding sources, including grant funding or contributions from other agencies. Funding Detail: The funding sources are listed along with the percentage of distribution to expansion, betterment, and/or replacement. Expenditure Schedule: The breakdown of a project’s expenditures by fiscal year – prior years’ cost along with a six-year budget schedule. Included in each year are all costs to complete the work scheduled in that year rounded up to the nearest $1,000. Project Schedule: The schedule of the primary project phase and estimated cost by the phases of planning, design, and construction shown with the estimated start date (month/year), finish date (month/year). The schedule time frames and estimated cost for each major phase of the project, correspond with the expenditure schedule information. Project Incremental Operation Expenditures: To determine the cost to maintain these new assets, the District looks at the cost of maintaining similar assets through the Infrastructure Management System and financial system. Costs are tracked by three main infrastructure asset groups of pipes, pump stations, and reservoirs, as well as capital purchases and other types. Pipes typically have only operation and maintenance (O&M) costs associated with them, pump stations have O&M as well as power cost, and reservoirs have O&M and chemical cost. Each of the capital purchases and other types has its own unique O&M cost. See page 27 for a further explanation of these expenditures. Project Location: A vicinity map is drawn in AutoCAD format using the GIS database as the foundation showing the approximate location and limits of a project within the District. Some projects do not have a specific location. In this case, a map of the entire District will then be shown as the project location. 38 Thomas Bros. Map: The Thomas Brothers’ map page is inserted in this field to show where the project is primarily located. Some projects do not have a specific location in which case the words “District-wide” will be shown. OWD Map Book: The page in the District’s facility map book where a project is primarily located. Some projects do not have a specific location in which case the words “District-wide” will be shown. Submitted By: The project manager who originally submitted or the project manager who revised the project sheet along with the date of submittal or last revision date of the CIP project sheet. 39 CIP No Project Description Page CAPITAL FACILITY PROJECTS P2083 PS - 870-2 Pump Station Replacement (28,000 GPM)42 P2267 36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations 44 P2434 Rancho Del Rey Groundwater Well Development 46 P2451 Otay Mesa Desalination Conveyance and Disinfection System 48 P2466 Regional Training Facility 50 P2486 Asset Management Plan Condition Assessment and Data Acquisition 52 P2511 Otay Interconnect Pipeline 54 P2514 PL - 30-Inch, 980 Zone, Hunte Parkway - Proctor Valley/Use Area 56 P2537 Operations Yard Property Acquisition Improvements 58 P2539 South Bay Bus Rapid Transit (BRT) Utility Relocations 60 P2541 624 Pressure Zone PRSs 62 P2542 850-3 Reservoir Interior Coating 64 R2048 RecPL - Otay Mesa Distribution Pipelines and Conversions 66 R2058 RecPL - 16-Inch, 860 Zone, Airway Road - Otay Mesa/Alta 68 R2077 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway 70 R2087 RecPL - 24-Inch, 927 Zone, Wueste Road - Olympic/Otay WTP 72 R2091 RecPS - 927-1 Pump Station Upgrade (10,000 GPM) and System Enhancements 74 R2107 RWCWRF Screening Compactor and Chlorine Injectors Enclosure 76 R2108 Res - 927-1 Reservoir Cover Replacement 78 R2110 RecPS - 927-1 Optimization and Pressure Zone modifications 80 S2039 Hidden Mountain Lift Station Enclosure 82 S2043 RWCWRF Sludge Handling System 84 22 Total Capital Facility Projects REPLACEMENT/RENEWAL PROJECTS P2366 APCD Engine Replacements and Retrofits 86 P2382 Safety and Security Improvements 88 P2440 I-905 Utility Relocations 90 P2453 SR-11 Utility Relocations 92 P2477 Res - 624-1 Reservoir Cover Replacement 94 P2485 SCADA Communication System and Software Replacement 96 P2493 624-2 Reservoir Interior/Exterior Coating 98 P2494 Multiple Species Conservation Plan 100 P2495 San Miguel Habitat Management/Mitigation Area 102 P2496 Otay Lakes Road Utility Relocations 104 P2504 Regulatory Site Access Road and Pipeline Relocation 106 P2507 East Palomar Street Utility Relocation 108 CIP Projects Index 40 CIP No Project Description Page REPLACEMENT/RENEWAL PROJECTS, continued P2508 Pipeline Cathodic Protection Replacement Program 110 P2513 East Orange Avenue Bridge Crossing 112 P2515 870-1 Reservoir Paving 114 P2518 803-3 Reservoir Interior/Exterior Coating 116 P2519 832-2 Reservoir Interior/Exterior Coating 118 P2520 Motorola Mobile Radio Upgrade 120 P2521 Large Meter Vault Upgrade Program 122 P2531 944-1 Reservoir Interior & Exterior Coating 124 P2532 944-2 Reservoir Interior & Exterior Coating 126 P2535 458-2 Reservoir Interior Coating 128 P2538 Administration and Operations Building Fire Sprinkler Replacement Program 130 R2109 Sweetwater River Wooden Trestle Improvement for the Recycled Water Forcemain 132 R2111 RWCWRF - RAS Pump Replacement 134 S2012 San Diego County Sanitation District Outfall and RSD Outfall Replacement 136 S2024 Campo Road Sewer Main Replacement 138 S2027 Rancho San Diego Pump Station Rehabilitation 140 S2033 Sewer System Rehabilitation 142 29 Total Renewal & Replacements CAPITAL PURCHASE PROJECTS P2282 Vehicle Capital Purchases 144 P2285 Office Equipment and Furniture Capital Purchases 146 P2286 Field Equipment Capital Purchases 148 P2469 Information Technology Network and Hardware 150 P2470 Financial System Enhancements 151 P2540 Work Management System Replacement 154 S2042 Sewer Vehicle Capital Purchases 156 7 Total Capital Purchase DEVELOPER REIMBURSEMENT PROJECTS R2082 RecPL - 24-Inch, 680 Zone, Olympic Parkway - Village 2/Heritage 158 R2083 RecPL - 20-Inch, 680 Zone, Heritage Road - Village 2/Olympic 160 R2084 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media 162 R2085 RecPL - 20-Inch, 680 Zone, La Media - State/Olympic 164 R2094 Potable Irrigation Meters to Recycled Water Conversions 166 5 Total Developer Reimbursement Projects CIP Projects Index 41 P2083 PS - 870-2 Pump Station Replacement (28,000 GPM) Jeff Marchioro 5/17/1995 P2451 2 7 1 $12,581,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of a new pump station to replace the existing Low Head and High Head pump stations and to expand capacity as projected within the Rosarito Desalination Technical Memorandums prepared by CDM. JUSTIFICATION OF PROJECT: The two existing pump stations have reached the end of their useful lives and are under capacity for delivery of the proposed Rosarito Desalination water supply. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $540 $550 $5,500 $5,381 $0 $0 $12,581 PRIOR YEARS: TOTAL $610 42 P2083 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 9/1/2013 9/1/2013 2/1/2015 $650 $1,100 PROJECT PHASE: 7/1/2015 4/1/2017 $10,831 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1332 055 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 43 P226736-Inch Main Pumpouts and Air/Vacuum Ventilation Installations Tadeo Vasquez 6/3/1996 3 1 2 $435,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Installation of ventilation equipment on the existing pump out and air/vacuum vaults on 36-inch transmission main from the San Diego County Water Authority Otay FCF No. 11 to the Regulatory Site. This project also includes upsizing the existing 2-inch air/vacuum valves to 6-inch. JUSTIFICATION OF PROJECT: The vault openings do not stay in place when refilling because they lack ventilation. By installing vents in these vaults, the lids will stay in place, thus eliminating a safety hazard. Draining and filling the 36-inch main at higher flow rates is required to return the system to service in shorter periods of time. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 1 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $5 $195 $0 $0 $0 $0 $435 PRIOR YEARS: TOTAL $235 44 P2267 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/1997 6/1/2016 $435 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1291 198 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/23/2013Bob Kennedy 45 P2434Rancho Del Rey Groundwater Well Development Jeff Marchioro 5/21/2009 2 22 1 $8,700,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Production groundwater well development of approximately 400 gallons per minute for potable water use. The project includes construction of a reverse osmosis treatment facility. JUSTIFICATION OF PROJECT: This project is needed to meet the IRP water supply goals. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 1 0 %5 %0 %0 %5 % Betterment ID 2 0 %2 %0 %0 %2 % Betterment ID 3 0 %4 %0 %0 %4 % Betterment ID 5 0 %1 %0 %0 %1 % Betterment ID 7 0 %5 %0 %0 %5 % Betterment ID 9 0 %2 %0 %0 %2 % Betterment ID 10 0 %4 %0 %0 %4 % Betterment ID 20 0 %7 %0 %0 %7 % Betterment ID 22 0 %30 %0 %0 %30 % New Water Supply Fee Projects 0 %0 %0 %40 %40 % TOTAL:0 %60 %0 %40 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $100 $0 $0 $0 $0 $0 $3,800 PRIOR YEARS: TOTAL $3,700 46 P2434 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/1994 12/1/2010 1/1/2011 12/31/2013 $2,600 $1,200 PROJECT PHASE: $4,900 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1310 127 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 47 P2451Otay Mesa Desalination Conveyance and Disinfection System Bob Kennedy 5/23/2006 P2083 2 7 1 $30,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: The Otay Water District could potentially receive a potable water supply source from the planned Rosarito Desalination Facility via a conveyance system, pumping facilities, and disinfection system. JUSTIFICATION OF PROJECT: The concept could provide for a independent water source to the Otay Water District. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 1 0 %5 %0 %0 %5 % Betterment ID 2 0 %2 %0 %0 %2 % Betterment ID 3 0 %4 %0 %0 %4 % Betterment ID 5 0 %1 %0 %0 %1 % Betterment ID 7 0 %5 %0 %0 %5 % Betterment ID 9 0 %2 %0 %0 %2 % Betterment ID 10 0 %4 %0 %0 %4 % Betterment ID 20 0 %7 %0 %0 %7 % Betterment ID 22 0 %30 %0 %0 %30 % New Water Supply Fee Projects 0 %0 %0 %40 %40 % TOTAL:0 %60 %0 %40 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $1,500 $4,300 $8,000 $8,000 $6,600 $0 $30,000 PRIOR YEARS: TOTAL $1,600 48 P2451 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2006 6/30/2014 7/1/2014 7/1/2015 $2,500 $3,300 PROJECT PHASE: 7/1/2015 8/1/2017 $24,200 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $5,000 $10,000 $15,000 $0 $0 $0 $3,000 $25,000 $25,000 $53,000 $0 $0 $0 $1,000 $3,500 $3,500 $8,000 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 49 P2466Regional Training Facility Lisa Coburn-Boyd 5/29/2007 P2504 5 20 1 $300,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: The project is the construction of a Regional Training Facility at the Regulatory Site through a partnership with the San Miguel Consolidated Fire Protection District. JUSTIFICATION OF PROJECT: The Otay Water District needs a training center to train staff on trenching, shoring, fire safety, rescue, and confined space. The San Miguel Consolidated Fire Protection District has secured funding for this project and will be the lead agency in the development of the training facility. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 2 0 %2 %0 %0 %2 % Betterment ID 3 0 %4 %0 %0 %4 % Betterment ID 5 0 %1 %0 %0 %1 % Betterment ID 7 0 %5 %0 %0 %5 % Betterment ID 9 0 %2 %0 %0 %2 % Betterment ID 10 0 %4 %0 %0 %4 % Betterment ID 20 0 %7 %0 %0 %7 % Betterment ID 22 0 %30 %0 %0 %30 % Betterment ID 1 0 %5 %0 %0 %5 % Expansion 40 %0 %0 %0 %40 % TOTAL:40 %60 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $14 $0 $0 $0 $0 $0 $300 PRIOR YEARS: TOTAL $286 50 P2466 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2007 6/30/2014 $300 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 343 2014 2015 2016 2017 2018 2019 Total $0 $0 $1,000 $1,000 $1,000 $1,000 $4,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 51 P2486Asset Management Plan Condition Assessment and Data Acquisition Ming Zhao 5/21/2009 0 District Wide 1 $1,090,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the development of an integrated Asset Management and replacement of GBA work order system with Azteca System. JUSTIFICATION OF PROJECT: Implementation of an Asset Management Plan is best practice and will provide for a formal means of maintaining, replacing, and funding the existing fixed assets. This project covers the replacement of our existing and obsolete work order system (IMS) and the integration of asset information to fully support asset management - $259K over FY2014-2019. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $75 $75 $75 $34 $0 $0 $1,090 PRIOR YEARS: TOTAL $831 52 P2486 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 6/30/2017 $1,090 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 53 P2511Otay Interconnect Pipeline Jeff Marchioro 5/17/2010 P2528 3 1 1 $37,300,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will provide for a 30-inch transmission main interconnection and pump station between the North District and South District to transport 10,000 gallons per minute between the two systems in either direction. Also, the system will allow for the ability to transfer water from the Sweetwater Authority Perdue Water Treatment Plant into either the North or South Districts. This project was previously titled "North District - South District Interconnection System." JUSTIFICATION OF PROJECT: The Integrated Water Resources Plan identifies the objective, goals, purpose, and benefits of interconnecting the North and South Districts as well as for the need to diversify water resources for increased reliability. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 40 %0 %0 %0 %40 % Betterment ID 1 0 %5 %0 %0 %5 % Betterment ID 2 0 %2 %0 %0 %2 % Betterment ID 3 0 %4 %0 %0 %4 % Betterment ID 5 0 %1 %0 %0 %1 % Betterment ID 7 0 %5 %0 %0 %5 % Betterment ID 9 0 %2 %0 %0 %2 % Betterment ID 10 0 %4 %0 %0 %4 % Betterment ID 20 0 %7 %0 %0 %7 % Betterment ID 22 0 %30 %0 %0 %30 % TOTAL:40 %60 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $600 $650 $500 $0 $0 $0 $3,450 PRIOR YEARS: TOTAL $1,700 54 P2511 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 6/1/2013 6/1/2013 6/30/2016 $1,250 $2,200 PROJECT PHASE: 7/1/2019 7/1/2021 $33,850 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1291 184 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 55 P2514PL - 30-Inch, 980 Zone, Hunte Parkway - Proctor Valley/Use Area Dan Martin 5/16/2011 5 22 1 $1,815,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 2,200 feet of 30-inch pipeline in Hunte Parkway from Proctor Valley Road to the existing 980 Pressure Zone 30-inch pipeline at the southern end of the District's Use Area. JUSTIFICATION OF PROJECT: The existing transmission main capacity within the 980 Pressure Zone is insufficient to meet the needs of the system during peak demand periods. This project will resolve the peak demand pressure issues. COMMENTS: Project under construction. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $130 $0 $0 $0 $0 $0 $1,815 PRIOR YEARS: TOTAL $1,685 56 P2514 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 12/1/2011 1/1/2012 12/1/2012 $100 $200 PROJECT PHASE: 1/1/2013 12/1/2013 $1,515 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 159 2014 2015 2016 2017 2018 2019 Total $700 $700 $700 $700 $700 $700 $4,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/30/2013Bob Kennedy 57 P2537Operations Yard Property Acquisition Improvements Bob Kennedy 11/13/2008 P2479 4 20 1 $300,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: The project will provide site improvements including fencing, grading, and paving for vehicle parking and equipment storage. JUSTIFICATION OF PROJECT: The site improvements are required to provide flexibility in operations and for future expansion purposes. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $50 $235 $0 $0 $0 $0 $300 PRIOR YEARS: TOTAL $15 58 P2537 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/1/2008 6/1/2013 7/1/2013 6/1/2014 $5 $60 PROJECT PHASE: 7/1/2014 6/1/2015 $235 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1291 318 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 59 P2539South Bay Bus Rapid Transit (BRT) Utility Relocations Bob Kennedy 1 22/27 1 $320,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for all utility relocations required due to construction of South Bay BRT. Facility relocations vary in size and they impact both the potable and recycled water systems. JUSTIFICATION OF PROJECT: Project improvements will affect the locations of some OWD facilities in streets in Chula Vista. Engineering/staff time will be needed to review the design drawings and identify any OWD facilities which will need relocation or vertical adjustment. A construction budget is also needed for the work in relocating and adjusting these facilities. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $80 $80 $160 $0 $0 $0 $320 PRIOR YEARS: TOTAL $0 60 P2539 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2013 7/1/2014 7/1/2014 1/1/2015 $80 $80 PROJECT PHASE: 1/1/2015 6/30/2016 $160 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311, 1330, 1331 80-82, 97-99, 113 & 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 61 P2541624 Pressure Zone PRSs Jeff Marchioro P2434 2 10, 22 1 $600,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will provide two pressure reducing stations feeding the 458 and 485 Pressure Zones from the 624 Pressure Zone (Sequoia & Brandywine 624/458 PRS and Terra Nova Drive 624/485 PRS, respectively). JUSTIFICATION OF PROJECT: This project would upgrade the 485 and 485 Pressure Zones to improve fire flow and enhance system reliability. The 624/485 PRS project will also improve blending and distribution of treated water from the future Rancho Del Rey Groundwater Well (CIP P2434). COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 10 0 %50 %0 %0 %50 % Betterment ID 22 0 %50 %0 %0 %50 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $300 $100 $200 $0 $0 $0 $600 PRIOR YEARS: TOTAL $0 62 P2541 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2013 10/1/2014 8/1/2013 7/1/2015 $10 $75 PROJECT PHASE: 1/8/2014 6/30/2016 $515 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1310 127 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 63 P2542850-3 Reservoir Interior Coating Kevin Cameron 5 20 2 $440,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior coating of the 850-3 Reservoir. JUSTIFICATION OF PROJECT: The interior coating is in poor condition and in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $10 $380 $50 $0 $0 $0 $440 PRIOR YEARS: TOTAL $0 64 P2542 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 5/5/2014 7/31/2014 8/1/2014 10/31/2014 $10 $60 PROJECT PHASE: 11/3/2014 8/1/2015 $370 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1272 355 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 65 R2048RecPL - Otay Mesa Distribution Pipelines and Conversions Dan Martin 6/23/2008 R2058, R2077, R2087 2 7 1 $2,200,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of various distribution pipeline links and conversion of existing pipelines for recycled water use within the 860 Pressure Zone of the Otay Mesa System. JUSTIFICATION OF PROJECT: This project will connect the existing distribution recycled water pipelines, currently supplied with potable water, to the planned construction of pipeline links to supply all those existing water demands within the Otay Mesa System with recycled water. Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102- 575. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $100 $1 $1 $1 $50 $1,547 $2,200 PRIOR YEARS: TOTAL $500 66 R2048 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2008 12/1/2008 1/1/2009 6/1/2014 $80 $520 PROJECT PHASE: 7/1/2015 6/30/2019 $1,550 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1351 12 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 67 R2058RecPL - 16-Inch, 860 Zone, Airway Road - Otay Mesa/Alta Dan Martin 6/16/1999 R2048, R2077, R2087 2 7 1 $3,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 10,700 feet of 16-inch pipeline within the 860 Pressure Zone in Airway Road from Otay Mesa Road to Alta Road. Portions of this project will be constructed by developers and these are subject to reimbursement at actual cost per Board policy. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for development of Otay Mesa within the 860 Pressure Zone. Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102-575. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $100 $1 $1 $1 $1 $2,046 $3,500 PRIOR YEARS: TOTAL $1,350 68 R2058 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2001 12/1/2009 1/1/2010 6/1/2014 $120 $330 PROJECT PHASE: 7/1/2018 6/1/2019 $3,050 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1351 12 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 69 R2077RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway Bob Kennedy 5/23/2006 R2048, R2058, R2087 2 7 1 $4,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 9,300 feet 24-inch pipeline within the 860 Pressure Zone in Alta Road from the Alta Gate location to Airway Road. This project will be constructed as part of the Otay Mesa recycled water system. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for development of Otay Mesa and link the planned 860-1 Reservoir with the recycled water transmission system in Otay Mesa. Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102-575. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $135 $600 $600 $410 $0 $0 $4,500 PRIOR YEARS: TOTAL $2,755 70 R2077 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2001 12/1/2009 1/1/2010 6/1/2011 $164 $451 PROJECT PHASE: 7/1/2011 6/1/2017 $3,885 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1332 39 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 71 R2087RecPL - 24-Inch, 927 Zone, Wueste Road - Olympic/Otay WTP Kevin Cameron 5/23/2006 R2048, R2058, R2077 1 22 1 $7,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 15,100 feet of 24-inch pipeline within the 927 Pressure Zone in Wueste Road from Olympic Parkway to near the existing City of San Diego Otay WTP. This project will be constructed as part of the Otay Mesa Recycled Water System Supply Link. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for development of Otay Mesa and is a part of the link to the 927 Pressure Zone supply to the planned 860-1 Reservoir within the Otay Mesa recycled water system. Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102-575. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $5 $5 $5 $5 $5 $5,925 $7,000 PRIOR YEARS: TOTAL $1,050 72 R2087 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 9/1/2006 12/1/2009 1/1/2010 6/1/2011 $180 $765 PROJECT PHASE: 7/1/2016 6/1/2019 $6,055 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1312 85 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 73 R2091RecPS - 927-1 Pump Station Upgrade (10,000 GPM) and System Enhancements Daniel Kay 5/29/2007 1 22 1 $2,130,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project consists of increasing the capacity of the existing station from 6,600 gallons per minute (gpm) to 10,000 gpm, installing three pressure reducing stations in the 927 Pressure Zone, replacing service saddles in a few streets, replacing 1,800 feet of 16-inch pipeline in EastLake Parkway, and replacing 1,200 of 16-inch pipeline in Hunte Parkway. JUSTIFICATION OF PROJECT: The overall operating conditions of the pump station have been modified as a result of the planned service to the Otay Mesa System recycled water system from the Central Area System. As a result the existing pumps within the station are undersized and some of the existing recycled water system pipelines will experience operating pressures above their rated pipeline pressure class. The project is planned to be accomplished in two phases. COMMENTS: Planned expenditures for FY 12 carried over to FY 13. Project substantially complete. FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $250 $0 $0 $0 $0 $0 $2,130 PRIOR YEARS: TOTAL $1,880 74 R2091 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2007 4/1/2008 5/1/2008 1/1/2011 $60 $120 PROJECT PHASE: 6/1/2011 12/1/2013 $1,950 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 115 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/30/2013Bob Kennedy 75 R2107RWCWRF Screening Compactor and Chlorine Injectors Enclosure Gary Stalker 5/15/2011 3 20 2 $130,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Install screening compactor at the RWCWRF headwork, repair concrete supports at headworks, and construct a 3-sided enclosure around the chlorine injectors at the reclamation plant chlorine contact basin. JUSTIFICATION OF PROJECT: The screening compactor will remove waste material at the headwork to the RWCWRF and compact the material for disposal to a landfill. This will result in reducing the amount of solids discharged back to Metro. The PVC chlorine injectors at the chlorine contact basin at the reclamation plant need to be protected from sunlight. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $60 $0 $0 $0 $0 $0 $130 PRIOR YEARS: TOTAL $70 76 R2107 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2012 6/1/2014 $130 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 319 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 77 R2108Res - 927-1 Reservoir Cover Replacement Jeff Marchioro 5 22/27 1 $1,400,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of the existing membrane floating cover and liner with new membrane system. JUSTIFICATION OF PROJECT: The existing membrane floating cover and liner have reached the end of their useful life and requires replacement to meet regulatory requirements. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $100 $1,300 $0 $0 $0 $0 $1,400 PRIOR YEARS: TOTAL $0 78 R2108 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2013 1/1/2014 1/1/2014 10/1/2014 $50 $100 PROJECT PHASE: 10/1/2014 7/1/2015 $1,250 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 172 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 79 R2110RecPS - 927-1 Optimization and Pressure Zone modifications Jeff Marchioro R2091 1 22 1 $150,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Improve the control strategy to increase pumping capacity and streamline operation of the pump station. As a result of this effort, replacement of 5 service saddles on Clubhouse Drive will need to be replaced to higher pressure class saddles. JUSTIFICATION OF PROJECT: Revising the control strategy will increase pumping capacity and improve the District's ability to operate the pump station during off-peak hours when electricity rates are low. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $150 $0 $0 $0 $0 $0 $150 PRIOR YEARS: TOTAL $0 80 R2110 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2013 10/1/2013 10/1/2013 12/1/2013 $10 $10 PROJECT PHASE: 12/1/2013 6/1/2013 $130 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 115 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 81 S2039Hidden Mountain Lift Station Enclosure Gary Stalker 5/15/2012 5 18 2 $37,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Install a larger enclosure around the Hidden Mountain lift station. JUSTIFICATION OF PROJECT: The Hidden Mountain lift station enclosure is too small to provide staff access for the preventative and corrective maintenance of the station. The three way valve at this lift station cannot be accessed for exercising and maintenance. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 18 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $8 $0 $0 $0 $0 $0 $37 PRIOR YEARS: TOTAL $29 82 S2039 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2012 12/1/2013 $37 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1272 C1 377 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 83 S2043RWCWRF Sludge Handling System Lisa Coburn-Boyd R2096 3 20 2 $1,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will provide funding for a Sludge Handling System at the RWCWRF to reduce the amount of solids the District sends to Metro. JUSTIFICATION OF PROJECT: The District currently sends all sludge produced at RWCWRF to Metro for treatment. The District's Wastewater Management Plan provided a preliminary estimate of the cost of handling sludge at the RWCWRF that is close to the cost Metro charges the District for treatment of solids. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 18 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $50 $100 $1,250 $100 $0 $0 $1,500 PRIOR YEARS: TOTAL $0 84 S2043 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2013 12/1/2014 12/1/2014 12/1/2015 $100 $150 PROJECT PHASE: 12/1/2015 12/1/2016 $1,250 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 319 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 85 P2366 APCD Engine Replacements and Retrofits Doug Rahders 12/6/2000 0 District Wide 1 $3,488,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will replace and/or retrofit 14 diesel fuel burning engines with the best technology exhaust gas control systems throughout the Otay Water District to comply with APCD engine emission regulations. The Otay Water District also needs to replace, re-power, and/or retrofit the heavy vehicle diesel fleet to comply with upcoming emissions regulations. JUSTIFICATION OF PROJECT: The Otay Water District is required to replace and/or retrofit its engines to meet current APCD requirements including the Air Toxics Control Measures, and to be consistent with the intended operation of the engines to meet system demands. The Otay Water District also needs to replace, re-power, and/or retrofit the heavy vehicle diesel fleet to meet future emissions requirements. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $5 $250 $225 $220 $243 $45 $3,488 PRIOR YEARS: TOTAL $2,500 86 P2366 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 12/1/2000 6/1/2001 7/1/2001 6/1/2010 $113 $312 PROJECT PHASE: 7/1/2010 6/1/2019 $3,063 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 87 P2382Safety and Security Improvements Steve Dobrawa 6/5/2002 0 District Wide 1 $3,397,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to improve the security of the Otay Water District facilities by installing and upgrading to current standards the hardware and software required to provide access control, video surveillance, intrusion detection and response, and SCADA communication. JUSTIFICATION OF PROJECT: Although existing facilities are relatively safe and secure, the Federal government has recommended that security to water systems be improved. The project is required to fund needed changes and improvements to District facilities. General Fund at 40% expansion and 60% replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 40 %0 %0 %0 %40 % Replacement 0 %0 %60 %0 %60 % TOTAL:40 %0 %60 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $500 $200 $200 $200 $100 $300 $3,397 PRIOR YEARS: TOTAL $1,897 88 P2382 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2002 8/1/2003 9/1/2003 6/1/2010 $62 $169 PROJECT PHASE: 8/1/2004 6/1/2017 $3,166 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 89 P2440I-905 Utility Relocations Jeff Marchioro 6/2/2004 2 7 1 $1,600,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for all utility relocations required due to construction of I-905 on the Otay Mesa. Pipeline relocations vary from 12-inch to 24-inch. Five locations have been identified where existing facilities are in conflict with I-905. JUSTIFICATION OF PROJECT: Caltrans is constructing I-905, which has resulted in utility conflicts with Otay pipelines. In all cases, the Otay Water District has prior and superior rights. The facilities must be relocated prior to Caltrans construction of I-905. The cost of the facilities relocations that have prior rights will be reimbursed by Caltrans. Utility agreements were developed by Caltrans for each of the required facility relocations. Any betterment work such as pipeline size increase and/or additional length are at the Otay Water District's expense. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $10 $0 $0 $0 $0 $0 $1,600 PRIOR YEARS: TOTAL $1,590 90 P2440 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2004 9/1/2006 10/1/2003 9/1/2006 $121 $332 PROJECT PHASE: 10/1/2006 12/1/2013 $1,147 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1351 10 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 91 P2453 SR-11 Utility Relocations Jeff Marchioro 5/23/2006 2 7 1 $2,250,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for all utility relocations required due to construction of SR-11 on the Otay Mesa. Facility relocations vary in size from 8-inch to 24-inch. Both the potable and recycled water systems are impacted. JUSTIFICATION OF PROJECT: Caltrans will construct SR-11, which will result in utility conflicts with existing Otay Water District facilities at various locations. In most cases, the Otay Water District does have prior and superior rights. The facilities must be relocated prior to Caltrans construction of SR-11. The cost of the facilities relocations that have prior rights will be reimbursed by Caltrans. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $125 $700 $565 $700 $0 $0 $2,250 PRIOR YEARS: TOTAL $160 92 P2453 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2006 6/1/2010 7/1/2009 6/30/2014 $20 $350 PROJECT PHASE: 10/8/2014 6/30/2017 $1,880 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1351 5 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 93 P2477Res - 624-1 Reservoir Cover Replacement Jeff Marchioro 6/23/2008 1 22 2 $1,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of the existing membrane floating cover with new membrane material system. JUSTIFICATION OF PROJECT: The existing floating membrane cover has reached the end of its useful life and requires replacement to meet regulatory requirements. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $50 $0 $0 $0 $0 $0 $1,000 PRIOR YEARS: TOTAL $950 94 P2477 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2008 2/1/2012 2/1/2012 10/10/2012 $8 $110 PROJECT PHASE: 10/10/2012 9/1/2013 $882 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 114 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 95 P2485SCADA Communication System and Software Replacement Gary Stalker 5/21/2009 0 District Wide 1 $1,846,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will replace the existing SCADA software and radio communication system and install fuel level transmitters on all diesel fuel tanks. A Battery Backup System will be installed at remote SCADA/Radio sites without emergency power generators. JUSTIFICATION OF PROJECT: The vendor will no longer be upgrading or supporting the existing system beginning 2012. The radio equipment needs replacement to allow for increased band width capability to increase security systems functionality. The fuel level transmitters on all diesel fuel tanks and remote SCADA monitoring will provide supervisors with real time fuel levels to monitor available runtime on stand-by engines during extended power outages. The battery backup system will provide continuous communications and SCADA monitoring and control for 3 days, if the District lost power at sites without emergency power generators. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $540 $455 $0 $0 $0 $0 $1,846 PRIOR YEARS: TOTAL $851 96 P2485 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2009 6/1/2015 $1,846 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 97 P2493624-2 Reservoir Interior/Exterior Coating Kevin Cameron 5/21/2009 4 22 1 $1,950,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior and exterior coating of the 624-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the most recent reservoir assessment report dated August 8, 2008 the 624-2 Reservoir interior coating is in relatively poor condition and is in need of replacement. Based on the FY 2012 Corrosion Report for Reservoir Coatings, the exterior is scheduled to be replaced in FY 2013. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $1,550 $390 $0 $0 $0 $0 $1,950 PRIOR YEARS: TOTAL $10 98 P2493 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 8/1/2010 9/1/2010 12/31/2013 $5 $95 PROJECT PHASE: 1/1/2014 8/1/2014 $1,850 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 130 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 99 P2494Multiple Species Conservation Plan Lisa Coburn-Boyd 5/21/2009 P2495 0 District Wide 1 $887,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to provide funding to develop a plan to streamline the environmental permitting processes for the capital improvement program projects to be constructed. JUSTIFICATION OF PROJECT: The project will save time and money when compared to environmental permitting each capital improvement program project individually. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $60 $0 $0 $0 $0 $0 $887 PRIOR YEARS: TOTAL $827 100 P2494 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 6/30/2014 $887 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 101 P2495San Miguel Habitat Management/Mitigation Area Lisa Coburn-Boyd 5/21/2009 P2494 5 22 1 $2,040,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to provide funding for the establishment and management of mitigation areas on capital improvement program projects sites and at the San Miguel Habitat Management Area to offset environmental impacts due to construction activities. JUSTIFICATION OF PROJECT: The resource agencies (USFWS, CDFG, etc.) require areas of land to be set aside, established, managed, and maintained in order to mitigate for impacts due to construction activities. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $140 $180 $190 $200 $200 $200 $2,040 PRIOR YEARS: TOTAL $930 102 P2495 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 6/30/2019 $2,040 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 159 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 103 P2496Otay Lakes Road Utility Relocations Dan Martin 5/21/2009 4 5 1 $325,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for all utility relocations required to accommodate the City of Chula Vista road improvement project located along Otay Lakes and Telegraph Canyon Roads. JUSTIFICATION OF PROJECT: The Otay Water District will be required to relocate all conflicting systems at its own expense for the City of Chula Vista has prior and superior rights. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $70 $0 $0 $0 $0 $0 $325 PRIOR YEARS: TOTAL $255 104 P2496 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 8/1/2009 9/1/2009 12/1/2009 $4 $11 PROJECT PHASE: 1/1/2010 12/31/2013 $260 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 113 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 105 P2504Regulatory Site Access Road and Pipeline Relocation Kevin Cameron 5/17/2010 P2466 5 20 1 $900,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Improve the existing access road from the proposed sheriff substation site to the Regulatory Reservoir Site. JUSTIFICATION OF PROJECT: Improving the existing access road will provide for increased safety and all weather permanent access to the Regulatory Reservoir Site. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 1 0 %50 %0 %0 %50 % Replacement 0 %0 %50 %0 %50 % TOTAL:0 %50 %50 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $325 $275 $0 $0 $0 $0 $900 PRIOR YEARS: TOTAL $300 106 P2504 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 9/1/2010 10/1/2010 12/1/2012 $85 $175 PROJECT PHASE: 1/1/2013 9/1/2014 $640 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 331 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 107 P2507East Palomar Street Utility Relocation Kevin Cameron 5/17/2010 2 10 2 $900,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the necessary utility relocations due to construction improvements to I-805 near East Palomar Street. Both the existing potable and recycled water systems will be impacted. JUSTIFICATION OF PROJECT: Caltrans will be making improvements to I-805 that will result in conflicts with existing pipelines. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $230 $375 $0 $0 $0 $0 $900 PRIOR YEARS: TOTAL $295 108 P2507 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 12/1/2010 1/1/2011 12/1/2011 $5 $195 PROJECT PHASE: 1/1/2012 6/1/2015 $700 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1330 80 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 109 P2508Pipeline Cathodic Protection Replacement Program Jeff Marchioro 5/17/2010 0 District Wide 1 $300,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement and repairs of existing cathodic protection systems on various pipelines. JUSTIFICATION OF PROJECT: The ongoing cathodic protection program efforts have identified various pipelines for anode replacement, cathodic test station repair, installation of isolation kits, and repair of existing anode beds. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $60 $125 $100 $0 $0 $0 $300 PRIOR YEARS: TOTAL $15 110 P2508 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 6/1/2013 6/1/2013 12/1/2013 $15 $45 PROJECT PHASE: 3/5/2014 9/1/2016 $240 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 111 P2513East Orange Avenue Bridge Crossing Kevin Cameron 5/16/2011 2 10 1 $1,350,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 1,900 feet of 12-inch pipeline in Olympic Parkway / East Orange Avenue across I-805. This project will provide a second pipeline to the area west of I-805. JUSTIFICATION OF PROJECT: The service area west of I-805 needs to have fire flow capacity increased as well as increased system reliability. City of Chula Vista and Caltrans are requiring work to be done at night to limit traffic impacts. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $300 $0 $0 $0 $0 $0 $1,350 PRIOR YEARS: TOTAL $1,050 112 P2513 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 6/1/2013 7/1/2013 5/1/2013 $25 $275 PROJECT PHASE: 6/1/2013 6/1/2014 $1,050 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1330 65 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 113 P2515870-1 Reservoir Paving Kevin Cameron 5/16/2011 2 7 2 $550,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for repaving the existing perimeter road around the 870-1 Reservoir and add roadway paving to the reservoir. JUSTIFICATION OF PROJECT: The existing perimeter reservoir roadway is at the end of its useful life and access to the reservoir is limited in the winter months and unsafe. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $490 $0 $0 $0 $0 $0 $550 PRIOR YEARS: TOTAL $60 114 P2515 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 12/1/2011 1/1/2012 6/30/2013 $50 $75 PROJECT PHASE: 7/1/2013 12/31/2013 $425 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1332 55 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 115 P2518803-3 Reservoir Interior/Exterior Coating Kevin Cameron 5/15/2012 5 20 2 $750,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior and exterior coating of the 803-3 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2010 Cathodic Assessment Report, the 803-3 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $125 $0 $0 $0 $0 $0 $750 PRIOR YEARS: TOTAL $625 116 P2518 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 9/1/2012 10/1/2012 12/1/2013 $10 $65 PROJECT PHASE: 1/1/2013 9/1/2013 $675 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1272 370 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 117 P2519 832-2 Reservoir Interior/Exterior Coating Kevin Cameron 5/15/2012 5 2 2 $775,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior and exterior coating of the 832-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2010 Cathodic Assessment Report, the 832-2 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $335 $0 $0 $0 $0 $0 $775 PRIOR YEARS: TOTAL $440 118 P2519 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 9/1/2012 10/1/2012 12/1/2013 $10 $50 PROJECT PHASE: 1/1/2013 9/1/2013 $715 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1272 332 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 119 P2520Motorola Mobile Radio Upgrade Jose Martinez 5/16/2011 0 District Wide 1 $100,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for Motorola radio upgrades which involves three components, radio repeater upgrade, portable and base unit upgrades, and vehicle mobile radio upgrades. JUSTIFICATION OF PROJECT: The existing Motorola radio equipment is an essential part of the District's Emergency Response Program. A recent assessment of the radio equipment has determined that the equipment has reached the end of its useful life and needs upgrades. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $30 $0 $0 $0 $0 $0 $100 PRIOR YEARS: TOTAL $70 120 P2520 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 8/1/2011 6/30/2014 $100 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 121 P2521Large Meter Vault Upgrade Program Roger Holly 5/16/2011 0 District Wide 1 $600,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the retrofit and upgrade of approximately 40 large water meters and vaults to above ground standards. JUSTIFICATION OF PROJECT: The existing large meters are installed in below grade vaults which create increased costs and safety issues due to confined space requirements. The existing below grade systems are subject to flooding and create corrosive environments. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $105 $100 $100 $113 $0 $0 $600 PRIOR YEARS: TOTAL $182 122 P2521 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 8/1/2011 6/1/2016 $600 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 123 P2531944-1 Reservoir Interior & Exterior Coating Kevin Cameron 5 9 2 $175,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior and exterior coating of the 944-1 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2011 Cathodic Assessment Report, the 944-1 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $5 $160 $10 $0 $0 $0 $175 PRIOR YEARS: TOTAL $0 124 P2531 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/1/2014 8/31/2014 9/1/2014 12/31/2014 $5 $25 PROJECT PHASE: 1/1/2015 8/1/2015 $145 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1272-G1 322 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 125 P2532944-2 Reservoir Interior & Exterior Coating Kevin Cameron 5 9 2 $725,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior and exterior coating of the 944-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2011 Cathodic Assessment Report, the 944-2 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $5 $660 $60 $0 $0 $0 $725 PRIOR YEARS: TOTAL $0 126 P2532 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/1/2014 8/31/2014 9/1/2014 12/31/2014 $5 $75 PROJECT PHASE: 1/1/2015 8/1/2015 $645 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1292-G1 322 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 127 P2535458-2 Reservoir Interior Coating Kevin Cameron 5/15/2012 2 9 2 $425,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior coating of the 458-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2011 Cathodic Assessment Report, the 458-2 Reservoir interior coating is in relatively poor condition and is in need of replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $345 $70 $0 $0 $0 $0 $425 PRIOR YEARS: TOTAL $10 128 P2535 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/1/2013 9/30/2013 10/1/2013 12/31/2014 $5 $65 PROJECT PHASE: 1/1/2014 6/1/2014 $355 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1330-J4 66 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 129 P2538Administration and Operations Building Fire Sprinkler Replacement Program Kevin Cameron 5 1 1 $400,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: A licensed fire sprinkler designer is required to prepare plans and specifications for the work and obtain all permits and approvals before the project can be competitively bid by contractors. JUSTIFICATION OF PROJECT: Inspections of the Administration building and the Operations building fire sprinkler systems are performed to NFPA-25, California Code of Regulations, Title 19 and Local Fire Department requirements annually. A recent inspection of the fire sprinkler system has identified corrosion throughout the systems as the cause for leaks the District experienced last year and is recommending the replacement of the existing fire sprinkler systems piping. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $100 $300 $0 $0 $0 $0 $400 PRIOR YEARS: TOTAL $0 130 P2538 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 12/1/2012 7/1/2013 7/1/2013 3/1/2014 $0 $50 PROJECT PHASE: 3/1/2014 12/1/2014 $350 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 131 R2109Sweetwater River Wooden Trestle Improvement for the Recycled Water Forcemain Bob Kennedy 3 22/27 2 $350,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Modification of the wooden trestle to reduce the potential damage of a wildfire event to the structure. JUSTIFICATION OF PROJECT: The existing wooden trestle over the Sweetwater River supports a 14-inch steel force main for recycled water. The 200 foot long wooden trestle was built in 1980 and a recent assessment has recommended a brush management plan be prepared to extend into the adjacent San Diego National Wildlife Refuge. The report also recommends the installation of a heat shield, installation of a fire suppression system, or modification of the existing structure to reduce the threat of wildfire to the structure. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $100 $100 $150 $0 $0 $0 $350 PRIOR YEARS: TOTAL $0 132 R2109 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2013 6/1/2014 7/1/2014 6/1/2015 $100 $100 PROJECT PHASE: 7/1/2015 6/1/2016 $150 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 319 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $3,000 $3,100 $3,200 $9,300 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 133 R2111RWCWRF - RAS Pump Replacement Lisa Coburn-Boyd R2096 3 20 1 $100,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Replace and upgrade the RAS pumps to 350 GPM to improve process control of the plant. . JUSTIFICATION OF PROJECT: These improvements are needed due to increased pumping requirements of the new process. The existing pumps were installed in 1992 and are reaching the end of their useful life. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $100 $0 $0 $0 $0 $0 $100 PRIOR YEARS: TOTAL $0 134 R2111 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: $100 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 319 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/30/2013Bob Kennedy 135 S2012 San Diego County Sanitation District Outfall and RSD Outfall Replacement Bob Kennedy 6/4/2003 3 18 1 $3,550,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the Otay Water District proportionate share of the San Diego County Sanitation District total costs for replacement of various system components of the existing Spring Valley and Rancho San Diego Outfall Systems per terms of an existing agreement with the SVSD. The reimbursement also includes a proportionate share of operating and maintenance costs. JUSTIFICATION OF PROJECT: Various components of the San Diego County Sanitation District Spring Valley Outfall and the Rancho San Diego Outfall are in very bad condition and are need of repair and/or replacement. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $450 $450 $450 $450 $450 $440 $3,550 PRIOR YEARS: TOTAL $860 136 S2012 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2003 6/1/2019 $3,550 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 137 S2024Campo Road Sewer Main Replacement Kevin Cameron 5/17/2010 3 18 2 $5,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funds to upgrade the sewer main capacity of approximately 11,050 feet of existing 10-inch PVC sewer main, 450 feet of 10-inch reinforced polymer mortar pipe sewer main, and 50 feet of 15-inch sewer main. The project location begins at the south end of Avocado Blvd, through the Rancho San Diego Village Shopping Center, paralleling SR-94/Campo Road in the adjacent open space. JUSTIFICATION OF PROJECT: The existing sewer main is under sized and must be replaced to increase capacity. Portions of the sewer main are located in areas of sensitive habitat making it difficult to access for maintenance. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 18 0 %100 %0 %0 %100 % TOTAL:0 %100 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $275 $1,975 $2,375 $825 $0 $0 $5,500 PRIOR YEARS: TOTAL $50 138 S2024 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 6/1/2014 7/1/2015 4/1/2016 $325 $825 PROJECT PHASE: 4/1/2016 6/1/2017 $4,350 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 330 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 139 S2027Rancho San Diego Pump Station Rehabilitation Bob Kennedy 5/16/2011 3 18 2 $2,900,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the rehabilitation of the Rancho San Diego Pump Station located near Singer Lane. JUSTIFICATION OF PROJECT: The existing sewer pump station is over 20 years old and the pumps have reached the end of their useful lives. The pump station also needs improvements to bring the station up to current OSHA requirements. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $500 $2,350 $0 $0 $0 $0 $2,900 PRIOR YEARS: TOTAL $50 140 S2027 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 7/1/2013 7/1/2012 7/1/2014 $50 $500 PROJECT PHASE: 1/1/2013 7/1/2015 $2,350 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 331 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 141 S2033Sewer System Rehabilitation Jeff Marchioro 5/16/2011 5 18 1 $6,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for sewer system rehabilitation efforts that have been identified. These efforts involve replacement of approximately 13,000 lineal feet of failing or damaged pipe segments, separated pipe joints, etc. JUSTIFICATION OF PROJECT: The closed circuit television sewer assessment program process has assisted in the identification of sewer mains containing sags, which has allowed debris to form, and/or are damaged and need to be repaired. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $800 $1,000 $1,300 $800 $800 $1,000 $6,000 PRIOR YEARS: TOTAL $300 142 S2033 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 1/1/2016 3/1/2013 1/1/2017 $400 $1,000 PROJECT PHASE: 1/1/2014 1/1/2019 $4,600 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 143 P2282Vehicle Capital Purchases Doug Rahders 6/3/1996 0 District Wide 1 $5,021,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for capital purchase of various vehicles for daily Otay Water District functions. JUSTIFICATION OF PROJECT: Replacements or newly acquired vehicles will be used for operational and administrative functions throughout the entire Otay Water District. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $266 $450 $450 $475 $500 $0 $5,021 PRIOR YEARS: TOTAL $2,880 144 P2282 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 12/1/2000 6/1/2018 $5,021 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 145 P2285Office Equipment and Furniture Capital Purchases Steve Dobrawa 6/3/1996 0 District Wide 1 $589,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for capital purchase of various office equipment and furniture items used for daily Otay Water District functions. JUSTIFICATION OF PROJECT: Replacements or new acquisitions of office equipment and furniture will be used for operational and administrative functions throughout the entire Otay Water District. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $55 $15 $15 $0 $0 $0 $589 PRIOR YEARS: TOTAL $504 146 P2285 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 12/1/2000 6/1/2018 $589 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 147 P2286 Field Equipment Capital Purchases Doug Rahders 6/3/1996 255 District Wide 1 $1,758,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for capital purchase of various pieces of field equipment used for daily Otay Water District functions. JUSTIFICATION OF PROJECT: Replacements or new acquisitions of field equipment will be used for operational functions throughout the entire Otay Water District. