HomeMy WebLinkAboutCapital Improvement Program Budget FY 2013-2018OTAY WATER DlSTRlCT . Capitallmprovement Program Budget Ftscal Year 2013-2018 Sprtng VaHey, Calif'omta Adopted Capltallmprovement Program Budget ftsca[ Year 2013-2018 GENERAL MANAGER Mark Watton SENIOR MANAGEMENT TEAM German Alvarez Assistant General Manager Joseph R. Beachem Chief Financial Officer Geoff Stevens Chief Information Officer Pedro Porras Chief of Water Operations Rod Posada Chief of Engineering Rom Sarno, Jr. Chief of Administrative Services BOARD OF DIRECTORS President Jose Lopez Division 4 Vice President David Gonzalez, Jr. Division 1 Treasurer Gary Croucher. Division 3 Mitchell Thompson Division 2 Mark Robak Division 5 Table of Contents Page Letter of Transmittal ii GENERAL INFORMATION CIP Budget Guide 1 At-A-Glance 2 General Information 3 Financial Awards 4 Awards 6 Current Economic Conditions 7 The Future 8 Demographics 9 Organization Chart 10 CIP Budget Calendar 11 CIP Budget Process 12 Resolution No. 4195 14 CAPITAL BUDGET SUMMARY Capital Improvement Program Narrative 16 Major CIP Projects 18 CIP Projects in Construction 19 CIP Reserve Funds 23 CIP Funding Source and Category 24 CIP Projects 25 CIP Justification and Impact on Operating Budget 27 CIP Project Schedule 28 Capital Purchases 34 CIP PROJECTS CIP Project Sheet Description 35 CIP Project Index 37 Capital Facility Projects 39 Replacement/Renewal Projects 85 Capital Purchase Projects 159 Developer Reimbursement Projects 173 APPENDIX Water Meter Capacity Fees 179 Glossary 180 List of Acronyms 183 Index 184 i September 4, 2012 Honorable Board of Directors Otay Water District I am pleased to present the Otay Water District’s Adopted Operating and Capital Budget for Fiscal Year 2013. This year’s budget supports the management plan to finance all of the District’s services and programs during the 2013 fiscal year. The mission of the District is to provide high value water and wastewater services to the customers of the Otay Water District, in a professional, effective and efficient manner. As in the past few years, we continue to deal with numerous challenges resulting from the slow recovery from the largest economic downturn since the Great Depression. The District also faces large rate increases from San Diego County’s wholesale water suppliers. San Diego County has very limited natural supplies of water and therefore must rely on imported water from Northern California and the Colorado River. The wholesale and retail water agencies serving San Diego County recognized their dependence on imported water in the early 1990s and since that time have been implementing programs to create a more reliable, robust water system, one that will also increase water independence. Programs to secure more water, as well as a more reliable water supply, are expensive and represent a contributing factor to increasing costs. Given the continuing uncertain times, efforts to keep rate increases to a minimum, without risking safety or reliability, the District must find the best solutions that balance many imperatives. The tool the District will use to accomplish this is the 2012-2014 Strategic Business Plan. The District’s first strategic plan was developed in 2003 and it has been updated every three years since then. We are now entering the second year of the 2012-2014 Strategic Plan. As with previous plans, the focus has been on the District’s transformation from a growth-centric to a maintenance-based organization. Where growth had been a significant focus in the early years of the District’s existence, today we have become equally focused on managing long-term maintenance and replacement of infrastructure. As an organization matures, fewer resources are needed to support growth, but the effort to maintain and improve infrastructure and assets increases. In addition, over time, an organization derives income more from customer rates and less from developer fees. At this stage in its development, increased maintenance and replacement costs place pressure on customer rates. To balance the customer’s interest in minimizing rate increases while also maintaining an organization’s infrastructure investments and a strong financial position, it must place greater ii emphasis on internal efficiency and the development of technology assisted best practices. In effect, an organization must use investments in technology to do more with the same or even fewer resources. A goal of the District’s earlier strategic plans included capitalizing on the technology investments and utilizing those technologies to continually improve efficiency and productivity. The success of this approach is evidenced by the gains in efficiency and by the reduction in staffing, even while the customer base has grown in recent years. Furthermore, the District has been able to absorb some of the pass-though costs from our water suppliers by increased efficiency and improved productivity that help address customer concerns about rising water rates. 17 4 . 7 5 17 2 . 7 5 16 8 . 7 5 16 6 15 9 15 6 14 8 120 130 140 150 160 170 180 Reduction of 15.3% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 2007 2008 2009 2010 2011 2012 2013 82.4 69.1% CWA vs. Otay Water District Rate Increases CWA Water Cost Increase Otay Water Rate Increase Population s Population Population Employee Count iii In the annual survey of water rates, for a typical District customer, Otay’s rates continue to be among the lowest in San Diego County. In this and coming years, the District will continue its efforts to improve business processes to further increase efficiency and productivity through adherence to the 2012-2014 Strategic Plan. Today, the District provides water service to nearly 48,540 potable and 695 recycled water customers within approximately 125.5 square miles of southeastern San Diego County. All of the potable water sold to customers is purchased from the San Diego County Water Authority (CWA). Fifty eight percent of this water is in turn purchased from the region’s primary water importer, the Metropolitan Water District of Southern California (MWD). The District also has entered into an agreement with the CWA to have the neighboring Helix Water District treat imported water on behalf of the Otay Water District at their Levy Water Treatment Plant. This action brought regional water treatment closer to customers, which helps reduce dependence on water treatment facilities located outside of San Diego County. The District also owns and operates a wastewater collection and recycling system to provide public sewer service to approximately 4,652 homes and businesses. Wastewater collected is delivered to the Ralph W. Chapman Water Recycling Facility (RWCWRF), which is capable of reclaiming wastewater at a rate of 1.3 million gallons per day. In addition to the Chapman facility, the District purchases up to 6 million gallons per day of recycled water from the City of San Diego’s South Bay Water Reclamation Plant. Recycled water from these two sources is used to irrigate golf courses, schools, public parks, roadway landscapes, and other approved uses in the City of Chula Vista, California. The use of recycled water reduces dependence on imported supplies and provides a local supply that diversifies District resources. BUDGET SUMMARY The Otay Water District’s operating expenditures consist of three major sectors: potable water, recycled water, and sewer, budgeted at $82,318,200 for Fiscal Year 2013. Revenues from potable and recycled water are projected to be $69,456,800, about $4,152,500 (6.4%) more than the Fiscal Year 2012 budget. Water sales volumes are expected to increase slightly by 1% over iv FY 2012 actual sales as the economy is slowly improving, while efforts to promote water conservation continue. Rate increases are therefore essential to offset the higher wholesale cost of water. Sewer revenues are projected to be $2,555,200, about $219,200 more than Fiscal Year 2012. This increase from higher rates is primarily to cover $4.4 million of additional capital projects over the next six years. The remaining budgeted revenues of $10.3 million come from various special fees, assessments, and miscellaneous income. Significant aspects of the Operating Budget are:  A balanced budget meeting the goals of the Strategic Plan.  The use of an economist to project growth for the region.  An updated six-year Rate Model to ensure sound financial planning and reserve levels.  Ongoing water supply rate increases of 9.1% from MWD and CWA because of the high cost of supply programs, higher energy costs, and operating costs.  Implemented rate increases in potable, recycled water, and sewer. This included pass- through rate increases from CWA and the County of San Diego.  In response to the economic slowdown, the District has again reduced staffing levels from 156 full-time equivalent positions to 148.  Of San Diego County’s 23 water agencies, Otay’s water rates are below the county-wide average. The Fiscal Year 2012-13 Capital Improvement Program (CIP) Budget consists of 70 projects and a budget of $18.0 million. The budget emphasizes long-term planning for ongoing programs while functioning within fiscal constraints and population growth. This year’s CIP budget decreased by $4.6 million compared to last year’s projection, due to the completion of some large projects as well as the deferral of projects to match the timing of land development. THE FUTURE The coming years will continue to pose challenges for those in California’s water community. For instance, it is uncertain if the challenges facing the Sacramento-San Joaquin Bay Delta, the source of 30 percent of Southern California’s water supply, will be addressed and at what cost to end users. Serious challenges also jeopardize water coming from the Colorado River. Furthermore, as the cost of water has increased to the retail customer, sales have decreased. As one would expect, water sales reductions have impacted revenues and will continue to affect the District’s finances. With this in mind, our success as an organization is vastly enhanced by the practices and policies put in place by the Board of Directors to ensure the strength and stability of the District even as we move forward through uncertain times. We are fully confident that with these policies and practices, supported by dedicated and talented staff, we will achieve continued success as an organization and, thus, assure the well-being of the people we serve. In adopting this budget, the challenges presented this year were met by the Otay Water District Board of Director’s resolve to keep the stability and financial strength of the District as one of its highest priorities. v AWARDS AND ACKNOWLEDGMENTS  The Government Finance Officers Association of the United States and Canada (GFOA) presented a Distinguished Budget Presentation Award to Otay Water District, California for its annual budget for the fiscal year beginning July 1, 2011. In order to receive this award, a governmental unit must publish a budget document that meets program criteria as a policy document, as an operations guide, as a financial plan, and as a communica- tions device.  The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Certificate of Award for Excellence in Operating Budgeting for Fiscal Year 2011-2012.  The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Certificate of Award for Excellence in Capital Budgeting for Fiscal Year 2011-2012.  The Municipal Information Systems Association of California (MISAC) presented the 2010-2011 Award for Excellence Information Technology Practices to Otay Water District. The award recognizes outstanding practices in Information Technology that have met or surpassed local government standards. In conclusion, this budget reflects the vision of the Board of Directors of the Otay Water District, its management, and its employees. We will continue to strive to make improvements in our budget processes, including an extensive review and analysis of projections for revenues, expenditures, capital projects, and reserves. I would like to thank all the staff involved in this process for the efforts put forth in the preparation of this budget to ensure a successful outcome. To the Board of Directors, we acknowledge and appreciate their continued support and direction in achieving excellence in financial management. __ Mark Watton, General Manager vi CIP Budget Guide The District views the Capital Improvement Program (CIP) Budget as an essential tool for proper financial management of the CIP projects. The District manages growth and maintenance of assets through this program. This CIP budget is developed with input from the various project managers throughout the organization and is adopted prior to the start of each fiscal year for the current fiscal year and five subsequent years. It is designed and presented for the general needs of the District, its staff, and citizens. It is a comprehensive and balanced financial plan. This plan features the CIP budget based on demands for services and the impact on the District’s financial status and future plans. The budget book is divided into the following sections. General Information The introductory section contains an overview and general information about the District including the organization chart and awards received. Also included are the budget calendar, a description of the budget process, and the resolution adopting the budget. Capital Budget Summary The Capital Budget Summary consists of an overview of the District’s CIP, including how the Water Resources Master Plan (WRMP) is used to modify the CIP each year based on the latest set of assumptions and criteria. Also included are highlights of the major CIP projects that are completed, in construction, or in design. Additionally, this section contains a review of the CIP reserve funds and funding sources, a six-year listing of CIP project expenditures, project justification and impact on the Operating Budget, project schedules, and the capital purchases budget. CIP Projects This section contains the project sheet description and project sheets for each CIP project. These sheets are developed by the project manager and contain critical information for the management of these projects. The projects are divided into four categories: Capital Facility Projects, Replacement/Renewal Projects, Capital Purchase Projects, and Developer Reimbursement Projects. Appendix The last section consists of the Water Meter Capacity Fee Schedule, a Glossary of budget and financial terms, a List of Acronyms used in this budget book, and an Index. 1 At-A-Glance History The Otay Water District was formed in January 1956 and joined the San Diego County Water Authority (CWA) in September 1956 to acquire the right to purchase and distribute imported water throughout its service area. The District is also responsible for the collection, treatment, and disposal of wastewater from a portion of the northern region of the District. In 1980, the District started operation of the Ralph W. Chapman Water Recycling Facility (RWCWRF), and in June, 2007 a new source of recycled water from the City of San Diego was obtained, allowing the Otay Water District to supply 12 percent of total water demand with recycled water. Mission Statement To provide high value water and wastewater services to the customers of the Otay Water District, in a professional, effective, and efficient manner. Service Area The District's boundaries encompass an area of approximately 125 square miles in San Diego County, lying immediately east of the City of San Diego metropolitan area and running from the City of El Cajon south to the international border. Government The Otay Water District was formed in 1956 to serve as a public water and sewer agency, authorized as a California special district, under the provisions of the Municipal Water District Act of 1911. The District’s ordinances, policies, taxes, and rates for service are set by five Directors elected by voters in their respective geographic area. Organizational Structure The General Manager reports directly to the Board of Directors. The Assistant General Manager along with District management oversees day-to-day operations. The Assistant General Manager oversees the five departments of Administrative Services; Finance; Information Technology and Strategic Planning; Water Operations; and Engineering. These and other lines of reporting are shown on the organization chart on page 16. 2 General Information For Fiscal Year 2013, the District will have a staff of 148 full-time equivalent employees under the leadership of the General Manager. The District provides water service to approximately 53% of its expected ultimate deliveries with a population of more than 208,000 people. This percentage increases as the District's service area continues to grow to ultimate build-out. The District is projected to deliver approximately 28,925 acre-feet of potable water to 48,860 potable customer accounts and to ultimately deliver by 2035 56,600 acre-feet of potable water to serve 285,000 people or 69,000 accounts. The rate of growth, as projected by the San Diego Association of Governments (SANDAG) for the Chula Vista area of San Diego County, is approximately 1.7% per year over the next decade. Using historical data and considering current economic conditions, staff has moderated this projection to a growth rate of 0.6% for Fiscal Year 2013. Since 1956, the District has provided high quality water to a semi-arid region of the southeastern San Diego County. In 1971, the District constructed a small collection and treatment plant for sewer in the northern section of the District, and in 1980 the District opened the Ralph W. Chapman Water Recycling Facility (RWCWRF). For over 50 years, the available supply of water has helped transform the District service area from a mostly scrub and cactus-covered backcountry into a balance of diverse environments. Recycled water from the RWCWRF is used to irrigate golf courses, schools, public parks, roadway landscapes, and various other approved uses in eastern Chula Vista. The RWCWRF is capable of recycling wastewater at a rate of 1.3 million gallons per day (1,200 acre-feet per year). The District is also in a partnership with the City of San Diego to beneficially reuse an additional 2,900 acre-feet per year of recycled water for Fiscal Year 2013, and ultimately up to 6,720 acre-feet per year. This makes Otay Water District the largest retail provider of recycled water in the county. The District also owns and operates a wastewater collection system providing public sewer service to approximately 4,652 customer accounts within the Jamacha drainage basin. The sewer service area covers approximately 8,797 acres, which is about 11% of the District’s total service area. Residential customers comprise 97% of the sewer customer base. 3 Financial Awards The Government Finance Officers Association of the United States and Canada (GFOA) presented a Distinguished Budget Presentation Award to Otay Water District, California for its annual budget for the fiscal year beginning July 1, 2011. In order to receive this award, a governmental unit must publish a budget document that meets program criteria as a policy document, as an operations guide, as a financial plan, and as a communications device. This award is valid for a period of one year only. We believe our current budget continues to conform to program requirements, and we are submitting it to GFOA to determine its eligibility for another award. 4 Financial Awards The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Certificate of Award for Excellence in Operating Budget for Fiscal Year 2011-2012. The California Society of Municipal Finance Officers (CSMFO) presented Otay Water District the Certificate of Award for Excellence in Capital Budget for Fiscal Year 2011-2012. 5 Awards The Municipal Information Systems Association of California presented the 2010/2011 Award for Excellence Information Technology Practices to Otay Water District. The award recognizes outstanding practices in Information Technology that have met or surpassed local government standards. 6 Current Economic Conditions Currently, the District services the needs of a growing population by purchasing water from the San Diego County Water Authority (CWA). CWA purchases its water from the Metropolitan Water District of Southern California (MWD) and the Imperial Irrigation District (IID). Otay takes delivery of the water through several connections of large diameter pipelines owned and operated by CWA. The District currently receives treated water from CWA and the Helix Water District (HWD) by contract with CWA. In the Southern region, in addition to the treated water deliveries from CWA, the District has an emergency agreement with the City of San Diego in the case of a shutdown of the main treated water source. Through innovative agreements like this, benefits can be achieved by both parties by using excess capacity of another agency and diversifying local supply, thereby increasing reliability. For several decades, the District has collected and recycled wastewater generated within the Jamacha drainage basin and pumped the recycled water south to the Salt Creek basin where it is used for irrigation and other non-potable uses. However, the demand for recycled water out-paced the supply, requiring the District to supplement the limited supply of recycled water with potable water. Through the agreement with the City of San Diego, the District has discontinued supplementing its recycled demand with potable water. Once again, this decreases the demand on potable water and increases reliability of the District’s supply. The District’s sewer service area is growing at a slow but steady rate of approximately 0.2% each year. Most of this growth is from small development projects or homeowners converting their septic system to sewer because of environmental issues. The District’s water service area was one of the fastest growing regions in the nation. During the past decade, the population of the service area has nearly doubled. It is estimated that the District is currently serving approximately 208,500 residents. In just the past nine years, the District has added more than 6,484 new customer connections, with 2,326 occurring in Fiscal Year 2004. The phenomenal growth has slowed, as our local and national economy is experiencing a downturn. This slowdown appears to have leveled off as the District’s Public Services Division approved on average 40 permits per month, and sold 316 water meters in Fiscal Year 2011-2012. 2012 Landscape Contest Winner 7 The Future The District continues to use the challenges presented by growth to create new opportunities and new organizational efficiencies. By utilizing and continuing to refine its Strategic Business Plan, it has captured the Board of Director’s vision and united its staff in a common mission. The organization has achieved a number of significant accomplishments based on its successful adherence to its Strategic Business Plan. The District is not only poised to continue successfully providing an affordable, safe, and reliable water supply for the people of its service area, but is set to reap the rewards of greater efficiencies and economies of scale. Meter Sales This year, because of the economic uncertainty of the region, the District employed an Economist to verify the growth in the region. Using the economist’s report, the Engineering Department projected that over the next six years the District will sell another 3,980 meters. SANDAG, the regional planning agency, shows a slowing of the historic annual growth rate of 6.3% since 1980, to a projected future annual growth rate of 1.7% through 2030, for the City of Chula Vista. For the unincorporated areas of the region the historic annual growth rate has been only 1.3% since 1980, but is expected to increase to 1.7% through 2030. 8 Demographics The District boundaries shown in the chart below encompass an area of approximately 125.5 square miles in San Diego County, located immediately east of the City of San Diego metropolitan area and running from the City of El Cajon south to the international border. SANDAG creates and maintains a tremendous quantity of demographic, economic, land use, transportation and criminal justice information about the San Diego region. The demographic data include population characteristics like age, education, and employment. Because of the overlapping of the District’s service area with the cities of Chula Vista, La Mesa, El Cajon, and the unincorporated areas of Spring Valley and Jamul, the following demographic data is from the City of Chula Vista as it most closely represents the District. The population of Chula Vista has grown from 83,927 in 1980, to 135,136 in 1990, to 173,556 in 2000, and in 2010 the population reached 243,916. This represents an increase of 159,989 in the past 30 years or a 190.6% increase, which correlates to the District’s rapid growth for the same period. The racial make up of Chula Vista is 58% Hispanic, 20% White, 14% Asian, 4% Black, and the remaining 7% is all other groups. The median household income for Chula Vista was $66,955 in 2009, and 92% of Chula Vista’s housing units were occupied. 9 Organization Chart GENERAL MANAGER Assistant General Manager Administrative Services Finance Water Operations Engineering Human Resources Purchasing and Facilities Safety and Risk Administration Water Conservation Controller and Budgetary Services Treasury and Accounting Services Customer Service Payroll and Accounts Payable IT Applications IT Operations GIS Water System Operations Utility Maintenance/ Construction Collection/ Treatment/ Recycle Operations Planning Design Water Resources Public Services Construction Survey Environmental Citizens and Customers Information Technology and Strategic Planning BOARD OF DIRECTORS 10 CIP Budget Calendar Each year, the Engineering Department prepares budget instructions for distribution to the departments. These instructions give direction and deadlines for each phase of the CIP budgeting process. The CIP Budget Process is explained on pages 12 and 13. January 11, 2012 Budget workbooks and instructions for the Operating and Capital Budget are distributed to departments. January 11, 2012 to February 24, 2012 Departments begin CIP Budget Process which includes:  Review existing FY 2012 CIP projects.  Remove any CIPs that are complete or will not be budgeted in the CIP budget the next six years.  Estimate the total project-to-date expenditures through 6/30/12 for each CIP.  Adjust the annual amount for the remaining CIPs when appropriate and include justification for the changes to each year’s changes.  Develop CIP project cost and schedules, unless more specific information is available.  Submit new CIP projects for consideration. March 6, 2012 Engineering Department reviews all CIP budget requests with Assistant General Manager and adjusts, if necessary. March 12, 2012 Engineering reviews and prepares CIP budget and submits to Finance for review and to incorporate into rate model to determine proposed rates. March 23, 2012 CIP budget presented to the General Manager for review and comments. April 2, 2012 Review Assumptions and Rates April 12, 2012 General Manager performs preliminary review of budget. May 3, 2012 Final review of proposed budget and rates is done by the General Manager. May 15, 2012 Board of Directors adopts Fiscal Year 2012-2013 Operating and Capital Budget. 11 CIP Budget Process The District has integrated the Capital Improvement Program (CIP) Budget and the Operating Budget. Appropriate budget amounts are determined by using the historical data of operations, growth, developers' input, SANDAG projections, and the economic outlook. Additionally, these budgets are developed based on the District's Water Resources Master Plan and the Strategic Business Plan, both long-range planning tools. To assure reliable, high-quality service to the growing customer base, the District has committed to a number of long-range strategies that drive the budgeting process. The strategies and assumptions used to develop the District's integrated budget are:  An average projected long-term growth rate of 1.7%.  Pass-through rate increases for costs imposed on the District by the wholesale water providers.  Accurate projection of capital budget needs including replacement needs.  Reserve funding in accordance with the Reserve Policy to meet future growth demands.  Funding of the Strategic Plan initiatives categorized into the Balanced Scorecard perspectives.  Avoidance of rate spikes by leveling rate increases over a six-year period. The Engineering Department (Engineering) issues budget instructions for the CIP budget process. Each project manager receives a report of year-to-date project expenses and then estimates costs to the end of the fiscal year, plus future costs including inflation, to complete the project. Costs are adjusted for scope changes as well as construction cost increases. Engineering then compiles the CIP Budget and submits it to the Assistant General Managers and the General Manager for review prior to presentation to the Board of Directors. Once these budgets have been calculated, the Finance Department inputs the operating revenues and expenses, CIP expenses, reserve funding, and reserve levels into the District’s Rate Model. Water and Sewer Rates Strategic Plan MWD/CWA & Sewer Rates Year End Balances Operating Budget Input CIP Budget Input Assumptions Interest Rates Inflation Growth Sales Targets Debt Coverage Reserve Levels Rate Model Operating Budget CIP Budget 12 CIP Budget Process Inflators for cost and volume changes are input into the Rate Model and cost and rates are calculated for the current fiscal year plus five subsequent years. Using this comprehensive modeling tool, the District is able to smooth future rate increases, determine when debt should be issued, and maintain all of the reserve levels in accordance with its Reserve Policy. In the spring, the Strategic Plan is presented to the Board of Directors for adoption. This is followed by the Finance and the Engineering Departments presenting to the Board of Directors their recommendations at a special budget meeting in May of each year. The adoption of the Strategic Plan and budget on an annual basis gives the District its direction for the following fiscal year. During the year, each project manager receives monthly budget and cost reports on their assigned CIP projects. These reports are essential to monitor and control costs. As events occur or conditions change, modifications to or deviations from the original budget may be necessary. In the event the General Manager determines that an emergency exists which requires immediate action, he may transfer appropriations within the budget allocations or request that the Board of Directors increase the current budgeted funds. All CIP budget adjustments and requests are submitted to the Engineering Department. The budgets are reviewed for accuracy, categorized into the appropriate project types and funding sources, and then prioritized based on need and timing of projects. Projects are reviewed to see if any grant funding is available and if so, estimated amounts are included as a funding source to these projects. Engineering submits the consolidated CIP list to the Assistant General Manager and General Manager for review and approval. After any necessary adjustments, the CIP budget is submitted to the Board of Directors for approval each fiscal year along with the Operating Budget. The District is accounted for and budgeted as an enterprise fund and conforms to the guidelines of generally accepted accounting principles (GAAP). The Budget Report is intended as a financial guide and may be modified by the Board of Directors during the 2013 fiscal year. 94 4 -I R R e c y c l e d W a t e r P u m p S t a t i o n 13 14 15 Capital Improvement Program The District provides water service to a population of approximately 208,000 which is expected to ultimately increase to 285,000 by the year 2035. This growth as well as the maintenance of existing assets requires long term capital planning. The process is dynamic, due to the evolving needs of the community, the water supply issues, and changing regulations. As such, capital planning is part of the District’s overall strategic planning. The capital planning process involves identifying current needs, future needs, and prioritizing them based on certain operating assumptions. The primary objective of this planning effort is to support an orderly and efficient program of expansion, new water supply, replacement, and betterment, while maintaining a stable long-range financial plan. To accommodate this growth requires that the District invest $475 million in capital assets through ultimate build-out. The Fiscal Year 2013 Capital Budget is $18 million and the six- year Capital Improvement Program (CIP) totals $116.4 million. A separate CIP Budget Notebook contains the descriptions, justifications, expenditures, and funding for all the identified projects to ultimate build-out. Assumptions and Criteria The CIP is developed based on the District's Water Resources Master Plan, incorporating historical data, growth, developers' input, SANDAG projections, and long-term economic outlook. The Water Resources Master Plan was built using several major assumptions and design criteria as follows: 1. Utilizing historical water demands for each land use type in the District to calculate future demands. 2. Using maximum day peaking factors that vary with demand level. 3. Utilizing land use as planned by the City of Chula Vista. 4. Providing ten days of emergency water supply through a maximum of five days in covered reservoirs and a minimum of five days from interconnections with adjacent agencies. 5. Inclusion of emergency operational storage to meet the five-day covered storage requirement into the ten-day outage supply requirement. CIP Justification and Impact on Operating Budget The justification for each project is determined by whether it is required due to growth (Expansion), new water sources (New Supply), improvements or upgrades (Betterment), or to replace an existing asset (Replacement). As these projects are completed and placed into service, there may be an impact on the Operating Budget by increasing costs in the areas of maintenance, energy, or chemicals as shown on the justification and impact pages in this section. 16 Capital Improvement Program Capital Purchases and Facilities All capital expenditures are in the CIP. This includes capital facilities and capital purchases. Capital purchases are non-recurring operating expenditures for assets that cost more than $10,000 each and have an estimated useful life of two years or more. The Capital Purchase Projects include Vehicle, Office Equipment, Furniture, and Field Equipment purchases. The details of these purchases can be found on page185. Capital Facility Projects are items that exceed $10,000 or $20,000 for infrastructure related items (as defined under Capital Equipment on page 251 of the Glossary) and have a useful life of at least two years. The CIP projects are identified and are prioritized based on the following criteria: 1. Safety, restoration of service, immediate obligation, Board directed, or critical system need. 2. System upgrades or requirements to maintain system reliability in the next few fiscal years. 3. Need to meet the future growth of the system. 4. Project requirement may be reduced in capacity or may have low probability of need in the future. The following are the four categories of CIP projects: New Water Supply Facilities required to support new sources of water are funded from new supply fees or user rates. Expansion Facilities required to support new or future users are funded from capacity fees or user rates. Betterment Facilities required because of inadequate capacity or new requirements that benefit existing users are funded from availability, betterment fees, or rates. Replacement Facilities required to renew or replace existing facilities that have deteriorated or have exceeded their useful life are funded from user rates. 17 Major CIP Projects Capital Improvement Projects The 2013 Fiscal Year CIP Budget contains 70 projects. The cost of the work planned for Fiscal Year 2013 is $18 million. Of the 70 projects planned for Fiscal Year 2013, only three are designated as reimbursable projects with estimated costs totaling $63,000. These projects are built by developers and reimbursed by the District. The following shows how the $18 million of projects are broken down into four categories: 1. Capital facilities $ 6.9 million 2. Replacement or renewal projects $ 9.9 million 3. Capital purchase projects $ 1.1 million 4. Developer reimbursement projects $ .1 million The Six-Year CIP and Fiscal Year 2013 Capital Budgets are consistent with the District's Water Resources Master Plan, current capacity fees, and the District's strategic financial objectives. 