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $149 $84 $68 $68 $68 $67 $1,758 PRIOR YEARS: TOTAL $1,254 148 P2286 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/1996 6/1/2019 $1,758 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 149 P2469Information Technology Network and Hardware Adolfo Segura 6/23/2008 0 District Wide 1 $2,509,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will provide hardware and operating system improvements in 2014 to create new functionality in the data center. - Net App Storage Area Network (SAN), Backup and Off-site Cloud Storage (DR Services): System Replacement ($150K) - Enhanced Network Switching ($200K) JUSTIFICATION OF PROJECT: Enhance data center hardware and software to accommodate purchase of new and more efficient services to enhance capacity, reliability, security, and disaster recovery. In addition, these funds will replace legacy end-of-life equipment. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 40 %0 %0 %0 %40 % Replacement 0 %0 %60 %0 %60 % TOTAL:40 %0 %60 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $350 $100 $100 $100 $200 $200 $2,509 PRIOR YEARS: TOTAL $1,459 150 P2469 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2008 6/30/2019 $2,509 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 151 P2470Financial System Enhancements Geoff Stevens 6/23/2008 0 District Wide 1 $2,322,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to develop enhancements and new integration functionality for Eden, GIS, Work-Order, and related core application systems. JUSTIFICATION OF PROJECT: This CIP funds the creation and enhancement and modifications of our existing financial information systems. Each year items which require software and hardware changes and additions to these systems are prioritized, scoped, and funded with this CIP. Funds are used for software development costs, software acquisition costs, consulting services, and associated new hardware. Items to be constructed and approximate costs for FY 2014 are listed below. Items for 2015 and beyond will be determined as part of the 2015-2017 strategic plan process. 1) Development with ESRI of GIS for Infrastructure Management $80K 2) Support for Eden modifications for Work Order, Purchasing, and Billing System Modifications ($50K) COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 40 %0 %0 %0 %40 % Replacement 0 %0 %60 %0 %60 % TOTAL:40 %0 %60 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $130 $100 $100 $100 $100 $161 $2,322 PRIOR YEARS: TOTAL $1,631 152 P2470 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2008 6/1/2019 $2,322 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 153 P2540Work Order Management System Replacement Geoff Stevens 0 District Wide 1 $700,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Replace existing work order system. JUSTIFICATION OF PROJECT: The work order system will organize and track all activities associated with District assets. As part of the implementation of enterprise asset management, the work order system will adopt a GIS centric architecture and integrate efficiently with other core systems. In addition, it needs to be able to assist in all phases of asset creation, maintenance, replacement, and decommission. The current system is at the end of its useful life and does not have the ability to be modified to meet these needs. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 40 %0 %0 %0 %40 % Replacement 0 %0 %60 %0 %60 % TOTAL:40 %0 %60 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $300 $300 $100 $0 $0 $0 $700 PRIOR YEARS: TOTAL $0 154 P2540 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2013 6/30/2016 $700 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 155 S2042Sewer Vehicle Capital Purchases Doug Rahders 5/15/2012 5 18 1 $367,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides sewer funding for capital purchase of various vehicles for daily Otay Water District functions. JUSTIFICATION OF PROJECT: Replacement or newly acquired vehicles will be used for operational functions throughout the Otay Water District sewer service area. It is planned to purchase two vehicles in Fiscal Year 2014. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $367 $0 $0 $0 $0 $0 $367 PRIOR YEARS: TOTAL $0 156 S2042 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2012 6/1/2013 $367 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/29/2013Bob Kennedy 157 R2082RecPL - 24-Inch, 680 Zone, Olympic Parkway - Village 2/Heritage Dan Martin 6/2/2004 R2083 2 22 2 $1,747,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 3,500 feet of 24-inch pipeline within the 680 Pressure Zone in Olympic Parkway through Village 2 to Heritage Road. Portions of this project will be constructed by developers and these are subject to reimbursement at actual cost per Board policy. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for the recycled water supply pumped from the 680-1 Pump Station to the 680 and higher pressure zones. Significant energy savings will occur due to lower total dynamic head requirements for the 680-1 Pump Station. Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102-575. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $1 $1 $1 $1 $1,000 $742 $1,747 PRIOR YEARS: TOTAL $1 158 R2082 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2004 6/1/2012 7/1/2012 6/1/2015 $0 $75 PROJECT PHASE: 7/1/2017 6/1/2019 $1,672 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1331 82 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $1,200 $1,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 159 R2083RecPL - 20-Inch, 680 Zone, Heritage Road - Village 2/Olympic Dan Martin 6/2/2004 R2082, R2084 1 22 2 $400,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 2,200 feet of 20-inch pipeline within the 680 Pressure Zone in Heritage Road through Village 2 to Olympic Parkway. This project will be constructed by developers and is subject to reimbursement at actual cost per Board policy. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for the recycled water supply pumped from the 680-1 Pump Station to the 680 and higher pressure zones. Significant energy savings will occur due to lower total dynamic head requirements for the 680-1 Pump Station. Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102-575. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $1 $1 $1 $1 $1 $395 $400 PRIOR YEARS: TOTAL $0 160 R2083 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2004 6/1/2018 7/1/2017 3/1/2018 $1 $4 PROJECT PHASE: 7/1/2018 6/1/2019 $395 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1331 82 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $700 $700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 161 R2084RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media Dan Martin 6/2/2004 R2083, R2085 1 22 3 $971,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 5,700 feet of 20-inch pipeline within the 680 Pressure Zone in Village 2 from Heritage Road to La Media Road in two phases. This project will be constructed by developers and is subject to reimbursement at actual cost per Board policy. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for the recycled water supply pumped from the 680-1 Pump Station to the 680 and higher pressure zones. Significant energy savings will occur due to lower total dynamic head requirements for the 680-1 Pump Station. Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102-575. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $1 $1 $1 $1 $350 $617 $971 PRIOR YEARS: TOTAL $0 162 R2084 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2004 6/1/2014 7/1/2015 6/1/2017 $1 $3 PROJECT PHASE: 7/1/2017 6/1/2019 $967 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1331 82 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $1,900 $1,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 163 R2085 RecPL - 20-Inch, 680 Zone, La Media - State/Olympic Dan Martin 6/2/2004 R2084 1 22 3 $600,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 3,800 feet of 20-inch pipeline within the 680 Pressure Zone in La Media Road from the high school site to Olympic Parkway. This project will be constructed by developers and is subject to reimbursement at actual cost per Board policy. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for the recycled water supply pumped from the 680-1 Pump Station to the 680 and higher pressure zones. Significant energy savings will occur due to lower total dynamic head requirements for the 680-1 Pump Station. Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102-575. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Expansion 100 %0 %0 %0 %100 % TOTAL:100 %0 %0 %0 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $1 $1 $1 $1 $1 $595 $600 PRIOR YEARS: TOTAL $0 164 R2085 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2004 6/1/2013 7/1/2013 6/1/2014 $0 $1 PROJECT PHASE: 7/1/2014 6/1/2019 $599 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1331 82 2014 2015 2016 2017 2018 2019 Total $0 $0 $1,300 $1,300 $0 $0 $2,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 165 R2094Potable Irrigation Meters to Recycled Water Conversions Dan Martin 5/21/2009 1 22 1 $1,700,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to fund the conversion of existing potable water irrigation systems to use recycled water within existing multifamily and commercial type developments located adjacent to existing recycled water mains within the City of Chula Vista. JUSTIFICATION OF PROJECT: The expansion of recycled water development allows for potable water savings and increases the purchases of supply from the South Bay Water Reclamation Plant. Water Supply project 40% expansion and betterment funds from ID 22 at 60%. COMMENTS: FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total Betterment ID 22 0 %60 %0 %0 %60 % New Water Supply Fee Projects 0 %0 %0 %40 %40 % TOTAL:0 %60 %0 %40 %100 % FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): FY FY FY FY FY FY FY 2014 2015 2016 2017 2018 2019 Total $150 $0 $0 $0 $0 $0 $1,700 PRIOR YEARS: TOTAL $1,550 166 R2094 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 12/1/2009 1/1/2010 6/1/2011 $80 $450 PROJECT PHASE: 7/1/2011 6/30/2014 $1,170 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: 2014 2015 2016 2017 2018 2019 Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/25/2013Bob Kennedy 167 IMPROVEMENT CAPACITY TOTAL NAME DISTRICT (ID)FEE (1)CHARGE (1) Capacity Fee Section 28.01 1,2,3,5,7,10,19,20,22,25,27 $7,903.58 $7,903.58 Triad Capacity Fee ID 22/27-BASE $5,914.77 $5,914.77 New Water Supply Fee $910.61 (1) This is based on a 3/4 inch water meter effective 7/1/2013. Note: For a full listing of fees per meter size visit the District's website at: www.otaywater.gov, Engineering, Public Services, Fees & Deposits, Effective 7/1/13. Water Meter Capacity Fees 168 Glossary The Capital Budget contains terminology that is unique to public finance and budgeting. The following budget glossary provides assistance in understanding these terms. Acre-Foot: The volume of water that will cover one acre to a depth of one foot. One acre-foot equals 435.6 units or 325,850 gallons. Annexation Fees: Whenever water service is requested for land outside the boundaries of the District it must first be annexed into the District. The annexation fee for water service was set at $1,477 per EDU on July 1, 2009. Whenever sewer service is requested for land outside the boundaries of an improvement district (ID) it must first be annexed into the ID. The fee for sewer annexation was set at $3,819 on December 16, 1998. These base rates are adjusted quarterly according to a cost of living index. The rates as of July 1, 2013 are $1,556.69 and $5,743.42 for water and sewer, respectively. Assets: Resources owned or held by the District that have monetary value. Availability Fees: The District levies charges each year in developed areas to be used for general purposes for construction of facilities, and in undeveloped areas to provide a source of funding for planning, mapping, and preliminary design of facilities to meet future development. Current legislation provides that any availability charge in excess of $10.00 per acre shall be restricted only for the purpose of constructing facilities in the improvement district for which it was assessed. Betterment Fees: In addition to other applicable water rates and charges, certain water customers pay a fee based on water service zone or improvement district. These are restricted for the use in the area where they are collected and may be used for the construction and maintenance of facilities. Betterment Fees for Maintenance: The Operating Budget earns betterment fees for maintenance work performed on infrastructure within special betterment zones, where fees are collected for the construction and maintenance of these specific assets. Capacity Fee: A connection fee is charged when a new water meter is placed into service. This fee is based on the estimated construction cost of expansion of the system to meet the needs of all future customers. This fee covers the cost including, but is not limited to, planning, design, construction, and financing of expansion of the system. Capacity Fee Revenues: These fees are earned by the Operating Budget as the Engineering Department supports expansion functions. 169 Glossary Capital Budget: The portion of the annual budget that appropriates funds for the purchase of capital equipment items and capital improvements. These expenditures are separated from regular operating items, such as salaries, utilities and office supplies. The Capital Budget includes funds for capital equipment purchases over $10,000, such as vehicles, furniture, machinery, microcomputers and special tools or $20,000 for infrastructure related items, which are distinguished from operating items according to their value and projected useful life. Capital Equipment: Fixed assets such as vehicles, marine equipment, computers, furniture, technical instruments, etc. which have a life expectancy of more than two years and a value over $10,000 or $20,000 for infrastructure related items (this may not extend useful life of the infrastructure, but without the purchase of the item, the whole asset is rendered useless and the dollar value to replace the item is $20,000 or more as described in the District’s Capitalization Policy). Capital Improvement Program: A long-range plan of the District for the construction, rehabilitation and modernization of the District-owned and operated infrastructure. CWA: The County Water Authority was organized in 1944 under the State County Water Authority Act for the primary purpose of importing Colorado River water to augment the local water supplies of the Authority's member agencies. The Authority purchases water from MWD which imports water from the Colorado River and the State Water Project. Debt Service: The District's obligation to pay the principal and interest of bonds and other debt instruments according to a predetermined payment schedule. Desalination: The removal of dissolved minerals (including salts) from seawater or brackish water. Engineered water desalination processes, which produce potable water from seawater or brackish water, have become important because many regions throughout the world suffer from water shortages. Expenditures/Expenses: These terms refer to the outflow of funds paid or to be paid for an asset, goods or services obtained regardless of when actually paid for. (Note: An encumbrance is not expenditure). An encumbrance reserves funds to be expended in a future period. Fiscal Year: Twelve-month term designating the beginning and ending period for recording financial transactions. The District has specified July 1 to June 30 as its fiscal year. Grants: Contributions or gifts of cash or other assets from another governmental agency to be used or expended for a specified purpose, activity, or facility. Capital grants are restricted by the grantor for the acquisition and/or construction of fixed assets. Operating grants are restricted by 170 Glossary the grantor for operating purposes or may be used for either capital or operating purposes at the discretion of the grantee. Interest Income: Earnings from the investment portfolio. Per District Policy Number 25, interest income will be allocated to improvement districts each month based upon each fund’s prior month-ending balance. Reserve Fund: The District maintains Reserve Funds per the District’s policy for both designated and restricted balances. Designated Reserve Funds are “general use” funds designated by the Board. Restricted reserves are those that are legally set aside for a particular purpose and cannot be used for any other purpose. Water Capacity Fees: Charges paid by customers to connect to a District water system for potable or recycled water service. Fees are determined by multiplying the demand factor for the meter size by the total of the District-wide capacity fee and applicable zone charge. 171 AF Acre-Foot/Feet AMR Automated Meter Reader/Reading APCD Air Pollution Control District ASCE American Society of Civil Engineers AWWA American Water Works Association CEQA California Environmental Quality Act CIP Capital Improvement Program CMAA Construction Management Association of America CSI California Solar Initiative CWA County Water Authority (San Diego) FCF Flow Control Facility FY Fiscal Year GAAP Generally Accepted Accounting Principles GIS Geographic Information System GPS Global Positioning System HWD Helix Water District ID Improvement District IID Imperial Irrigation District IMS Infrastructure Management System IRP Integrated Water Resources Plan LOPS Lower Otay Pump Station MBR Membrane Bioreactor MG Million Gallons MGD Million Gallons per Day MWD Metropolitan Water District O&M or O/M Operations and Maintenance OIS Otay Information System PB Pacific Bay PL Pipeline PS Pump Station RWCWRF Ralph W. Chapman Water Recycling Facility SANDAG San Diego Association of Governments SCADA Supervisory Control and Data Acquisition SDCWA San Diego County Water Authority SVSD Spring Valley Sanitation District VCP Vitrified Clay Pipe WD Water District WRMP Water Resources Master Plan WTP Water Treatment Plant List of Acronyms 172 Index At-A-Glance 2 Awards 4-6 Capital Facility Projects 42-84 Capital Improvement Program Narrative 17-18 Capital Purchases Budget 36 Capital Purchase Projects 144-156 CIP Budget Calendar 12 CIP Budget Guide 1 CIP Budget Process 13-14 CIP Funding Source and Category 27 CIP Justification and Impact on Operating Budget 30 CIP Project Index 40-41 CIP Project Schedule 31-35 CIP Project Sheet Description 37-39 CIP Projects 28-29 CIP Projects in Construction 21-25 CIP Reserve Funds 26 Current Economic Conditions 7 Demographics 9 Developer Reimbursement Projects 158-166 General Information 3 Glossary 169-171 Index 173 Letter of Transmittal ii-vii List of Acronyms 172 Major CIP Projects 20 Organization Chart 11 Replacement/Renewal Projects 86-142 Resolution No. 4210 15-16 Table of Contents i The Future 8 Water Meter Capacity Fees 168 173