18 CIP Projects in Construction Phase I of 944-1R Recycled Water Pump Station Upgrades and System Enhancements (R2091)  Phase I of 944-1R Recycled Water Pump Station Improvements  Installation of New Pump  New Instrumentation  New Suction Header Piping  Three new Pressure Reducing Stations  $1.88M Budget  Start: June 2011  Estimated Completion: September 2012 New Suction Header and Grating at 944-1R Pump Station New Pressure Reducing Station on Eastlake Parkway 19 CIP Projects in Construction RWCRWF Upgrades and Modifications (R2096) New Air Scour Facility for the Filters Refurbished Aeration Basin under Operation RWCRWF Upgrades and Modifications (R2096)  RWCRWF Upgrades  New Aeration System, Blower System, and Electrical Instrumentation  $4.95M Budget  Start: July 2011  Estimated Completion: August 2012 20 CIP Projects in Construction La Presa System Improvements (P2370) Completed PRV Station at La Presa Site Demolition of the Dorchester Reservoir and PRV  La Presa System Improvements  Demolition of 850-1 and 657-1 Pump Stations and Forebay Reservoir  Multiple Interconnections Throughout Spring Valley  Demolition of Dorchester Reservoir and Pressure Reducing Station  $1.24M Budget  Start: November 2011  Estimated Completion: August 2012 21 CIP Projects in Construction Sewer Main Replacement Projects (S2019, S2020, S2022, & S2026)  Calavo Garden Sewer Rehabilitation  Replacement of 4,500 Linear Feet of Sewer  Manhole Rehabilitation/Replacement  Capacity Upgrades  New Flow Control and Diversion Vault for Calavo Lift Station  $3.10M Budget  Start: February 2012  Estimated Completion: May 2013 Excavating for Sewer Replacement on Calavo Drive Installing New 15-Inch Sewer on Avocado Blvd. 22 (Thousand $000s)FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total Beginning Balance 48,044$ 40,377$ 37,199$ 39,454$ 40,550$ 41,369$ Capacity Fees 3,861$ 6,087$ 8,577$ 10,114$ 11,711$ 12,624$ 52,976$ Debt financing - - - 4,700 800 - 5,500 Grants 400 350 100 100 100 500 1,550 Interest 269 259 359 457 787 1,089 3,220 Betterment Charges 705 721 735 750 762 774 4,448 Temporary Meters 545 545 546 549 552 553 3,291 Availability (Betterment Portion)519 530 540 550 560 569 3,268 New Supply Fee 399 644 912 1,052 1,214 1,305 5,527 COPS 2010B Reimbursement 5,380 7,587 8,703 830 830 830 24,160 Transfer from General Fund 7,899 8,907 11,182 12,113 11,720 10,925 62,746 Interfund Transfers 111 99 86 18 30 42 385 Total Sources 20,088 25,729 31,740 31,233 29,066 29,211 167,069 CIP Projects 17,994 19,228 19,807 20,224 18,455 20,699 116,407 Betterment Fees for Maintenance 689 695 704 714 725 737 4,264 Debt Service 7,891 7,962 7,944 8,159 8,016 7,971 47,942 Developer Services 1,181 1,022 1,030 1,040 1,051 1,062 6,385 Transfer to State Loan Reserve - - - - - - - Interfund Transfers - - - - - - - Total Uses 27,755 28,907 29,485 30,137 28,247 30,469 174,998 Net Sources (Uses)(7,667)$ (3,178)$ 2,255$ 1,096$ 819$ (1,258)$ (7,929)$ Ending Balance 40,377$ 37,199$ 39,454$ 40,550$ 41,369$ 40,111$ CIP Reserve Funds The CIP Reserve Funds presentation, shown on the following pages, is designed to provide an understanding of how the funding of CIPs is expected to financially influence the District over the next six years. The financial impacts are based on CIPs and their funding sources, including fund transfers in accordance with the District’s Reserve Policy, and planned debt issuances. This data is captured in the District’s Rate Model on an annual basis in order to make these projections. $0 $10,000 $20,000 $30,000 $40,000 $50,000 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Th o u s a n d s Reserve Fund Balances New Supply Expansion Replacement Betterment $40,377 $37,199 $39,453 $40,550 $41,369 $40,111 23 CIP Funding Source (Thousands $000s)FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 TOTAL Expansion 3,988$ 2,794$ 4,205$ 1,805$ 400$ 12,171$ 25,363$ Betterment 4,129 4,706 7,418 9,000 6,010 652 31,915 Replacement 9,273 9,808 4,264 5,499 8,605 7,560 45,009 New Supply 604 1,920 3,920 3,920 3,440 316 14,120 TOTAL 17,994$ 19,228$ 19,807$ 20,224$ 18,455$ 20,699$ 116,407$ CIP Category (Thousands $000s)FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 TOTAL Capital Facility Projects 6,938$ 7,902$ 9,992$ 10,317$ 13,666$ 16,375$ 65,190$ Replacement/Renewal Projects 9,874 9,640 4,310 6,165 3,237 1,162 34,388 Capital Purchase Projects 1,119 1,062 844 774 575 551 4,925 Developer Reimbursement Projects 63 595 300 300 300 290 1,848 Subtotal 17,994 19,199 15,446 17,556 17,778 18,378 106,351 FY 2014 Through FY 2018 Projects - 29 4,361 2,668 677 2,321 10,056 TOTAL 17,994$ 19,228$ 19,807$ 20,224$ 18,455$ 20,699$ 116,407$ CIP Funding Source and Category $0 $10,000 $20,000 $30,000 $40,000 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Six-Year CIP by Funding Source Betterment Replacement Expansion New Supply $0 $10,000 $20,000 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Six-Year CIP by Category Capital Facility Projects Replacement/Renewal Projects Capital Purchase Projects Developer Reimbursement Projects 24 CIP No Description FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total CAPITAL FACILITY PROJECTS P2009 PL - 36-Inch, SDCWA Otay FCF No. 14 to Regulatory Site $900 $900 P2083 PS - 870-2 Pump Station Replacement (28,000 GPM) 50 1 1 750 5,250 5,948 12,000 P2267 36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations 5 230 200 435 P2370 La Presa System Improvements 195 195 P2434 Rancho Del Rey Groundwater Well Development 500 3,100 1,500 5,100 P2451 Otay Mesa Desalination Conveyance and Disinfection System 1,000 1,500 8,000 9,500 8,300 500 28,800 P2466 Regional Training Facility 14 14 28 P2486 Asset Management Plan Condition Assessment and Data Acquisition 200 50 60 60 60 59 489 P2502 803-1 Pump Station Modifications 50 50 P2503 850-2 Pump Station Modifications 50 50 P2511 North District - South District Interconnection System 1,000 1,000 2,000 P2514 PL - 30-Inch, 980 Zone, Hunte Parkway - Proctor Valley/Use Area 1,150 1,150 P2527 1200-1 Pump Station Facility Cover 30 30 P2528 30-Inch Potable Water Pipeline Manifold at 624 Reservoirs 300 1,000 1,300 P2536 HMBP-Emergency Stand-By Generator Secondary Containment 60 60 P2537 Operations Yard Property Acquisition Improvements 250 50 300 R2048 RecPL - Otay Mesa Distribution Pipelines and Conversions 15 1 1 1 50 1,752 1,820 R2058 RecPL - 16-Inch, 860 Zone, Airway Road - Otay Mesa/Alta 5 1 1 1 1 2,141 2,150 R2077 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway 950 950 224 2,124 R2087 RecPL - 24-Inch, 927 Zone, Wueste Road - Olympic/Otay WTP 5 5 5 5 5 5,975 6,000 R2091 RecPS - 927-1 Pump Station Upgrade (10,000 GPM) and System Enhancements 65 65 R2107 RWCWRF Screening Compactor and Chlorine Injectors Enclosure 115 115 S2039 Hidden Mountain Lift Station Enclosure 29 29 23 Total Capital Facility Projects 6,938 7,902 9,992 10,317 13,666 16,375 65,190 REPLACEMENT/RENEWAL PROJECTS P2366 APCD Engine Replacements and Retrofits 120 265 200 175 162 162 1,084 P2382 Safety and Security Improvements 300 300 300 300 300 1,500 P2440 I-905 Utility Relocations 5 5 10 P2453 SR-11 Utility Relocations 200 125 125 1,000 700 2,150 P2458 AMR Manual Meter Replacement 1,400 500 1,900 P2477 Res - 624-1 Reservoir Cover Replacement 690 690 P2484 Large Water Meter Testing and Replacement Program 150 100 250 P2485 SCADA Communication System and Software Replacement 629 491 1,120 P2491 850-3 Reservoir Exterior Coating 150 150 P2493 624-2 Reservoir Interior/Exterior Coating 8 1,450 390 1,848 P2494 Multiple Species Conservation Plan 93 30 123 P2495 San Miguel Habitat Management/Mitigation Area 120 200 200 200 200 200 1,120 P2496 Otay Lakes Road Utility Relocations 50 50 P2504 Regulatory Site Access Road and Pipeline Relocation 50 225 175 450 P2507 East Palomar Street Utility Relocation 150 330 235 715 P2508 Pipeline Cathodic Protection Replacement Program 80 50 130 P2513 East Orange Avenue Bridge Crossing 840 150 990 P2515 870-1 Reservoir Paving 100 425 525 P2518 803-3 Reservoir Interior/Exterior Coating 700 50 750 P2519 832-2 Reservoir Interior/Exterior Coating 725 50 775 P2520 Motorola Mobile Radio Upgrade 50 50 P2521 Large Meter Vault Upgrade Program 150 150 100 60 460 P2535 458-2 Reservoir Interior Coating 5 275 20 300 R2096 RWCWRF - Upgrades and Modifications 60 60 R2099 Recycled System Air and Vacuum Value Retrofit 233 233 466 S2012 San Diego County Sanitation District Outfall and RSD Outfall Replacement 100 450 450 450 450 800 2,700 S2019 Avocado Boulevard 8-Inch Sewer Main Improvement 1,375 1,375 S2020 Calavo Drive 8-Inch Sewer Main Replacement 210 210 S2022 Hidden Mesa Drive 8-Inch Sewer Main Rehabilitation 50 50 S2023 Calavo Drive Sewer Main Utility Relocation 60 60 S2024 Campo Road Sewer Main Replacement 50 275 1,250 3,120 800 5,495 S2026 Challenge Boulevard 8-Inch Sewer Main Replacement 155 155 S2027 Rancho San Diego Pump Station Rehabilitation 300 2,490 2,790 S2028 Explorer Way 8-Inch Sewer Main Replacement 1 1 30 60 25 117 CIP Projects ($1,000s) The 2013 Fiscal Year CIP Budget contains 70 projects. The costs for the work planned for Fiscal Year 2013 is $18 million. Of the 70 projects planned for Fiscal Year 2013, three are designated as reimbursable projects with an estimated cost of $63 thousand. These projects are built by a developer and reimbursed by the District. 25 CIP Projects ($1,000s) CIP No Description FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total REPLACEMENT/RENEWAL PROJECTS, continued S2033 Sewer System Various Locations Rehabilitation 200 420 150 770 S2040 Calavo Sewer Basin Improvements 275 525 450 1,250 S2041 Rancho San Diego Sewer Basin Improvements 40 75 235 800 600 1,750 38 Total Renewal & Replacements 9,874 9,640 4,310 6,165 3,237 1,162 34,388 CAPITAL PURCHASE PROJECTS P2282 Vehicle Capital Purchases 49 392 400 425 450 476 2,192 P2286 Field Equipment Capital Purchases 115 90 75 74 75 75 504 P2443 Wireless Communications System 200 130 330 P2461 Records Management System Upgrade 2 90 90 P2469 Information Technology Network and Hardware 120 250 169 75 614 P2470 Financial System Enhancements 220 200 200 200 50 870 S2042 Sewer Vehicle Capital Purchases 325 325 7 Total Capital Purchase 1,119 1,062 844 774 575 551 4,925 DEVELOPER REIMBURSEMENT PROJECTS P2325 PL - 10-inch to 12-inch Oversize, 1296 Zone, PB Road - Rolling Hills Hydro PS/PB Bndy 49 49 R2083 RecPL - 20-Inch, 680 Zone, Heritage Road - Village 2/Olympic 4 395 399 R2094 Potable Irrigation Meters to Recycled Water Conversions 10 200 300 300 300 290 1,400 3 Total Reimbursement Projects 63 595 300 300 300 290 1,848 71 Total- FY2013 Projects 17,994 19,199 15,446 17,556 17,778 18,378 106,351 17 Total- FY2014 Through FY 2018 Projects - 29 4,361 2,668 677 2,321 10,056 Grand Totals $ 17,994 $ 19,228 $ 19,807 $ 20,224 $ 18,455 $ 20,699 $ 116,407 26 CIP Justification and Impact on Operating Budget CIP #Description Cost Cat. (2) Funding Source (3) FY 13 FY 14 FY 15 FY 16 FY 17 FY 18 TOTAL (4) P2009 PL - 36-Inch, SDCWA Otay FCF No. 14 to Regulatory Site M E/B $9,600 $9,900 $10,200 $10,500 $10,800 $11,100 $62,100 P2325 PL - 10-inch to 12-inch Oversize, 1296 Zone, PB Road - Rolling Hills Hydro PS/PB Bndy E E $0 $2,300 $2,400 $2,500 $2,600 $0 $9,800 P2370 La Presa System Improvements M B ($1,900)($2,000)($2,100)($2,200)($2,300)$0 ($10,500) P2434 Rancho Del Rey Groundwater Well Development M/E/C N/B $0 $604,000 $604,000 $604,000 $604,000 $604,000 $3,020,000 P2443 Wireless Communications System M R/E $0 $0 $18,000 $18,500 $19,100 $0 $55,600 P2451 Otay Mesa Desalination Conveyance and Disinfection System E/C N/B $0 $0 $0 $10,000 $28,500 $38,500 P2458 AMR Manual Meter Replacement M R $0 $0 $0 ($226,400)($233,200)($240,000)($699,600) P2502 803-1 Pump Station Modifications E B $0 ($40,950)($81,900)($84,400)($86,900)($89,500)($383,650) P2503 850-2 Pump Station Modifications E B $0 ($25,200)($50,400)($51,900)($53,500)($55,100)($236,100) P2514 PL - 30-Inch, 980 Zone, Hunte Parkway - Proctor Valley/Use Area M E $0 $700 $700 $700 $700 $0 $2,800 R2082 RecPL - 24-Inch, 680 Zone, Olympic Parkway - Village 2/Heritage M E $0 $0 $0 $1,200 $1,200 $0 $2,400 R2083 RecPL - 20-Inch, 680 Zone, Heritage Road - Village 2/Olympic M E $0 $0 $700 $700 $700 $0 $2,100 R2084 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media M E $0 $0 $0 $1,900 $0 $1,900 R2085 RecPL - 20-Inch, 680 Zone, La Media - State/Olympic M E $0 $0 $0 $1,300 $1,300 $0 $2,600 $7,700 $548,750 $501,600 $274,500 $276,400 $259,000 $1,867,950 FY 13 FY 14 FY 15 FY 16 FY 17 FY 18 TOTAL $7,700 $338,600 $357,500 $134,300 $130,200 $101,100 $1,069,400 $0 $196,150 $130,100 $126,200 $131,200 $140,400 $724,050 $0 $14,000 $14,000 $14,000 $15,000 $17,500 $74,500 $7,700 $548,750 $501,600 $274,500 $276,400 $259,000 $1,867,950 (1)Projected Incremental Operating Expenditures (operating cost) or O&M includes labor, benefits, materials, and overhead. (2) (3) (4) Note:See pages 182-183 for complete description of CIP projects. The following schedule shows anticipated operating costs associated with each project in the CIP. Below is a summary of each category of new costs that will be impacted. No additional revenues are associated with the individual projects, as revenues are linked more directly to growth in water sales and capacity fee revenues. Cost Category Maintenance (M) Energy (E) Chemical (C) Total Operating Budget Cost Impact Negative cost reflect savings gained from operational efficiencies or the retirement of a facility. Total Operating Budget Cost Impact Projected Incremental Operating Expenditures (1) E - Expansion B - Betterment R - Replacement N - New Supply Cost Category - Indicates maintenance cost, energy cost, or chemical cost, based on the project type and Engineer's estimates. O&M cost for pipes: Total annual operating cost divided by the number of feet of pipe in the system = O&M cost to maintain a foot of pipe. This rate is then multiplied by the number of feet in new pipeline, and is increased annually for inflation. O&M cost for a pump station: Total annual operating cost divided by the number of million of gallons a day (MGD) capacity in the system = O&M cost per MGD. This rate is then multiplied by the MGD capacity of the new pump station. Similarly, power cost per MGD for transmission is calculated and applied to the MGD of the new pump station. Chemical expenses are incurred for pumping at the well sites. All estimated costs are increased annually for inflation. O&M cost for a reservoir: Total annual operating cost divided by the number of million gallons (MG) of storage capacity in the system. This rate per MG is then multiplied by the MG capacity of the new reservoir. Reservoirs require chemical treatment; therefore, the chemical cost per MG is estimated and applied to the future operating cost. Both O&M and chemical costs are increased annually for inflation. Each of the capital purchases and other types of assets has its own unique O&M cost. Funding Source - Some projects have multiple funding sources as indicated by a slash (/): 27 Task Name Project Name Start Finish P2009 PL - 36-Inch, SDCWA Otay FCF No. 14 to Regulatory Site Tue 4/24/12 Tue 4/24/12 Construction Wed 7/1/09 Wed 1/1/14 P2083 PS - 870-2 Pump Station Replacement (28,000 GPM) Tue 4/24/12 Tue 4/24/12 Planning Tue 4/24/12 Sat 6/1/13 Design Mon 7/1/13 Mon 11/30/15 Construction Tue 4/24/12 Mon 12/31/18 P2104 PL - 12-Inch, 711 Zone, La Media Road - Birch/Rock Mountain Tue 4/24/12 Tue 4/24/12 Planning Thu 7/1/04 Fri 5/31/13 Design Mon 7/1/13 Fri 5/30/14 Construction Tue 7/1/14 Fri 5/29/15 P2107 PL - 12-Inch, 711 Zone, Rock Mountain Road - La Media/SR 125 Tue 4/24/12 Tue 4/24/12 Planning Thu 7/1/04 Fri 5/31/13 Design Mon 7/1/13 Fri 5/30/14 Construction Tue 7/1/14 Fri 5/29/15 P2190 PL - 10-Inch, 1485 Zone, Jamul Highlands Tue 4/24/12 Tue 4/24/12 Planning Fri 7/1/05 Thu 5/31/07 Design Mon 7/2/07 Tue 5/31/11 Construction Mon 7/11/11 Fri 5/31/13 P2267 36-Inch Main Pumpouts and Air/Vacuum Ventilation Tue 4/24/12 Tue 4/24/12 Construction Tue 7/1/97 Fri 5/29/15 P2282 Vehicle Capital Purchases Tue 4/24/12 Tue 4/24/12 Planning Fri 12/1/00 Thu 5/31/18 P2285 Office Equipment and Furniture Capital Purchases Tue 4/24/12 Tue 4/24/12 Planning Fri 12/1/00 Wed 5/31/17 P2286 Field Equipment Capital Purchases Tue 4/24/12 Tue 4/24/12 Planning Fri 12/1/00 Thu 5/31/18 P2325 PL - 10" to 12" Oversize, 1296 Zone, PB Road - Rolling Hills Tue 4/24/12 Tue 4/24/12 Planning Thu 7/1/04 Fri 5/31/13 Design Mon 9/2/13 Fri 11/29/13 Construction Wed 1/1/14 Fri 5/30/14 P2366 APCD Engine Replacements and Retrofits Tue 4/24/12 Tue 4/24/12 Construction Thu 7/1/10 Thu 5/31/18 P2370 La Presa System Improvements Tue 4/24/12 Tue 4/24/12 Construction Mon 8/1/11 Fri 6/29/12 P2382 Safety and Security Improvements Tue 4/24/12 Tue 4/24/12 Design Mon 9/1/03 Mon 5/31/10 Construction Mon 8/2/04 Wed 5/31/17 P2403 PL - 12-Inch, 624 Zone, Heritage Road - Olympic/Otay Valley Tue 4/24/12 Tue 4/24/12 Design Mon 7/3/06 Wed 5/31/17 Construction Mon 7/3/17 Thu 5/31/18 P2434 Rancho Del Rey Groundwater Well Development Tue 4/24/12 Tue 4/24/12 Design Mon 1/3/11 Fri 6/29/12 Construction Wed 8/1/12 Fri 7/31/15 P2440 I-905 Utility Relocations Tue 4/24/12 Tue 4/24/12 Construction Mon 10/2/06 Fri 11/29/13 P2443 Wireless Communications System Tue 4/24/12 Tue 4/24/12 Planning Fri 7/1/05 Thu 5/31/18 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2013 2014 2015 2016 2017 2018 Otay Water District FY 2013 - FY 2018 CIP Project Schedule 28 Task Name Project Name Start Finish P2451 Otay Mesa Desalination Conveyance and Disinfection Tue 4/24/12 Tue 4/24/12 Planning Mon 7/3/06 Thu 2/28/13 Design Fri 3/1/13 Fri 8/29/14 Construction Wed 10/1/14 Fri 9/30/16 P2453 SR-11 Utility Relocations Tue 4/24/12 Tue 4/24/12 Planning Mon 7/3/06 Mon 5/31/10 Design Wed 7/1/09 Thu 9/30/10 Construction Mon 11/1/10 Fri 5/30/14 P2458 AMR Manual Meter Replacement Tue 4/24/12 Tue 4/24/12 Construction Mon 7/3/06 Fri 5/30/14 P2461 Records Management System Upgrade 2 Tue 4/24/12 Tue 4/24/12 Planning Mon 7/2/07 Thu 5/31/18 P2466 Regional Training Facility Tue 4/24/12 Tue 4/24/12 Planning Tue 8/1/06 Fri 6/28/13 P2469 Information Technology Network and Hardware Tue 4/24/12 Tue 4/24/12 Planning Tue 7/1/08 Wed 6/29/16 P2470 Application Systems Development a Tue 4/24/12 Tue 4/24/12 Planning Tue 4/24/12 Tue 5/31/16 P2477 Res - 624-1 Reservoir Cover Replacement Tue 4/24/12 Tue 4/24/12 Planning Tue 7/1/08 Tue 1/31/12 Design Wed 2/1/12 Fri 9/28/12 Construction Mon 10/1/12 Thu 1/31/13 P2484 Large Water Meter Testing and Replacement Program Tue 4/24/12 Tue 4/24/12 Construction Wed 7/1/09 Fri 5/30/14 P2485 SCADA Communication System and Software Replacement Tue 4/24/12 Tue 4/24/12 Construction Wed 7/1/09 Fri 5/30/14 P2486 Asset Management Plan Condition Assessment and Data Acquisition Tue 4/24/12 Tue 4/24/12 Planning Wed 7/1/09 Thu 5/31/18 P2491 850-3 Reservoir Exterior Coating Tue 4/24/12 Tue 4/24/12 Construction Thu 12/1/11 Fri 5/31/13 P2493 624-2 Reservoir Interior/Exterior Coating Tue 4/24/12 Tue 4/24/12 Design Wed 9/1/10 Mon 12/30/13 Construction Wed 1/1/14 Thu 7/31/14 P2494 Multiple Species Conservation Plan Tue 4/24/12 Tue 4/24/12 Planning Wed 7/1/09 Fri 6/28/13 P2495 San Miguel Habitat Management/Mitigation Area Tue 4/24/12 Tue 4/24/12 Planning Wed 7/1/09 Fri 6/29/18 P2496 Otay Lakes Road Utility Relocations Tue 4/24/12 Tue 4/24/12 Construction Fri 1/1/10 Mon 12/30/13 P2502 803-1 Pump Station Modifications Tue 4/24/12 Tue 4/24/12 Construction Mon 5/2/11 Fri 11/30/12 P2503 850-2 Pump Station Modifications Tue 4/24/12 Tue 4/24/12 Construction Mon 5/2/11 Fri 11/30/12 P2504 Regulatory Site Access Road and Pipeline Relocation Tue 4/24/12 Tue 4/24/12 Design Fri 10/1/10 Fri 11/30/12 Construction Tue 1/1/13 Fri 8/29/14 P2507 East Palomar Street Utility Relocatio Tue 4/24/12 Tue 4/24/12 Construction Mon 1/2/12 Fri 5/30/14 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2013 2014 2015 2016 2017 2018 Otay Water District FY 2013 - FY 2018 CIP Project Schedule 29 Task Name Project Name Start Finish P2508 Pipeline Cathodic Protection Replacement Program Tue 4/24/12 Tue 4/24/12 Design Fri 10/1/10 Fri 4/27/12 Construction Tue 5/1/12 Mon 12/30/13 P2511 North District - South District Interconnection System Tue 4/24/12 Tue 4/24/12 Planning Thu 7/1/10 Fri 12/28/12 Design Mon 4/2/12 Fri 7/31/15 Construction Mon 7/2/18 Wed 7/1/20 P2513 East Orange Avenue Bridge Crossin Tue 4/24/12 Tue 4/24/12 Planning Fri 7/1/11 Fri 5/31/13 Design Mon 7/1/13 Fri 11/29/13 Construction Wed 1/1/14 Tue 5/31/16 P2514 PL - 30-Inch, 980 Zone, Hunte Parkway - Proctor Valley/Use Area Tue 4/24/12 Tue 4/24/12 Design Mon 1/2/12 Fri 11/30/12 Construction Tue 1/1/13 Fri 8/30/13 P2515 870-1 Reservoir Paving Tue 4/24/12 Tue 4/24/12 Planning Fri 7/1/11 Wed 11/30/11 Design Mon 1/2/12 Fri 6/28/13 Construction Mon 7/1/13 Mon 12/30/13 P2518 803-3 Reservoir Interior/Exterior Coating Tue 4/24/12 Tue 4/24/12 Planning Fri 7/1/11 Fri 8/31/12 Design Mon 10/1/12 Fri 11/29/13 Construction Tue 1/1/13 Fri 8/30/13 P2519 832-2 Reservoir Interior/Exterior Coating Tue 4/24/12 Tue 4/24/12 Planning Fri 7/1/11 Fri 8/31/12 Design Mon 10/1/12 Fri 11/29/13 Construction Tue 1/1/13 Fri 8/30/13 P2520 Motorola Mobile Radio Upgrade Tue 4/24/12 Tue 4/24/12 Construction Mon 8/1/11 Fri 9/28/12 P2521 Large Meter Vault Upgrade Program Tue 4/24/12 Tue 4/24/12 Construction Mon 8/1/11 Mon 11/30/15 P2527 1200-1 Pump Station Facility Cover Tue 4/24/12 Tue 4/24/12 Construction Mon 7/1/13 Fri 5/30/14 P2528 30-Inch Potable Water Pipeline Manifold at 624 Reservoirs Tue 4/24/12 Tue 4/24/12 Planning Mon 7/1/13 Mon 6/30/14 Design Tue 7/1/14 Tue 6/30/15 Construction Mon 7/2/18 Wed 7/1/20 P2529 711-2 Reservoir Interior & Exterior Coating Tue 4/24/12 Tue 4/24/12 Planning Mon 6/1/15 Fri 8/28/15 Design Tue 9/1/15 Wed 12/30/15 Construction Fri 1/1/16 Fri 7/29/16 P2530 711-1 Reservoir Interior & Exterior Coating Tue 4/24/12 Tue 4/24/12 Planning Mon 6/1/15 Fri 8/28/15 Design Tue 9/1/15 Wed 12/30/15 Construction Fri 1/1/16 Fri 7/29/16 P2531 944-1 Reservoir Interior & Exterior Coating Tue 4/24/12 Tue 4/24/12 Planning Mon 6/2/14 Fri 8/29/14 Design Mon 9/1/14 Tue 12/30/14 Construction Thu 1/1/15 Fri 7/31/15 P2532 944-2 Reservoir Interior & Exterior Coating Tue 4/24/12 Tue 4/24/12 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2013 2014 2015 2016 2017 2018 Otay Water District FY 2013 - FY 2018 CIP Project Schedule 30 Task Name Project Name Start Finish Planning Mon 6/2/14 Fri 8/29/14 Design Mon 9/1/14 Tue 12/30/14 Construction Wed 1/1/14 Thu 7/31/14 P2533 1200-1 Reservoir Interior & Exterior Coating Tue 4/24/12 Tue 4/24/12 Planning Wed 6/1/16 Thu 9/29/16 Design Mon 10/3/16 Fri 12/30/16 Construction Mon 1/2/17 Wed 8/30/17 P2534 978-1 Reservoir Interior & Exterior Coating Tue 4/24/12 Tue 4/24/12 Planning Thu 6/2/16 Thu 9/29/16 Design Mon 10/3/16 Fri 12/30/16 Construction Mon 1/2/17 Mon 7/31/17 P2535 458-2 Reservoir Interior Coating Tue 4/24/12 Tue 4/24/12 Planning Mon 6/3/13 Fri 9/27/13 Design Tue 10/1/13 Tue 12/30/14 Construction Wed 1/1/14 Fri 5/30/14 P2536 HMBP-Emergency Stand-By Generator Secondary Containment Tue 4/24/12 Tue 4/24/12 Construction Mon 7/2/12 Fri 5/31/13 P2537 Operations Yard Property Acquisition Improvements Tue 4/24/12 Tue 4/24/12 Planning Mon 11/3/08 Fri 9/28/12 Design Thu 11/1/12 Mon 12/31/12 Construction Fri 2/1/13 Thu 2/28/13 R2028 RecPL - 8-Inch, 680 Zone, Heritage Road - Santa Victoria/Otay Valley Tue 4/24/12 Tue 4/24/12 Design Mon 7/3/06 Wed 5/31/17 Construction Mon 7/3/17 Thu 5/31/18 R2042 RecPL - 8-Inch, 927 Zone, Rock Mountain Road - SR-125/EastLake Tue 4/24/12 Tue 4/24/12 Design Fri 9/1/06 Wed 5/31/17 Construction Mon 7/3/17 Thu 5/31/18 R2047 RecPL - 12-Inch, 680 Zone, La Media Road - Birch/Rock Mountain Tue 4/24/12 Tue 4/24/12 Design Fri 9/1/06 Wed 5/31/17 Construction Mon 7/3/17 Thu 5/31/18 R2048 RecPL - Otay Mesa Distribution Pipelines and Conversions Tue 4/24/12 Tue 4/24/12 Construction Wed 7/1/15 Fri 6/29/18 R2058 RecPL - 16-Inch, 860 Zone, Airway Road - Otay Mesa/Alta Tue 4/24/12 Tue 4/24/12 Construction Fri 7/1/11 Wed 5/31/17 R2077 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway Tue 4/24/12 Tue 4/24/12 Construction Fri 7/1/11 Fri 5/29/15 R2082 RecPL - 24-Inch, 680 Zone, Olympic Parkway - Village Tue 4/24/12 Tue 4/24/12 Planning Thu 7/1/04 Thu 5/31/12 Design Mon 7/2/12 Fri 5/29/15 Construction Wed 7/1/15 Tue 5/31/16 R2083 RecPL - 20-Inch, 680 Zone, Heritage Road - Village 2/Olympic Tue 4/24/12 Tue 4/24/12 Construction Mon 7/2/12 Fri 5/30/14 R2084 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media Tue 4/24/12 Tue 4/24/12 Planning Thu 7/1/04 Fri 5/31/13 Design Mon 7/2/12 Mon 11/30/15 Construction Wed 7/1/15 Tue 5/31/16 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2013 2014 2015 2016 2017 2018 Otay Water District FY 2013 - FY 2018 CIP Project Schedule 31 Task Name Project Name Start Finish R2085 RecPL - 20-Inch, 680 Zone, La Media - State/Olympic Tue 4/24/12 Tue 4/24/12 Planning Thu 7/1/04 Fri 5/31/13 Design Mon 7/1/13 Fri 5/30/14 Construction Tue 7/1/14 Fri 5/29/15 R2087 RecPL - 24-Inch, 927 Zone, Wueste Road - Olympic/Otay WTP Tue 4/24/12 Tue 4/24/12 Construction Fri 7/1/16 Wed 5/31/17 R2091 RecPS - 927-1 Pump Station Upgrade (10,000 GPM) and System Tue 4/24/12 Tue 4/24/12 Construction Wed 6/1/11 Fri 6/29/12 R2094 Potable Irrigation Meters to Recycled Water Conversions Tue 4/24/12 Tue 4/24/12 Construction Fri 7/1/11 Wed 5/31/17 R2096 RWCWRF - Upgrades and Modifications Tue 4/24/12 Tue 4/24/12 Construction Mon 5/2/11 Fri 5/31/13 R2099 Recycled System Air and Vacuum Value Retrofit Tue 4/24/12 Tue 4/24/12 Planning Fri 7/1/11 Fri 5/30/14 R2107 RWCWRF Screening Compactor and Chlorine Injectors Enclosure Tue 4/24/12 Tue 4/24/12 Planning Tue 4/24/12 Tue 4/24/12 Design Tue 4/24/12 Tue 4/24/12 Construction Mon 7/2/12 Fri 5/31/13 S2012 San Diego County Sanitation District Outfall and RSD Outfall Tue 4/24/12 Tue 4/24/12 Planning Tue 7/1/03 Thu 5/31/18 S2019 Avocado Boulevard 8-Inch Sewer Main Improvement Tue 4/24/12 Tue 4/24/12 Construction Fri 10/1/10 Fri 11/30/12 S2020 Calavo Drive 8-Inch Sewer Main Replacement Tue 4/24/12 Tue 4/24/12 Construction Fri 10/1/10 Fri 11/30/12 S2022 Hidden Mesa Drive 8-Inch Sewer Main Rehabilitation Tue 4/24/12 Tue 4/24/12 Construction Fri 10/1/10 Fri 11/30/12 S2023 Calavo Drive Sewer Main Utility Relocation Tue 4/24/12 Tue 4/24/12 Planning Wed 7/1/09 Mon 8/31/09 Design Thu 10/1/09 Fri 6/29/12 Construction Mon 7/2/12 Wed 2/27/13 S2024 Campo Road Sewer Main Replacement Tue 4/24/12 Tue 4/24/12 Planning Thu 7/1/10 Fri 11/30/12 Design Mon 1/2/12 Tue 12/31/13 Construction Mon 2/2/15 Wed 5/31/17 S2026 Challenge Boulevard 8-Inch Sewer Main Replacement Tue 4/24/12 Tue 4/24/12 Construction Mon 1/2/12 Tue 4/30/13 S2027 Rancho San Diego Pump Station Rehabilitation Tue 4/24/12 Tue 4/24/12 Planning Fri 7/1/11 Thu 5/31/12 Design Mon 7/2/12 Fri 11/30/12 Construction Tue 1/1/13 Fri 8/29/14 S2028 Explorer Way 8-Inch Sewer Main Replacement Tue 4/24/12 Tue 4/24/12 Planning Fri 7/1/11 Tue 12/30/14 Design Thu 1/1/15 Tue 6/30/15 Construction Tue 9/1/15 Wed 8/31/16 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2013 2014 2015 2016 2017 2018 Otay Water District FY 2013 - FY 2018 CIP Project Schedule 32 Task Name Project Name Start Finish S2033 Sewer System Various Locations Rehabilitation Tue 4/24/12 Tue 4/24/12 Planning Fri 7/1/11 Fri 5/31/13 Design Mon 7/2/12 Fri 6/28/13 Construction Mon 9/2/13 Mon 8/31/15 S2039 Hidden Mountain Lift Station Enclosure Tue 4/24/12 Tue 4/24/12 Planning Tue 4/24/12 Tue 4/24/12 Design Tue 4/24/12 Tue 4/24/12 Construction Mon 7/2/12 Fri 5/31/13 S2040 Calavo Sewer Basin Improvements Tue 4/24/12 Tue 4/24/12 Planning Mon 7/2/12 Fri 12/28/12 Design Tue 1/1/13 Fri 6/28/13 Construction Mon 9/2/13 Fri 8/29/14 S2041 Rancho San Diego Sewer Basin Improvements Tue 4/24/12 Tue 4/24/12 Planning Mon 7/2/12 Mon 12/30/13 Design Wed 1/1/14 Tue 6/30/15 Construction Tue 9/1/15 Wed 8/31/16 S2042 Sewer Vehicle Capital Purchases Tue 4/24/12 Tue 4/24/12 Planning Mon 7/2/12 Fri 5/31/13 Design Tue 4/24/12 Tue 4/24/12 Construction Tue 4/24/12 Tue 4/24/12 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2013 2014 2015 2016 2017 2018 Otay Water District FY 2013 - FY 2018 CIP Project Schedule 33 Item#Amount Type Engineering Development Services R R R R R R R R R R Grand Total : P2366 APCD 120,000$ P2282 Vehicle 49,000$ P2286 Field 114,600$ S2042 Sewer Vehicle 325,000$ 608,600$ FY 2013 Capital Purchases Total of Vehicles 374,000.00 Total of Field Equipment 234,600.00 Vehicles Operations 3 This vehicle (Unit 110) is a Class 8 sewer line cleaning vehicle utilized to maintain the District's sewer collection system as required by the San Diego Regional Water Quality Control Board. The funding for this replacement will come from the Vehicle Capital Replacement Purchases (S2042) 325,000.00 11 Replacement backhoe (P2366)105,000.00 608,600.00 Summary by Project 4 2012 Ford F150 (P2282)26,000.00 6 2012 Toyota Matrix (P2282)23,000.00 1 Mueller CL-12 Tapping Machine (P2286)22,600.00 9 Heavy equipment trailer. (P2286)23,000.00 10 Portable light tower. (P2366)15,000.00 Operations 7 Crane for Unit 174 (P2286)26,000.00 8 Heavy equipment trailer. (P2286)23,000.00 Capital purchases are non-recurring operating expense items for District-wide use that cost more than $10,000 each and have an estimated useful life of two years or more. The Capital Purchase Projects include Field Equipment, Office Equipment and Furniture, and Vehicle purchases. Description Field Equipment 2 GPS Base Station consisting of a NetR9 receiver and Zephyr Geodetic II Antenna (P2286) 20,000.00 34 CIP Project Sheet Description The following pages describe each information item on the individual CIP project sheets included in this section. CIP Number: The CIP project number for all projects is assigned by the Engineering Project Manager, and is a unique identifying code on all District records for the specified project. Project Title: Project titles follow a set format as described herein. The type of project should be identified first. For example, if a project were a 711 Pressure Zone 24-inch pipeline, the title would read “PL - 24-Inch, 711 Zone, Location - From A to B.” Pump stations and reservoirs are identified similarly with abbreviations for type and size. Director Division: All projects are located within a Board of Director’s division boundary unless they apply to the entire District or are outside of the District boundaries. The Director division where the majority of the physical project is located is listed. If it is a District-wide project it is listed as “District-wide.” If it is outside the District boundary it is listed as “None.” Project Manager: The person responsible for managing the project from inception through completion. I.D. Location: Most projects are located within one or more improvement districts. The I.D. location listed is where the majority of the physical project is located. However, projects located in portions of the District which have not yet been annexed into an improvement district are listed as “None.”. Original Approved Date: The date the project was originally approved with budget expenditures for the corresponding fiscal year by the Board of Directors. Priority: The priority of the project is listed in this field as one of the following: 1. HIGH: Safety, restoration of service to customers, obligation that requires immediate action, directed by the Board of Directors, and/or critical system need. 2. MEDIUM: Upgrade of system or expansion requirement to maintain system reliability not critical. Identified through planning effort as required within next few fiscal years. 3. LOW: Identified through planning effort as required in future years to support development; not anticipated in the immediate future. 4. VERY LOW: Requirement may have low probability of need in the future. Related CIP Projects: A maximum of three CIP project numbers that affect the scheduling and/or is related to the subject project and/or could provide important information. Budget Amount: The estimated budget includes all costs needed to complete a project including land, right-of-way, consultants, contractors, District staff time, etc. All prior years’ costs are part of the total cost and dollars are rounded up to the nearest $1,000. Description of Project: A brief description of a project which typically includes size, length, capacity, etc. 35 Justification of Project: A brief explanation of why a project is required which addresses flexibility, reliability, water quality, safety, contractual obligation, immediate growth, etc., as appropriate. Comments: Pertinent information that should be known about a project that is not shown elsewhere on the project sheet, including details of funding sources, including grant funding or contributions from other agencies. Funding Detail: The funding sources are listed along with the percentage of distribution to expansion, betterment, and/or replacement. Expenditure Schedule: The breakdown of a project’s expenditures by fiscal year – prior years’ cost along with a six-year budget schedule. Included in each year are all costs to complete the work scheduled in that year rounded up to the nearest $1,000. Project Schedule: The schedule of the primary project phase and estimated cost by the phases of planning, design, and construction shown with the estimated start date (month/year), finish date (month/year). The schedule time frames and estimated cost for each major phase of the project, correspond with the expenditure schedule information. Project Incremental Operation Expenditures: To determine the cost to maintain these new assets, the District looks at the cost of maintaining similar assets through the Infrastructure Management System and financial system. Costs are tracked by three main infrastructure asset groups of pipes, pump stations, and reservoirs, as well as capital purchases and other types. Pipes typically have only operation and maintenance (O&M) costs associated with them, pump stations have O&M as well as power cost, and reservoirs have O&M and chemical cost. Each of the capital purchases and other types has its own unique O&M cost. See page 27 for a further explanation of these expenditures. Project Location: A vicinity map is drawn in AutoCAD format using the GIS database as the foundation showing the approximate location and limits of a project within the District. Some projects do not have a specific location. In this case, a map of the entire District will then be shown as the project location. Thomas Bros. Map: The Thomas Brothers’ map page is inserted in this field to show where the project is primarily located. Some projects do not have a specific location in which case the words “District-wide” will be shown. OWD Map Book: The page in the District’s facility map book where a project is primarily located. Some projects do not have a specific location in which case the words “District-wide” will be shown. Submitted By: The project manager who originally submitted or the project manager who revised the project sheet along with the date of submittal or last revision date of the CIP project sheet. 36 CIP No Project Description Page P2009 PL - 36-Inch, SDCWA Otay FCF No. 14 to Regulatory Site 39 P2083 PS - 870-2 Pump Station Replacement (28,000 GPM)41 P2267 36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations 43 P2370 La Presa System Improvements 45 P2434 Rancho Del Rey Groundwater Well Development 47 P2451 Otay Mesa Desalination Conveyance and Disinfection System 49 P2466 Regional Training Facility 51 P2486 Asset Management Plan Condition Assessment and Data Acquisition 53 P2502 803-1 Pump Station Modifications 55 P2503 850-2 Pump Station Modifications 57 P2511 North District - South District Interconnection System 59 P2514 PL - 30-Inch, 980 Zone, Hunte Parkway - Proctor Valley/Use Area 61 P2527 1200-1 Pump Station Facility Cover 63 P2528 30-Inch Potable Water Pipeline Manifold at 624 Reservoirs 65 P2536 HMBP-Emergency Stand-By Generator Secondary Containment 67 P2537 Operations Yard Property Acquisition Improvements 69 R2048 RecPL - Otay Mesa Distribution Pipelines and Conversions 71 R2058 RecPL - 16-Inch, 860 Zone, Airway Road - Otay Mesa/Alta 73 R2077 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway 75 R2087 RecPL - 24-Inch, 927 Zone, Wueste Road - Olympic/Otay WTP 77 R2091 RecPS - 927-1 Pump Station Upgrade (10,000 GPM) and System Enhancements 79 R2107 RWCWRF Screening Compactor and Chlorine Injectors Enclosure 81 S2039 Hidden Mountain Lift Station Enclosure 83 23 Total Capital Facility Projects P2366 APCD Engine Replacements and Retrofits 85 P2382 Safety and Security Improvements 87 P2440 I-905 Utility Relocations 89 P2453 SR-11 Utility Relocations 91 P2458 AMR Manual Meter Replacement 93 P2477 Res - 624-1 Reservoir Cover Replacement 95 P2484 Large Water Meter Testing and Replacement Program 97 P2485 SCADA Communication System and Software Replacement 99 P2491 850-3 Reservoir Exterior Coating 101 P2493 624-2 Reservoir Interior/Exterior Coating 103 P2494 Multiple Species Conservation Plan 105 P2495 San Miguel Habitat Management/Mitigation Area 107 P2496 Otay Lakes Road Utility Relocations 109 P2504 Regulatory Site Access Road and Pipeline Relocation 111 P2507 East Palomar Street Utility Relocation 113 P2508 Pipeline Cathodic Protection Replacement Program 115 P2513 East Orange Avenue Bridge Crossing 117 P2515 870-1 Reservoir Paving 119 P2518 803-3 Reservoir Interior/Exterior Coating 121 CIP Projects Index CAPITAL FACILITY PROJECTS REPLACEMENT/RENEWAL PROJECTS REPLACEMENT/RENEWAL PROJECTS, continued 37 CIP Projects Index P2519 832-2 Reservoir Interior/Exterior Coating 123 P2520 Motorola Mobile Radio Upgrade 125 P2521 Large Meter Vault Upgrade Program 127 P2535 458-2 Reservoir Interior Coating 129 R2096 RWCWRF - Upgrades and Modifications 131 R2099 Recycled System Air and Vacuum Value Retrofit 133 S2012 San Diego County Sanitation District Outfall and RSD Outfall Replacement 135 S2019 Avocado Boulevard 8-Inch Sewer Main Improvement 137 S2020 Calavo Drive 8-Inch Sewer Main Replacement 139 S2022 Hidden Mesa Drive 8-Inch Sewer Main Rehabilitation 141 S2023 Calavo Drive Sewer Main Utility Relocation 143 S2024 Campo Road Sewer Main Replacement 145 S2026 Challenge Boulevard 8-Inch Sewer Main Replacement 147 S2027 Rancho San Diego Pump Station Rehabilitation 149 S2028 Explorer Way 8-Inch Sewer Main Replacement 151 S2033 Sewer System Various Locations Rehabilitation 153 S2040 Calavo Sewer Basin Improvements 155 S2041 Rancho San Diego Sewer Basin Improvements 157 37 Total Renewal & Replacements P2282 Vehicle Capital Purchases 159 P2286 Field Equipment Capital Purchases 161 P2443 Wireless Communications System 163 P2461 Records Management System Upgrade 2 165 P2469 Information Technology Network and Hardware 167 P2470 Financial System Enhancements 169 S2042 Sewer Vehicle Capital Purchases 171 7 Total Capital Purchase P2325 PL - 10-inch to 12-inch Oversize, 1296 Zone, PB Road - Rolling Hills Hydro PS/PB Bndy 173 R2083 RecPL - 20-Inch, 680 Zone, Heritage Road - Village 2/Olympic 175 R2094 Potable Irrigation Meters to Recycled Water Conversions 177 3 Total Developer Reimbursement Projects DEVELOPER REIMBURSEMENT PROJECTS REPLACEMENT/RENEWAL PROJECTS, continued CAPITAL PURCHASE PROJECTS 38 P2009PL - 36-Inch, SDCWA Otay FCF No. 14 to Regulatory Site Ron Ripperger 7/16/1997 5 3 & 20 1 $21,600,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 27,300 feet of 36-inch pipeline from San Diego County Water Authority (SDCWA) Otay FCF No. 14 to the Regulatory Site and fund 50% of the cost to upgrade FCF No. 14 to a capacity of 16 million gallons per day. JUSTIFICATION OF PROJECT: The East County Regional Treated Water Improvement Program (ECRTWIP) Agreement was approved by Otay Water District Board in December 2005 and by the SDCWA Board in February 2006. Per terms of the agreement and its amendments the Otay Water District is obligated to construct the pipeline by January 1, 2011 and SDCWA is to have FCF No. 14 operational by then as well. COMMENTS: The SDCWA has provided $4.2 million in funds towards construction of the pipeline per terms of the Agreement Between the San Diego County Water Authority and Otay Water District Regarding Implementation of the East County Regional Treated Water Improvement Program. The cost estimate includes the payment of $620,000 to SDCWA. Betterment ID 9 0 %2 %0 %0 %2 % Expansion 40 %0 %0 %0 %40 % Betterment ID 10 0 %4 %0 %0 %4 % Betterment ID 22 0 %30 %0 %0 %30 % Betterment ID 20 0 %7 %0 %0 %7 % Betterment ID 1 0 %5 %0 %0 %5 % Betterment ID 7 0 %5 %0 %0 %5 % Betterment ID 2 0 %2 %0 %0 %2 % Betterment ID 5 0 %1 %0 %0 %1 % Betterment ID 3 0 %4 %0 %0 %4 % TOTAL:40 % 60 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $21,600$0$0$0$0$0$900 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $20,700 39 P2009 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/1997 10/1/2007 11/1/2007 6/1/2009 $309 $2,691 PROJECT PHASE: 7/1/2009 1/1/2014 $18,600 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1272 356 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $62,100$11,100$10,800$10,500$10,200$9,900$9,600 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:9/22/2011Ron Ripperger 40 P2083PS - 870-2 Pump Station Replacement (28,000 GPM) Jeff Marchioro 5/17/1995 P2451 2 7 1 $12,581,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of a new pump station to replace the existing Low Head and High Head pump stations and to expand capacity as projected within the Rosarito Desalination Technical Memorandums prepared by CDM. JUSTIFICATION OF PROJECT: The two existing pump stations have reached the end of its useful lives and are under capacity for delivery of the proposed Rosarito Desalination water supply. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $12,581$5,948$5,250$750$1$1$50 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $581 41 P2083 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/1/2013 7/1/2013 12/1/2015 $650 $1,100 PROJECT PHASE: 1/1/2016 1/1/2019 $10,831 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1332 055 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:9/22/2011Jeff Marchioro 42 P226736-Inch Main Pumpouts and Air/Vacuum Ventilation Installations Tadeo Vasquez 6/3/1996 3 1 2 $435,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Installation of ventilation equipment on the existing pump out and air/vacuum vaults on 36-inch transmission main from the San Diego County Water Authority Otay FCF No. 11 to the Regulatory Site. This project also includes upsizing the existing 2-inch air/vacuum valves to 6-inch. JUSTIFICATION OF PROJECT: The vault openings do not stay in place when refilling because they lack ventilation. By installing vents in these vaults, the lids will stay in place, thus eliminating a safety hazard. Draining and filling the 36-inch main at higher flow rates is required to return the system to service in shorter periods of time. COMMENTS: Betterment ID 1 0 % 100 %0 %0 %100 % TOTAL:0 % 100 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $435$0$0$0$200$230$5 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 43 P2267 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/1997 6/1/2015 $435 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1291 198 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/19/2011Tadeo Vasquez 44 P2370La Presa System Improvements Daniel Kay 7/16/1997 3 1 1 $1,430,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project includes the construction of four interconnections in the La Presa System. Three of the connections are between the 36-inch main and 6-inch main in San Carlos Street. The fourth connection is in Paradise Valley Road at the beginning of the 42- inch main and the 16-inch pipeline. The project will also demolish the existing Dorchester Reservoir and hydropneumatic pump station on Dorchester Street. The La Presa 657-1 and 850-1 Pump Stations will be demolished after a new pressure reducing station between the 850/657 pressure zone is constructed. JUSTIFICATION OF PROJECT: The interconnections will provide enhanced capacity, increased reliability, and operational flexibility for the La Presa System. The existing reservoir and pump station are no longer required to serve customers. The pressure reducing station will allow for necessary increased flow rates into the 657 Pressure Zone to meet supply requirements. COMMENTS: Betterment ID 1 0 % 100 %0 %0 %100 % TOTAL:0 % 100 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,430$0$0$0$0$0$195 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,235 45 P2370 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2005 11/1/2010 12/1/2010 7/1/2011 $3 $110 PROJECT PHASE: 8/1/2011 7/1/2012 $1,317 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1290 301 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 ($10,500)$0($2,300)($2,200)($2,100)($2,000)($1,900) Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/19/2011Daniel Kay 46 P2434Rancho Del Rey Groundwater Well Development Jeff Marchioro 5/21/2009 2 22 1 $8,700,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Production groundwater well development of approximately 400 gallons per minute for potable water use. The project includes construction of a reverse osmosis treatment facility. JUSTIFICATION OF PROJECT: This project is needed to meet the IRP water supply goals. COMMENTS: Water Supply project at 40% expansion and betterment funds from ID 1 at 5%, ID 2 at 2%, ID 3 at 4%, ID 5 at 1%, ID 7 at 5%, ID 9 at 2%, ID 10 at 4%, ID 20 at 7%, and ID 22 at 30%. Betterment ID 9 0 %2 %0 %0 %2 % New Water Supply Fee Projects 0 %0 %0 %40 %40 % Betterment ID 10 0 %4 %0 %0 %4 % Betterment ID 22 0 %30 %0 %0 %30 % Betterment ID 20 0 %7 %0 %0 %7 % Betterment ID 1 0 %5 %0 %0 %5 % Betterment ID 7 0 %5 %0 %0 %5 % Betterment ID 2 0 %2 %0 %0 %2 % Betterment ID 5 0 %1 %0 %0 %1 % Betterment ID 3 0 %4 %0 %0 %4 % TOTAL:0 %60 %0 %40 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $8,700$0$0$0$1,500$3,100$500 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $3,600 47 P2434 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/1994 12/1/2010 1/1/2011 7/1/2012 $2,600 $1,050 PROJECT PHASE: 8/1/2012 8/1/2015 $5,050 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1310 127 $70,000$14,000$14,000$14,000$14,000$14,000$0 $1,300,000$260,000$260,000$260,000$260,000$260,000$0 $1,650,000$330,000$330,000$330,000$330,000$330,000$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/20/2011Jeff Marchioro 48 P2451Otay Mesa Desalination Conveyance and Disinfection System Bob Kennedy 5/23/2006 P2083 2 7 1 $30,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: The Otay Water District could potentially receive a potable water supply source from the planned Rosarito Desalination Facility via a conveyance system, pumping facilities, and disinfection system. JUSTIFICATION OF PROJECT: The concept could provide for a independent water source to the Otay Water District. COMMENTS: Betterment ID 9 0 %2 %0 %0 %2 % New Water Supply Fee Projects 0 %0 %0 %40 %40 % Betterment ID 10 0 %4 %0 %0 %4 % Betterment ID 22 0 %30 %0 %0 %30 % Betterment ID 20 0 %7 %0 %0 %7 % Betterment ID 1 0 %5 %0 %0 %5 % Betterment ID 7 0 %5 %0 %0 %5 % Betterment ID 2 0 %2 %0 %0 %2 % Betterment ID 5 0 %1 %0 %0 %1 % Betterment ID 3 0 %4 %0 %0 %4 % TOTAL:0 %60 %0 %40 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $30,000$500$8,300$9,500$8,000$1,500$1,000 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,200 49 P2451 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2006 3/1/2013 3/1/2013 9/1/2014 $1,200 $3,300 PROJECT PHASE: 10/1/2014 10/1/2016 $25,500 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $4,500$3,500$1,000$0$0$0$0 $34,000$25,000$9,000$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/20/2011Bob Kennedy 50 P2466Regional Training Facility Lisa Coburn-Boyd 5/29/2007 P2504 5 20 1 $300,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: The project is the construction of a Regional Training Facility at the Regulatory Site through a partnership with the San Miguel Consolidated Fire Protection District. JUSTIFICATION OF PROJECT: The Otay Water District needs a training center to train staff on trenching, shoring, fire safety, rescue, and confined space. The San Miguel Consolidated Fire Protection District has secured funding for this project and will be the lead agency in the development of the training facility. COMMENTS: Betterment ID 10 0 %4 %0 %0 %4 % Expansion 40 %0 %0 %0 %40 % Betterment ID 20 0 %7 %0 %0 %7 % Betterment ID 1 0 %5 %0 %0 %5 % Betterment ID 22 0 %30 %0 %0 %30 % Betterment ID 2 0 %2 %0 %0 %2 % Betterment ID 9 0 %2 %0 %0 %2 % Betterment ID 3 0 %4 %0 %0 %4 % Betterment ID 7 0 %5 %0 %0 %5 % Betterment ID 5 0 %1 %0 %0 %1 % TOTAL:40 % 60 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $300$0$0$0$0$14$14 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $272 51 P2466 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 8/1/2006 6/30/2013 $300 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 343 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/20/2011Lisa Coburn-Boyd 52 OTAY WATER DISTRICT P2486Asset Management Plan Condition Assessment and Data Acquisition Geoff Stevens 5/21/2009 District Wide 1 $1,350,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the development of an integrated Asset Management and replacement of GBA work order system with Azteca system. JUSTIFICATION OF PROJECT: Implementation of an Asset Management Plan is best practice and will provide for a formal means of maintaining, replacing, and funding the existing fixed assets. COMMENTS: :RUNRUGHUDQGILHOGV\VWHPVLPSOHPHQWDWLRQ. ,QWHUQDOODERU. 'HFLVLRQ6XSSRUW&RQVXOWLQJ,PSOHPHQWDWLRQ. 5HDOORFDWLQJIXQGVQRWVSHQWLQ)<QRWLQFUHDVLQJRYHUDOOEXGJHW Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,350$59$60$60$60$50$200 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $861 CAPITAL IMPROVEMENT PROGRAM 53 P2486 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 6/1/2018 $1,350 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/13/2011Geoff Stevens 54 P2502803-1 Pump Station Modifications Jeff Marchioro 5/17/2010 P2503 5 20 1 $625,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Modify the existing pumps within the pump station to allow for suction from the 640 Reservoirs. The concept is to install variable frequency drives and rebuild the existing pump motors to inverter duty. JUSTIFICATION OF PROJECT: The completion of the 640 reservoir project allows for a reduced static lift of 120 feet resulting in significant electrical energy savings. COMMENTS: Betterment ID 3 0 % 100 %0 %0 %100 % TOTAL:0 % 100 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $625$0$0$0$0$0$50 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $575 55 P2502 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 9/1/2010 10/1/2010 4/1/2011 $5 $45 PROJECT PHASE: 5/1/2011 12/1/2012 $575 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 343 $0$0$0$0$0$0$0 ($383,650)($89,500)($86,900)($84,400)($81,900)($40,950)$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Jeff Marchioro 56 P2503850-2 Pump Station Modifications Jeff Marchioro 5/17/2010 P2502 5 20 1 $525,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Modify the existing pumps within the pump station to allow for suction from the 640 Reservoirs and the 520 Reservoirs. The concept is to install variable frequency drives and rebuild the existing fixed speed pump motors to inverter duty. JUSTIFICATION OF PROJECT: The completion of the 640 reservoir project allows for a reduced static lift of 120 feet resulting in significant electrical energy savings. COMMENTS: Betterment ID 20 0 % 100 %0 %0 %100 % TOTAL:0 % 100 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $525$0$0$0$0$0$50 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $475 57 P2503 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 9/1/2010 10/1/2010 4/1/2011 $5 $45 PROJECT PHASE: 5/1/2011 12/1/2012 $475 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 343 $0$0$0$0$0$0$0 ($236,100)($55,100)($53,500)($51,900)($50,400)($25,200)$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Jeff Marchioro 58 P2511North District - South District Interconnection System Jeff Marchioro 5/17/2010 P2528 3 1 1 $37,300,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will provide for a 30-inch transmission main interconnection and pump station between the North District and South District to transport 10,000 gallons per minute between the two systems in either direction. Also the system will allow for the ability to transfer water from the Sweetwater Authority Perdue Water Treatment Plant into either the North or South District. JUSTIFICATION OF PROJECT: The Integrated Water Resources Plan identifies the objective, goals, purpose, and benefits of interconnecting the North and South Districts as well as for the need to diversify water resources for increased reliability. COMMENTS: General Fund at 40% expansion and betterment funds from ID 1 at 5%, ID 2 at 2%, ID 3 at 4%, ID 5 at 1%, ID 7 at 5%, ID 9 at 2%, ID 10 at 4%, ID 20 at 7%, and ID 22 at 30%. Betterment ID 7 0 %5 %0 %0 %5 % Betterment ID 22 0 %30 %0 %0 %30 % Betterment ID 9 0 %2 %0 %0 %2 % Betterment ID 20 0 %7 %0 %0 %7 % Betterment ID 10 0 %4 %0 %0 %4 % Expansion 40 %0 %0 %0 %40 % Betterment ID 5 0 %1 %0 %0 %1 % Betterment ID 1 0 %5 %0 %0 %5 % Betterment ID 3 0 %4 %0 %0 %4 % Betterment ID 2 0 %2 %0 %0 %2 % TOTAL:40 % 60 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $3,550$0$0$0$0$1,000$1,000 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,550 59 P2511 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 12/31/2012 4/1/2012 8/1/2015 $1,250 $2,200 PROJECT PHASE: 7/1/2018 7/1/2020 $33,850 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1291 184 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Jeff Marchioro 60 P2514PL - 30-Inch, 980 Zone, Hunte Parkway - Proctor Valley/Use Area Daniel Kay 5 22 1 $1,550,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 2,200 feet of 30-inch pipeline in Hunte Parkway from Proctor Valley Road to the existing 980 Pressure Zone 30-inch pipeline at the southern end of the District's Use Area. JUSTIFICATION OF PROJECT: The existing transmission main capacity within the 980 Pressure Zone is insufficient to meet the needs of the system during peak demand periods. This project will resolve the peak demand pressure issues. COMMENTS: Expansion 100 % 0 %0 %0 %100 % TOTAL:100 % 0 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,550$0$0$0$0$0$1,150 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $400 61 P2514 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 12/1/2011 1/1/2012 12/1/2012 $100 $200 PROJECT PHASE: 1/1/2013 9/1/2013 $1,250 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 159 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $2,800$0$700$700$700$700$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Daniel Kay 62 P25271200-1 Pump Station Facility Cover Gary Stalker 5 03 2 $30,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Install a cover over the 1200-1 pump station. JUSTIFICATION OF PROJECT: The cover will protect the motor casings, electrical conduit, and rubber seals from deterioration at the 1200-1 pump station. COMMENTS: Betterment ID 3 0 % 100 %0 %0 %100 % TOTAL:0 % 100 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $30$0$0$0$0$0$30 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 63 P2527 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2013 6/1/2014 $30 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1252 E7 378 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:2/21/2012Gary Stalker 64 P252830-Inch Potable Water Pipeline Manifold at 624 Reservoirs Jeff Marchioro P2511 1 22/27 1 $7,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 8,000 feet of 30-inch potable water pipeline with control valving between the 624-1 and 624-2 reservoirs. JUSTIFICATION OF PROJECT: This project is needed to fully utilize the Otay Interconnect Pipeline (also known as North District - South District Interconnection System, CIP Number P2511) Project to its planned 10,000 gpm capacity. COMMENTS: Betterment ID 7 0 %5 %0 %0 %5 % Betterment ID 22 0 %30 %0 %0 %30 % Betterment ID 9 0 %2 %0 %0 %2 % Betterment ID 20 0 %7 %0 %0 %7 % Betterment ID 10 0 %4 %0 %0 %4 % Expansion 40 %0 %0 %0 %40 % Betterment ID 5 0 %1 %0 %0 %1 % Betterment ID 1 0 %5 %0 %0 %5 % Betterment ID 3 0 %4 %0 %0 %4 % Betterment ID 2 0 %2 %0 %0 %2 % TOTAL:40 % 60 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,300$0$0$0$0$1,000$300 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 65 P2528 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2013 7/1/2014 7/1/2014 7/1/2015 $300 $1,000 PROJECT PHASE: 7/1/2018 7/1/2020 $5,700 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 130 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:2/3/2012Jeff Marchioro 66 P2536HMBP-Emergency Stand-By Generator Secondary Containment Rick Acuna District Wide 1 $60,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: The Otay Water District Hazardous Material Business Plan has identified the need for secondary containment at 10 sites with emergency stand-by generators. JUSTIFICATION OF PROJECT: Secondary containment will prevent spills from stand-by generator diesel fuel or engine coolant from running off District property by containing it inside a block enclosure where it can be safely cleaned up. COMMENTS: Betterment ID 10 0 %4 %0 %0 %4 % Expansion 40 %0 %0 %0 %40 % Betterment ID 20 0 %7 %0 %0 %7 % Betterment ID 5 0 %1 %0 %0 %1 % Betterment ID 22 0 %30 %0 %0 %30 % Betterment ID 1 0 %5 %0 %0 %5 % Betterment ID 9 0 %2 %0 %0 %2 % Betterment ID 2 0 %2 %0 %0 %2 % Betterment ID 7 0 %5 %0 %0 %5 % Betterment ID 3 0 %4 %0 %0 %4 % TOTAL:40 % 60 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $60$0$0$0$0$0$60 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 67 P2536 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2012 6/1/2013 $60 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:2/17/2012Rick Acuna 68 P2537Operations Yard Property Acquisition Improvements Daniel Kay 11/13/2008 P2479 4 20 1 $300,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: The project will provide site improvements including fencing, grading, and paving for vehicle parking and equipment storage. JUSTIFICATION OF PROJECT: The site improvements are required to provide flexibility in operations and for future expansion purposes. COMMENTS: Expansion 100 % 0 %0 %0 %100 % TOTAL:100 % 0 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $300$0$0$0$0$50$250 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 69 P2537 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 11/1/2008 10/1/2012 11/1/2012 1/1/2013 $5 $20 PROJECT PHASE: 2/1/2013 3/1/2013 $275 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1291 318 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:12/14/2011Daniel Kay 70 R2048RecPL - Otay Mesa Distribution Pipelines and Conversions Daniel Kay 6/23/2008 R2058, R2077, R2087 2 7 1 $2,200,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of various distribution pipeline links and conversion of existing pipelines for recycled water use within the 860 Pressure Zone of the Otay Mesa System. JUSTIFICATION OF PROJECT: This project will connect the existing distribution recycled water pipelines, currently supplied with potable water, to the planned construction of pipeline links to supply all those existing water demands within the Otay Mesa System with recycled water. COMMENTS: Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102- 575. Expansion 100 % 0 %0 %0 %100 % TOTAL:100 % 0 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $2,200$1,752$50$1$1$1$15 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $380 71 R2048 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2008 12/1/2008 1/1/2009 6/1/2011 $80 $220 PROJECT PHASE: 7/1/2015 6/30/2018 $1,900 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1351 12 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/25/2011Daniel Kay 72 R2058RecPL - 16-Inch, 860 Zone, Airway Road - Otay Mesa/Alta Daniel Kay 6/16/1999 R2048, R2077, R2087 2 7 1 $3,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 10,700 feet of 16-inch pipeline within the 860 Pressure Zone in Airway Road from Otay Mesa Road to Alta Road. Portions of this project will be constructed by developers and these are subject to reimbursement at actual cost per Board policy. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for development of Otay Mesa within the 860 Pressure Zone. COMMENTS: Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102- 575. Expansion 100 % 0 %0 %0 %100 % TOTAL:100 % 0 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $3,500$2,141$1$1$1$1$5 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,350 73 R2058 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2001 12/1/2009 1/1/2010 6/1/2011 $120 $330 PROJECT PHASE: 7/1/2011 6/1/2017 $3,050 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1351 12 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/25/2011Daniel Kay 74 R2077RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway Daniel Kay 5/23/2006 R2048, R2058, R2087 2 7 1 $4,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 9,300 feet 24-inch pipeline within the 860 Pressure Zone in Alta Road from the Alta Gate location to Airway Road. This project will be constructed as part of the Otay Mesa recycled water system. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for development of Otay Mesa and link the planned 860-1 Reservoir with the recycled water transmission system in Otay Mesa. COMMENTS: Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102- 575. Expansion 100 % 0 %0 %0 %100 % TOTAL:100 % 0 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $4,500$0$0$0$224$950$950 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $2,376 75 R2077 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2001 12/1/2009 1/1/2010 6/1/2011 $164 $451 PROJECT PHASE: 7/1/2011 6/1/2015 $3,885 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1332 39 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/25/2011Daniel Kay 76 R2087RecPL - 24-Inch, 927 Zone, Wueste Road - Olympic/Otay WTP Kevin Cameron 5/23/2006 R2048, R2058, R2077 1 22 1 $7,000,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 15,100 feet of 24-inch pipeline within the 927 Pressure Zone in Wueste Road from Olympic Parkway to near the existing City of San Diego Otay WTP. This project will be constructed as part of the Otay Mesa recycled water system supply link. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for development of Otay Mesa and is a part of the link to the 927 Pressure Zone supply to the planned 860-1 Reservoir within the Otay Mesa recycled water system. COMMENTS: Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102- 575. Expansion 100 % 0 %0 %0 %100 % TOTAL:100 % 0 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $7,000$5,975$5$5$5$5$5 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,000 77 R2087 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 9/1/2006 12/1/2009 1/1/2010 6/1/2011 $180 $765 PROJECT PHASE: 7/1/2016 6/1/2017 $6,055 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1312 85 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Kevin Cameron 78 R2091RecPS - 927-1 Pump Station Upgrade (10,000 GPM) and System Enhancements Daniel Kay 5/29/2007 1 22 1 $1,880,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project consists of increasing the capacity of the existing station from 6,600 gallons per minute (gpm) to 10,000 gpm, installing three pressure reducing stations in the 927 Pressure Zone, replacing service saddles in a few streets, replacing 1,800 feet of 16-inch pipeline in EastLake Parkway, and replacing 1,200 of 16-inch pipeline in Hunte Parkway. JUSTIFICATION OF PROJECT: The overall operating conditions of the pump station have been modified as a result of the planned service to the Otay Mesa System recycled water system from the Central Area System. As a result the existing pumps within the station are undersized and some of the existing recycled water system pipelines will experience operating pressures above their rated pipeline pressure class. The project is planned to be accomplished in two phases. COMMENTS: Expansion 100 % 0 %0 %0 %100 % TOTAL:100 % 0 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,880$0$0$0$0$0$65 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,815 79 R2091 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2007 4/1/2008 5/1/2008 1/1/2011 $60 $120 PROJECT PHASE: 6/1/2011 6/30/2012 $1,700 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 115 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Daniel Kay 80 R2107RWCWRF Screening Compactor and Chlorine Injectors Enclosure Gary Stalker 3 20 2 $115,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Install screening compactor at the RWCWRF headwork and a 3-sided enclosure around the chlorine injectors at the reclamation plant chlorine contact basin. JUSTIFICATION OF PROJECT: 7KHVFUHHQLQJFRPSDFWRUZLOOUHPRYHZDVWHPDWHULDODWWKHKHDGZRUNWRWKH5:&:5)DQGFRPSDFWWKHPDWHULDOIRUGLVSRVDOWRD ODQGILOO7KLVZLOOUHVXOWLQUHGXFLQJWKHDPRXQWRIVROLGVGLVFKDUJHGEDFNWR0HWUR 7KH39&FKORULQHLQMHFWRUVDWWKHFKORULQHFRQWDFWEDVLQDWWKHUHFODPDWLRQSODQWQHHGWREHSURWHFWHGIURPVXQOLJKW COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $115$0$0$0$0$0$115 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 81 R2107 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2012 6/1/2013 $115 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 319 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:2/24/2012Gary Stalker 82 S2039Hidden Mountain Lift Station Enclosure Gary Stalker 5 18 2 $29,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Install a larger enclosure around the Hidden Mountain lift station. JUSTIFICATION OF PROJECT: The Hidden Mountain lift station enclosure is too small to provide staff access for the preventative and corrective maintenance of the station. The three way valve at this lift station cannot be accessed for exercising and maintenance. COMMENTS: Betterment ID 18 0 % 100 %0 %0 %100 % TOTAL:0 % 100 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $29$0$0$0$0$0$29 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 83 S2039 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2012 6/1/2013 $29 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1272 C1 377 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:2/24/2012Gary Stalker 84 OTAY WATER DISTRICT P2366APCD Engine Replacements and Retrofits Doug Rahders 12/6/2000 District Wide 1 $3,488,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will replace and/or retrofit 14 diesel fuel burning engines with best technology exhaust gas control systems throughout the Otay Water District to comply with APCD engine emission regulations. The Otay Water District also needs to replace, repower, and/or retrofit the heavy vehicle diesel fleet to comply with upcoming emissions regulations. JUSTIFICATION OF PROJECT: The Otay Water District is required to replace and/or retrofit its engines to meet current APCD requirements including the Air Toxics Control Measures, and to be consistent with the intended operation of the engines to meet system demands. The Otay Water District also needs to replace, repower, and/or retrofit the heavy vehicle diesel fleet to meet future emissions requirements. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $3,488$162$162$175$200$265$120 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $2,404 CAPITAL IMPROVEMENT PROGRAM 85 P2366 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 12/1/2000 6/1/2001 7/1/2001 6/1/2010 $113 $312 PROJECT PHASE: 7/1/2010 6/1/2018 $3,063 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/19/2011Doug Rahders 86 P2382Safety and Security Improvements Jerry Munoz 6/5/2002 District Wide 1 $3,397,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to improve the security of the Otay WD facilities by installing and upgrading to current standards the hardware and software required to provide access control, video surveillance, intrusion detection and response, and SCADA communication. JUSTIFICATION OF PROJECT: Although existing facilities are relatively safe and secure, the Federal government has recommended that security to water systems be improved. The project is required to fund needed changes and improvements to District facilities. COMMENTS: General Fund at 40% expansion and 60% replacement. Expansion 40 %0 %60 %0 %100 % TOTAL:40 %0 %60 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $3,397$0$300$300$300$300$300 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,897 87 P2382 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2002 8/1/2003 9/1/2003 6/1/2010 $62 $169 PROJECT PHASE: 8/1/2004 6/1/2017 $3,166 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/19/2011Jerry Munoz 88 P2440I-905 Utility Relocations Jeff Marchioro 6/2/2004 2 7 1 $1,600,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for all utility relocations required due to construction of I-905 on the Otay Mesa. Pipeline relocations vary from 12-inch to 24-inch. Five locations have been identified where existing facilities are in conflict with I-905. JUSTIFICATION OF PROJECT: Caltrans is constructing I-905, which has resulted in utility conflicts with Otay WD pipelines. In all cases, the Otay WD has prior and superior rights. The facilities must be relocated prior to Caltrans construction of I-905. The cost of the facilities relocations that have prior rights will be reimbursed by Caltrans. COMMENTS: Utility agreements were developed by Caltrans for each of the required facility relocations. Any betterment work such as pipeline size increase and/or additional length are at the Otay WD expense. Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,600$0$0$0$0$5$5 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,590 89 P2440 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 1/1/2003 9/1/2006 10/1/2003 9/1/2006 $121 $332 PROJECT PHASE: 10/1/2006 12/1/2013 $1,147 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1351 10 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/20/2011Jeff Marchioro 90 P2453SR-11 Utility Relocations Daniel Kay 5/23/2006 2 7 1 $2,250,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for all utility relocations required due to construction of SR-11 on the Otay Mesa. Facility relocations vary in size from 8-inch to 24-inch. Both the potable and recycled water systems are impacted. JUSTIFICATION OF PROJECT: Caltrans will construct SR-11, which will result in utility conflicts with existing Otay Water District facilities at various locations. In most cases, the Otay Water District does have prior and superior rights. The facilities must be relocated prior to Caltrans construction of SR-11. The cost of the facilities relocations that have prior rights will be reimbursed by Caltrans. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $2,250$0$700$1,000$125$125$200 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $100 91 P2453 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2006 6/1/2010 7/1/2009 10/1/2010 $20 $250 PROJECT PHASE: 11/1/2010 6/1/2014 $1,980 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1351 5 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/20/2011Daniel Kay 92 P2458AMR Manual Meter Replacement Tim Keeran 5/23/2006 District Wide 1 $9,400,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will provide funding to replace all manually read meters with Automatic Meter Reading (AMR) meters. Approximately 34,700 existing manual 3/4-inch meters will be replaced with the AMR meters. JUSTIFICATION OF PROJECT: This program will benefit the Otay Water District by reducing manpower resources. The goal is to complete twelve routes or approximately 5,760 existing meters per year. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $9,400$0$0$0$0$500$1,400 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $7,500 93 P2458 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2006 6/1/2014 $9,400 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 ($699,600)($240,000)($233,200)($226,400)$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/20/2011Tim Keeran 94 P2477Res - 624-1 Reservoir Cover Replacement Jeff Marchioro 6/23/2008 1 22 2 $800,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement of the existing membrane floating cover with new membrane material system. JUSTIFICATION OF PROJECT: The existing floating membrane cover has reached the end of its useful life and requires replacement to meet regulatory requirements. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $800$0$0$0$0$0$690 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $110 95 P2477 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2008 2/1/2012 2/1/2012 10/1/2012 $8 $110 PROJECT PHASE: 10/1/2012 2/1/2013 $682 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 114 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/20/2011Jeff Marchioro 96 P2484Large Water Meter Testing and Replacement Program Tim Keeran 5/21/2009 District Wide 1 $835,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for testing and any necessary replacement of water meters larger than 2-inch that do not meet the AWWA standards. There are a total of about 220 meters. JUSTIFICATION OF PROJECT: To be assured that all of the larger meters are registering accurately and the billing system is collecting the proper funds for water consumed. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $835$0$0$0$0$100$150 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $585 97 P2484 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2009 6/1/2014 $835 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Tim Keeran 98 P2485SCADA Communication System and Software Replacement Gary Stalker 5/21/2009 District Wide 1 $1,846,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will replace the existing SCADA software and radio communication system and install fuel level transmitters on all diesel fuel tanks. A Battery Backup System will be installed at remote SCADA/Radio sites without emergency power generators. JUSTIFICATION OF PROJECT: The vendor will no longer be upgrading or supporting the existing system beginning 2012. The radio equipment needs replacement to allow for increased band width capability to increase security systems functionality. The fuel level transmitters on all diesel fuel tanks and remote SCADA monitoring will provide supervisors with real time fuel levels to monitor available runtime on stand-by engines during extended power outages. The battery backup system will provide continuous communications and SCADA monitoring and control for 3 days, if the District lost power at sites without emergency power generators. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,846$0$0$0$0$491$629 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $726 99 P2485 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 7/1/2009 6/1/2014 $1,846 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Gary Stalker 100 P2491850-3 Reservoir Exterior Coating Kevin Cameron 5/21/2009 5 20 1 $350,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the exterior coating of the 850-3 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: The 850-3 Reservoir exterior coating is in poor condition and is in need of replacement. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $350$0$0$0$0$0$150 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $200 101 P2491 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 8/1/2009 9/1/2009 11/1/2011 $5 $30 PROJECT PHASE: 12/1/2011 6/1/2013 $315 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1272 355 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Kevin Cameron 102 P2493624-2 Reservoir Interior/Exterior Coating Kevin Cameron 5/21/2009 4 22 1 $1,850,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior and exterior coating of the 624-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the most recent reservoir assessment report dated August 8, 2008 the 624-2 Reservoir interior coating is in relatively poor condition and is in need of replacement. Based on the FY 2012 Corrosion Report for Reservoir Coatings, the exterior is scheduled to be replaced in FY 2013. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,850$0$0$0$390$1,450$8 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $2 103 P2493 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 8/1/2010 9/1/2010 12/31/2013 $5 $55 PROJECT PHASE: 1/1/2014 8/1/2014 $1,790 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 130 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Kevin Cameron 104 P2494Multiple Species Conservation Plan Lisa Coburn-Boyd 5/21/2009 P2495 District Wide 1 $930,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to provide funding to develop a plan to streamline the environmental permitting processes for the capital improvement program projects to be constructed. JUSTIFICATION OF PROJECT: The project will save time and money when compared to environmental permitting each capital improvement program project individually. COMMENTS: Expansion 100 % 0 %0 %0 %100 % TOTAL:100 % 0 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $930$0$0$0$0$30$93 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $807 105 P2494 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 6/30/2013 $930 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Lisa Coburn-Boyd 106 P2495San Miguel Habitat Management/Mitigation Area Lisa Coburn-Boyd 5/21/2009 P2494 5 22 1 $1,900,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to provide funding for the establishment and management of mitigation areas on capital improvement program projects sites and at the San Miguel Habitat Management Area to offset environmental impacts due to construction activities. JUSTIFICATION OF PROJECT: The resource agencies (USFWS, CDFG, etc.) require areas of land to be set aside, established, managed, and maintained in order to mitigate for impacts due to construction activities. COMMENTS: Expansion 100 % 0 %0 %0 %100 % TOTAL:100 % 0 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,900$200$200$200$200$200$120 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $780 107 P2495 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 6/30/2018 $1,900 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 159 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Lisa Coburn-Boyd 108 P2496Otay Lakes Road Utility Relocations Daniel Kay 5/21/2009 4 5 1 $275,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for all utility relocations required to accommodate the City of Chula Vista road improvement project located along Otay Lakes and Telegraph Canyon Roads. JUSTIFICATION OF PROJECT: The Otay WD will be required to relocate all conflicting systems at its own expense for the City of Chula Vista has prior and superior rights. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $275$0$0$0$0$0$50 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $225 109 P2496 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 8/1/2009 9/1/2009 12/1/2009 $4 $11 PROJECT PHASE: 1/1/2010 12/31/2013 $260 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 113 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Daniel Kay 110 P2504Regulatory Site Access Road and Pipeline Relocation Kevin Cameron 5/17/2010 P2466 5 20 1 $600,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Improve the existing access road from the proposed sheriff substation site to the Regulatory Reservoir Site. JUSTIFICATION OF PROJECT: Improving the existing access road will provide for increased safety and all weather permanent access to the Regulatory Reservoir Site. COMMENTS: Replacement 0 %0 %50 %0 %50 % Betterment ID 1 0 %50 %0 %0 %50 % TOTAL:0 %50 %50 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $600$0$0$0$175$225$50 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $150 111 P2504 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 9/1/2010 10/1/2010 12/1/2012 $55 $95 PROJECT PHASE: 1/1/2013 9/1/2014 $450 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 331 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Kevin Cameron 112 P2507East Palomar Street Utility Relocation Kevin Cameron 5/17/2010 2 10 2 $900,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the necessary utility relocations due to construction improvements to I-805 near East Palomar Street. Both the existing potable and recycled water systems will be impacted. JUSTIFICATION OF PROJECT: Caltrans will be making improvements to I-805 that will result in conflicts with existing pipelines. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $900$0$0$0$235$330$150 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $185 113 P2507 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 12/1/2010 1/1/2011 12/1/2011 $5 $195 PROJECT PHASE: 1/1/2012 6/1/2014 $700 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1330 80 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Kevin Cameron 114 P2508Pipeline Cathodic Protection Replacement Program Daniel Kay 5/17/2010 District Wide 1 $150,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the replacement and repairs of existing cathodic protection systems on various pipelines. JUSTIFICATION OF PROJECT: The ongoing cathodic protection program efforts have identified various pipelines for anode replacement, cathodic test station repair, installation of isolation kits, and repair of existing anode beds. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $150$0$0$0$0$50$80 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $20 115 P2508 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 9/1/2010 10/1/2010 4/30/2012 $5 $30 PROJECT PHASE: 5/1/2012 12/31/2013 $115 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Daniel Kay 116 P2513East Orange Avenue Bridge Crossing Kevin Cameron 2 10 1 $1,200,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 1,900 feet of 12-inch pipeline in Olympic Pkwy. / East Orange Ave. across I-805. This project will provide a needed and redundant pipeline to the area west of I 805. JUSTIFICATION OF PROJECT: The service area west of I-805 needs to have fire flow capacity increased as well as increase system reliability. COMMENTS: City of Chula Vista and Caltrans are requiring work to be done at night to limit traffic impacts. Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,200$0$0$0$0$150$840 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $210 117 P2513 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 6/1/2013 7/1/2013 12/1/2013 $25 $175 PROJECT PHASE: 1/1/2014 6/1/2016 $1,000 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1330 65 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Kevin Cameron 118 P2515870-1 Reservoir Paving Kevin Cameron 2 7 2 $550,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for repaving the existing perimeter road around the 870-1 Reservoir and add roadway paving to the reservoir. JUSTIFICATION OF PROJECT: The existing perimeter reservoir roadway is at the end of its useful life and access to the reservoir is limited in the winter months and unsafe. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $550$0$0$0$0$425$100 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $25 119 P2515 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 12/1/2011 1/1/2012 6/30/2013 $50 $75 PROJECT PHASE: 7/1/2013 12/31/2013 $425 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1332 55 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/24/2011Kevin Cameron 120 P2518803-3 Reservoir Interior/Exterior Coating Kevin Cameron 5 20 2 $750,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior and exterior coating of the 803-3 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2010 Cathodic Assessment Report, the 803-3 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $750$0$0$0$0$50$700 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 121 P2518 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 9/1/2012 10/1/2012 12/1/2013 $10 $50 PROJECT PHASE: 1/1/2013 9/1/2013 $690 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1272 370 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/25/2011Kevin Cameron 122 P2519832-2 Reservoir Interior/Exterior Coating Kevin Cameron 5 2 2 $775,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior and exterior coating of the 832-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2010 Cathodic Assessment Report, the 832-2 Reservoir interior and exterior coatings are in relatively poor condition and are in need of replacement. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $775$0$0$0$0$50$725 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 123 P2519 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 9/1/2012 10/1/2012 12/1/2013 $10 $50 PROJECT PHASE: 1/1/2013 9/1/2013 $715 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1272 332 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/25/2011Kevin Cameron 124 P2520Motorola Mobile Radio Upgrade Frank Anderson District Wide 1 $100,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for Motorola radio upgrades which involves three components, radio repeater upgrade, portable and base unit upgrades, and vehicle mobile radio upgrades. JUSTIFICATION OF PROJECT: The existing Motorola radio equipment is an essential part of the District's Emergency Response Program. A recent assessment of the radio equipment has determined that the equipment has reached the end of its useful life and needs upgrades. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $100$0$0$0$0$0$50 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $50 125 P2520 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 8/1/2011 10/1/2012 $100 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/25/2011Frank Anderson 126 P2521Large Meter Vault Upgrade Program Tim Keeran District Wide 1 $600,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is for the retrofit and upgrade of approximately 40 large water meters and vaults to above ground standards. JUSTIFICATION OF PROJECT: The existing large meters are installed in below grade vaults which create increased costs and safety issues due to confined space requirements. The existing below grade systems are subject to flooding and create corrosive environments. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $600$0$0$60$100$150$150 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $140 127 P2521 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: $0 $0 PROJECT PHASE: 8/1/2011 12/1/2015 $600 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/25/2011Tim Keeran 128 P2535458-2 Reservoir Interior Coating Kevin Cameron 2 9 2 $300,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the interior coating of the 458-2 Reservoir. In addition, an assessment of the facility will be accomplished to assure compliance to all applicable codes and OSHA standards. JUSTIFICATION OF PROJECT: Based upon the 2011 Cathodic Assessment Report, the 458-2 Reservoir interior coating is in relatively poor condition and is in need of replacement. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $300$0$0$0$20$275$5 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 129 P2535 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 6/1/2013 9/30/2013 10/1/2013 12/31/2014 $5 $45 PROJECT PHASE: 1/1/2014 6/1/2014 $250 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1330-J4 66 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:2/21/2012Kevin Cameron 130 R2096RWCWRF - Upgrades and Modifications Daniel Kay 5/21/2009 3 20 1 $4,995,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project includes the rehabilitation of the RWCWRF blower system, air pipeline replacement, and filter storage reservoir cover replacement along with the identification and implementation of modifications for optimization of the air system and other treatment systems to control total nitrogen. JUSTIFICATION OF PROJECT: The existing blowers are old and not efficient and the existing air piping system is leaking due to corrosion. The plant effluent is exceeding its discharge limit for total nitrogen thus the treatment process must be modified and optimized so that all discharge requirements can be met. The existing flexible membrane cover material is damaged and is in need of replacement. Recycled water quality is currently being comprised. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $4,995$0$0$0$0$0$60 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $4,935 131 R2096 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 9/1/2009 10/1/2009 4/1/2011 $40 $110 PROJECT PHASE: 5/1/2011 6/1/2013 $4,845 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 319 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Daniel Kay 132 R2099Recycled System Air and Vacuum Value Retrofit Roger Holly 1 22 1 $700,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to provide funding for the upgrading of approximately 274 existing recycled water system air and vacuum valves that are presently above grade to below grade installations. JUSTIFICATION OF PROJECT: Some of the recycled water system existing air and vacuum valves are located in streets, roadways, and other locations that are subject to being struck and damaged by vehicles. Some of these facilities will require extension of the piping outside of the traveled way. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $700$0$0$0$0$233$233 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $234 133 R2099 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 6/1/2014 $700 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Roger Holly 134 S2012San Diego County Sanitation District Outfall and RSD Outfall Replacement Bob Kennedy 6/4/2003 3 18 1 $3,550,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the Otay Water District proportionate share of the San Diego County Sanitation District total costs for replacement of various system components of the existing Spring Valley and Rancho San Diego Outfall Systems per terms of an existing agreement with the SVSD. The reimbursement also includes a proportionate share of operating and maintenance costs. JUSTIFICATION OF PROJECT: Various components of the San Diego County Sanitation District Spring Valley Outfall and the Rancho San Diego Outfall are in very bad condition and are need of repair and/or replacement. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $3,550$800$450$450$450$450$100 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $850 135 S2012 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2003 6/1/2018 $3,550 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Bob Kennedy 136 S2019Avocado Boulevard 8-Inch Sewer Main Improvement Daniel Kay 5/21/2009 5 18 1 $2,275,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides sewer main capacity upgrades for approximately 3,200 feet of existing 8-inch ABS sewer main in Avocado Boulevard. JUSTIFICATION OF PROJECT: The existing sewer main is under sized and the capacity must be increased and has debris deposit problems. COMMENTS: Betterment ID 18 0 % 100 %0 %0 %100 % TOTAL:0 % 100 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $2,275$0$0$0$0$0$1,375 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $900 137 S2019 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 2/1/2010 3/1/2010 9/1/2010 $65 $275 PROJECT PHASE: 10/1/2010 12/1/2012 $1,935 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 342 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Daniel Kay 138 S2020Calavo Drive 8-Inch Sewer Main Replacement Daniel Kay 5/21/2009 5 18 1 $600,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funds to replace approximately 600 feet of existing 8-inch ABS sewer main in Calavo Drive. JUSTIFICATION OF PROJECT: The existing sewer main is under sized and the capacity must be increased and has debris deposit problems. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $600$0$0$0$0$0$210 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $390 139 S2020 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 2/1/2010 3/1/2010 9/1/2010 $14 $60 PROJECT PHASE: 10/1/2010 12/1/2012 $526 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 342 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Daniel Kay 140 S2022Hidden Mesa Drive 8-Inch Sewer Main Rehabilitation Daniel Kay 5/21/2009 5 18 1 $180,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funds to replace approximately 315 feet of existing 8-inch VCP sewer main in Hidden Mesa Drive. JUSTIFICATION OF PROJECT: The existing sewer main is under sized and the capacity must be increased and has debris deposit problems. COMMENTS: Betterment ID 18 0 % 100 %0 %0 %100 % TOTAL:0 % 100 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $180$0$0$0$0$0$50 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $130 141 S2022 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 2/1/2010 3/1/2010 9/1/2010 $2 $40 PROJECT PHASE: 10/1/2010 12/1/2012 $138 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1272 368 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Daniel Kay 142 S2023Calavo Drive Sewer Main Utility Relocation Daniel Kay 5/21/2009 5 14 1 $80,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funds to replace approximately 230 feet of existing 8-inch ABS sewer main in Calavo Drive. JUSTIFICATION OF PROJECT: The County of San Diego plans to install a new storm drain culvert that conflicts with the existing sewer main. The County of San Diego has prior and superior rights thus Otay Water District will be responsible for the cost to replace the sewer main. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $80$0$0$0$0$0$60 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $20 143 S2023 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 9/1/2009 10/1/2009 6/30/2012 $2 $18 PROJECT PHASE: 7/1/2012 2/28/2013 $60 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 342 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Daniel Kay 144 S2024Campo Road Sewer Main Replacement Kevin Cameron 5/17/2010 3 18 2 $5,500,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funds to upgrade the sewer main capacity of approximately 11,050 feet of existing 10-inch PVC sewer main, 450 feet of 10-inch reinforced polymer mortar pipe sewer main, and 50 feet of 15-inch sewer main. The project location begins at the south end of Avocado Blvd, through the Rancho San Diego Village Shopping Center, paralleling SR-94/Campo Road in the adjacent open space. JUSTIFICATION OF PROJECT: The existing sewer main is under sized and must be replaced to increase capacity. Portions of the sewer main are located in areas of sensitive habitat making it difficult to access for maintenance. COMMENTS: Betterment ID 18 0 % 100 %0 %0 %100 % TOTAL:0 % 100 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $5,500$0$800$3,120$1,250$275$50 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $5 145 S2024 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2010 12/1/2012 1/1/2012 1/1/2014 $175 $725 PROJECT PHASE: 2/1/2015 6/1/2017 $4,600 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 330 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Kevin Cameron 146 S2026Challenge Boulevard 8-Inch Sewer Main Replacement Daniel Kay 5 14 2 $280,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funds to replace approximately 260 feet of existing 8-inch ABS sewer main in Challenge Boulevard. JUSTIFICATION OF PROJECT: The existing sewer main has several sags which has allowed debris deposits to form and is deformed in one section allowing groundwater infiltration. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $280$0$0$0$0$0$155 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $125 147 S2026 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 9/30/2011 10/1/2011 12/31/2011 $2 $30 PROJECT PHASE: 1/1/2012 5/1/2013 $248 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 354 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Daniel Kay 148 S2027Rancho San Diego Pump Station Rehabilitation Bob Kennedy 3 18 2 $2,800,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for the rehabilitation of the Rancho San Diego Pump Station located near Singer Lane. JUSTIFICATION OF PROJECT: The existing sewer pump station is over 20 years old and the pumps have reached the end of their useful lives. The pump station also needs improvements to bring the station up to current OSHA requirements. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $2,800$0$0$0$0$2,490$300 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $10 149 S2027 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 6/1/2012 7/1/2012 12/1/2012 $5 $50 PROJECT PHASE: 1/1/2013 9/1/2014 $2,745 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 331 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Bob Kennedy 150 S2028Explorer Way 8-Inch Sewer Main Replacement Jeff Marchioro 5 18 2 $125,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funds to replace approximately 200 feet of existing 8-inch PVC sewer main in Explorer Way. JUSTIFICATION OF PROJECT: The existing sewer main has several sags which has allowed debris deposits to form. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $125$0$25$60$30$1$1 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $8 151 S2028 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 12/31/2014 1/1/2015 7/1/2015 $15 $25 PROJECT PHASE: 9/1/2015 9/1/2016 $85 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 354 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011Jeff Marchioro 152 S2033Sewer System Various Locations Rehabilitation Jeff Marchioro S2040/S2041 5 18 2 $800,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for various sewer system rehabilitation efforts that have been identified. These efforts involve replacement of various very short segments of damaged sewer main, separated pipe joints, etc. JUSTIFICATION OF PROJECT: The closed circuit television sewer assessment program process have assisted in the identification of sewer mains that are damaged and need to be repaired. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $800$0$0$0$150$420$200 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $30 153 S2033 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2011 6/1/2013 7/1/2012 7/1/2013 $50 $225 PROJECT PHASE: 9/1/2013 9/1/2015 $525 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/27/2011Jeff Marchioro 154 S2040Calavo Sewer Basin Improvements Jeff Marchioro S2033 5 18 1 $1,250,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for various sewer system rehabilitation efforts that have been identified. These efforts involve replacement of approximately 3,000 lineal feet of various failing or damaged pipe segments, separated pipe joints, etc. JUSTIFICATION OF PROJECT: The closed circuit television sewer assessment program process has assisted in the identification of sewer mains containing sags, which has allowed debris to form, and/or are damaged and need to be repaired. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,250$0$0$0$450$525$275 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 155 S2040 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2012 12/31/2012 1/1/2013 7/1/2013 $75 $200 PROJECT PHASE: 9/1/2013 9/1/2014 $975 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271 342S, 353S, 354S, 36 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:2/15/2012Jeff Marchioro 156 S2041Rancho San Diego Sewer Basin Improvements Jeff Marchioro S2033 5 18 2 $1,750,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for various sewer system rehabilitation efforts that have been identified. These efforts involve replacement of approximately 4,000 lineal feet of various failing or damaged pipe segments, separated pipe joints, etc. JUSTIFICATION OF PROJECT: The closed circuit television sewer assessment program process has assisted in the identification of sewer mains containing sags, which has allowed debris to form, and/or are damaged and need to be repaired. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,750$0$600$800$235$75$40 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 157 S2041 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2012 12/31/2013 1/1/2014 7/1/2015 $100 $250 PROJECT PHASE: 9/1/2015 9/1/2016 $1,400 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1271, 1252, 1272 344S, 356S, 357S, 36 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:2/15/2012Jeff Marchioro 158 P2282Vehicle Capital Purchases Doug Rahders 6/3/1996 District Wide 1 $5,021,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for capital purchase of various vehicles for daily Otay Water District functions. JUSTIFICATION OF PROJECT: Replacements or newly acquired vehicles will be used for operational and administrative functions throughout the entire Otay Water District. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $5,021$476$450$425$400$392$49 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $2,829 159 P2282 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 12/1/2000 6/1/2018 $5,021 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/19/2011Doug Rahders 160 P2286Field Equipment Capital Purchases Doug Rahders 6/3/1996 District Wide 1 $1,758,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides funding for capital purchase of various pieces of field equipment used for daily Otay Water District functions. JUSTIFICATION OF PROJECT: Replacements or new acquisitions of field equipment will be used for operational functions throughout the entire Otay Water District. COMMENTS: Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,758$75$75$74$75$90$115 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,254 161 P2286 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 12/1/2000 6/1/2018 $1,758 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/19/2011Doug Rahders 162 OTAY WATER DISTRICT P2443Wireless Communications System Geoff Stevens 5/23/2005 District-Wide 1 $1,492,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Install hardware to provide wireless communication infrastructure to district facilities. JUSTIFICATION OF PROJECT: The Otay Water District is implementing new work processes that will require field access to GIS data and support field automation such as GPS expansion. This project will ensure that the technology is appropriate and implemented in a planned and cost effective manner. COMMENTS: In Fiscal Year 2012 we refocused our effort on better security for the Treatment Plant and finishing the systems in the North District. This delayed our expansion to the South District so the bulk of these funds have been transferred from Fiscal Year 2012 to Fiscal Year 2013. This is not an increase in funding. Replacement 0 %0 %60 %0 %60 % Expansion 40 %0 %0 %0 %40 % TOTAL:40 %0 %60 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $1,492$0$0$0$0$130$200 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,162 CAPITAL IMPROVEMENT PROGRAM 163 P2443 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2005 6/1/2018 $1,492 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $55,600$0$19,100$18,500$18,000$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/13/2011Geoff Stevens 164 P2461Records Management System Upgrade 2 Geoff Stevens 5/29/2007 District Wide 1 $475,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will continue with the expansion of the current records management system to capture existing paper records, scan, categorize, and expand scanning capabilities to all Otay Water District departments. This includes the implementation and record conversion costs. JUSTIFICATION OF PROJECT: This project is required to achieve strategic objectives for business process improvements and to meet the demands for business backup and recovery goals. Funding will be used to complete the inclusion of existing files and modify software to improve functionality. COMMENTS: Replacement 0 %0 %60 %0 %60 % Expansion 40 %0 %0 %0 %40 % TOTAL:40 %0 %60 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $475$0$0$0$0$0$90 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $385 165 P2461 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2007 6/1/2018 $475 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/13/2011Geoff Stevens 166 P2469Information Technology Network and Hardware Geoff Stevens 6/23/2008 District Wide 1 $2,173,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project will provide hardware and operating system improvements to create new functionality in the data center. JUSTIFICATION OF PROJECT: Enhance data center hardware and software to accommodate purchase of new and more efficient services such as automated backup, virus protection, and disaster recovery. COMMENTS: Replacement 0 %0 %60 %0 %60 % Expansion 40 %0 %0 %0 %40 % TOTAL:40 %0 %60 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $2,173$0$0$75$169$250$120 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,559 167 P2469 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2008 6/30/2016 $2,173 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/13/2011Geoff Stevens 168 P2470Financial System Enhancements Geoff Stevens 6/23/2008 District Wide 1 $2,732,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to develop enhancements and new integration functionality for Eden, GIS, IMS, and related core application systems. JUSTIFICATION OF PROJECT: This CIP funds the creation and enhancement and modifications of our existing financial information systems. Each year items which require software and hardware changes and additions to these systems are prioritized, scoped, and funded with this CIP. Funds are used for software development costs, software acquisition costs, consulting services, and associated new hardware. Items to be constructed and approximate costs for 2013 and 2014 are listed below. Items for 2015 and beyond will be determined as part of the 2015-2017 strategic plan process. COMMENTS: (OHFWURQLF3D\PHQWVDQGSXUFKDVHVPRGXOHV. &,33ODQQLQJ%XGJHWLQJDQG&RVWWUDFNLQJ0RGXOHV. ,QYHQWRU\&RQWURO±(TXLSPHQWWUDFNLQJ. &XVWRPHU%LOOLQJDQG3KRQH6\VWHP(QKDQFHPHQWV. Replacement 0 %0 %60 %0 %60 % Expansion 40 %0 %0 %0 %40 % TOTAL:40 %0 %60 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $2,732$0$50$200$200$200$220 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,862 169 P2470 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2008 6/1/2016 $2,732 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/13/2011Geoff Stevens 170 S2042Sewer Vehicle Capital Purchases Doug Rahders 5 18 1 $325,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project provides sewer funding for capital purchase of various vehicles for daily Otay Water District functions. JUSTIFICATION OF PROJECT: Replacement or newly acquired vehicles will be used for operational functions throughout the Otay Water District sewer service area. COMMENTS: It is planned to purchase two vehicles in Fiscal Year 2013. Replacement 0 %0 %100 %0 %100 % TOTAL:0 %0 %100 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $325$0$0$0$0$0$325 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $0 171 S2042 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2012 6/1/2013 $325 $0 PROJECT PHASE: $0 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:4/11/2012Doug Rahders 172 P2325PL - 10-inch to 12-inch Oversize, 1296 Zone, PB Road - Rolling Hills Hydro PS/PB Bndy David Charles 6/7/2000 5 22 2 $50,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 6,900 feet of 12-inch pipeline within the 1296 Pressure Zone from the Rolling Hills Hydropneumatic Pump Station to the future 1296 Reservoir. A portion of the project will be constructed by the developer and is subject to reimbursement at actual cost for the oversize portion per Board policy. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for development of Rolling Hills Ranch, Bello Lago, and possible future adjacent areas within the Rolling Hills Hydropneumatic Pressure Zone. COMMENTS: Expansion 100 % 0 %0 %0 %100 % TOTAL:100 % 0 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $50$0$0$0$0$0$49 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1 173 P2325 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2004 6/1/2013 9/1/2013 12/1/2013 $1 $6 PROJECT PHASE: 1/1/2014 6/1/2014 $43 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1311 160 $0$0$0$0$0$0$0 $9,800$0$2,600$2,500$2,400$2,300$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:12/14/2011David Charles 174 R2083RecPL - 20-Inch, 680 Zone, Heritage Road - Village 2/Olympic David Charles 6/2/2004 R2082, R2084 1 22 2 $400,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: Construction of approximately 2,200 feet of 20-inch pipeline within the 680 Pressure Zone in Heritage Road through Village 2 to Olympic Parkway. This project will be constructed by developers and is subject to reimbursement at actual cost per Board policy. JUSTIFICATION OF PROJECT: This project will provide transmission capacity for the recycled water supply pumped from the 680-1 Pump Station to the 680 and higher pressure zones. Significant energy savings will occur due to lower total dynamic head requirements for the 680-1 Pump Station. COMMENTS: Funding opportunity is the United States Bureau of Reclamation Water Reclamation and Reuse Program, Title XVI of P.L. 102- 575. Expansion 100 % 0 %0 %0 %100 % TOTAL:100 % 0 %0 %0 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $400$0$0$0$0$395$4 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1 175 R2083 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2004 6/1/2006 7/1/2006 12/1/2006 $16 $44 PROJECT PHASE: 7/1/2012 6/1/2014 $340 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book:1331 82 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $2,100$0$700$700$700$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011David Charles 176 R2094Potable Irrigation Meters to Recycled Water Conversions David Charles 5/21/2009 1 22 1 $3,100,000 PROJECT MANAGER: ORIGINAL APPROVED DATE: RELATED CIP PROJECTS: PROJECT TITLE:CIP Number: DIRECTOR DIVISION: I.D. LOCATION: PRIORITY: BUDGET AMOUNT: DESCRIPTION OF PROJECT: This project is to fund the conversion of existing potable water irrigation systems to use recycled water within existing multifamily and commercial type developments located adjacent to existing recycled water mains within the City of Chula Vista. JUSTIFICATION OF PROJECT: The expansion of recycled water development allows for potable water savings and increases the purchases of supply from the South Bay Water Reclamation Plant. COMMENTS: Water Supply project 40% expansion and betterment funds from ID 22 at 60%. New Water Supply Fee Projects 0 %0 %0 %40 %40 % Betterment ID 22 0 %60 %0 %0 %60 % TOTAL:0 %60 %0 %40 %100 % FUNDING SOURCE:Expansion Betterment Replacement New Water Supply Total FUND DETAILS: EXPENDITURE SCHEDULE (X $1,000): $3,100$290$300$300$300$200$10 Total201820172016201520142013 FYFYFYFYFYFYFYPRIOR YEARS: TOTAL $1,700 177 R2094 PROJECT SCHEDULE: PLANNING: DESIGN: CIP Number: ESTIMATED START DATE ESTIMATED FINISHED DATE ESTIMATED COST (X $1,000): CONSTRUCTION: 7/1/2009 12/1/2009 1/1/2010 6/1/2011 $80 $450 PROJECT PHASE: 7/1/2011 6/1/2017 $2,570 PROJECT LOCATION:Thomas Bros. Map:OWD Map Book: $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 $0$0$0$0$0$0$0 Total201820172016201520142013 PROJECTED INCREMENTAL OPERATING EXPENDITURES SCHEDULE ($): MAINT: ENERGY: CHEMICAL: Submitted By:Date:10/26/2011David Charles 178 Effective 7/1/12 IMPROVEMENT CAPACITY TOTAL NAME DISTRICT (ID)FEE CHARGE Capacity Fee Section 28.01 1,2,3,5,7,10,19,20,22,25,27 $7,900 $7,900 Triad Capacity Fee ID 22/27-BASE $5,912 $5,912 New Water Supply Fee $910 Note: This is based on a 3/4 inch water meter. For a full listing of fees per meter size visit the District's website at: www.otaywater.gov, Engineering, Public Services, Meter Fees and Deposits. Water Meter Capacity Fees 179 Glossary The Capital Budget contains terminology that is unique to public finance and budgeting. The following budget glossary provides assistance in understanding these terms. Acre-Foot: The volume of water that will cover one acre to a depth of one foot. One acre-foot equals 435.6 units or 325,850 gallons. Annexation Fees: Whenever water service is requested for land outside the boundaries of the District it must first be annexed into the District. The annexation fee for water service was set at $1,477 per EDU on July 1, 2009. Whenever sewer service is requested for land outside the boundaries of an improvement district (ID) it must first be annexed into the ID. The fee for sewer annexation was set at $3,819 on December 16, 1998. These base rates are adjusted quarterly according to a cost of living index. The rates as of July 1, 2011 are $1,518 and $5,602 for water and sewer, respectively. Assets: Resources owned or held by the District that have monetary value. Availability Fees: The District levies charges each year in developed areas to be used for general purposes for construction of facilities, and in undeveloped areas to provide a source of funding for planning, mapping, and preliminary design of facilities to meet future development. Current legislation provides that any availability charge in excess of $10.00 per acre shall be restricted only for the purpose of constructing facilities in the improvement district for which it was assessed. Betterment Fees: In addition to other applicable water rates and charges, certain water customers pay a fee based on water service zone or improvement district. These are restricted for the use in the area where they are collected and may be used for the construction and maintenance of facilities. Betterment Fees for Maintenance: The Operating Budget earns betterment fees for maintenance work performed on infrastructure within special betterment zones, where fees are collected for the construction and maintenance of these specific assets. Capacity Fee: A connection fee is charged when a new water meter is placed into service. This fee is based on the estimated construction cost of expansion of the system to meet the needs of all future customers. This fee covers the cost including, but is not limited to, planning, design, construction, and financing of expansion of the system. Capacity Fee Revenues: These fees are earned by the Operating Budget as the Engineering Department supports expansion functions. 180 Glossary Capital Budget: The portion of the annual budget that appropriates funds for the purchase of capital equipment items and capital improvements. These expenditures are separated from regular operating items, such as salaries, utilities and office supplies. The Capital Budget includes funds for capital equipment purchases over $10,000, such as vehicles, furniture, machinery, microcomputers and special tools or $20,000 for infrastructure related items, which are distinguished from operating items according to their value and projected useful life. Capital Equipment: Fixed assets such as vehicles, marine equipment, computers, furniture, technical instruments, etc. which have a life expectancy of more than two years and a value over $10,000 or $20,000 for infrastructure related items (this may not extend useful life of the infrastructure, but without it, the whole asset is rendered useless). Capital Improvement Program: A long-range plan of the District for the construction, rehabilitation and modernization of the District-owned and operated infrastructure. CWA: The County Water Authority was organized in 1944 under the State County Water Authority Act for the primary purpose of importing Colorado River water to augment the local water supplies of the Authority's member agencies. The Authority purchases water from MWD which imports water from the Colorado River and the State Water Project. Debt Service: The District's obligation to pay the principal and interest of bonds and other debt instruments according to a predetermined payment schedule. Desalination: The removal of dissolved minerals (including salts) from seawater or brackish water. Engineered water desalination processes, which produce potable water from seawater or brackish water, have become important because many regions throughout the world suffer from water shortages. Expenditures/Expenses: These terms refer to the outflow of funds paid or to be paid for an asset, goods or services obtained regardless of when actually paid for. (Note: An encumbrance is not expenditure). An encumbrance reserves funds to be expended in a future period. Fiscal Year: Twelve-month term designating the beginning and ending period for recording financial transactions. The District has specified July 1 to June 30 as its fiscal year. Grants: Contributions or gifts of cash or other assets from another governmental agency to be used or expended for a specified purpose, activity, or facility. Capital grants are restricted by the grantor for the acquisition and/or construction of fixed assets. Operating grants are restricted by the grantor for operating purposes or may be used for either capital or operating purposes at the discretion of the grantee. 181 Glossary Interest Income: Earnings from the investment portfolio. Per District Policy Number 25, interest income will be allocated to improvement districts each month based upon each fund’s prior month-ending balance. Reserve Fund: The District maintains Reserve Funds per the District’s policy for both designated and restricted balances. Designated Reserve Funds are “general use” funds designated by the Board. Restricted reserves are those that are legally set aside for a particular purpose and cannot be used for any other purpose. Water Capacity Fees: Charges paid by customers to connect to a District water system for potable or recycled water service. Fees are determined by multiplying the demand factor for the meter size by the total of the District-wide capacity fee and applicable zone charge 182 AF Acre-Foot/Feet AMR Automated Meter Reader/Reading APCD Air Pollution Control District ASCE American Society of Civil Engineers AWWA American Water Works Association CEQA California Environmental Quality Act CIP Capital Improvement Program CMAA Construction Management Association of America CSI California Solar Initiative CWA County Water Authority (San Diego) FCF Flow Control Facility FY Fiscal Year GAAP Generally Accepted Accounting Principles GIS Geographic Information System GPS Global Positioning System HWD Helix Water District ID Improvement District IID Imperial Irrigation District IMS Infrastructure Management System IRP Integrated Water Resources Plan LOPS Lower Otay Pump Station MBR Membrane Bioreactor MG Million Gallons MGD Million Gallons per Day MWD Metropolitan Water District O&M or O/M Operations and Maintenance OIS Otay Information System PB Pacific Bay PL Pipeline PS Pump Station RWCWRF Ralph W. Chapman Water Recycling Facility SANDAG San Diego Association of Governments SCADA Supervisory Control and Data Acquisition SDCWA San Diego County Water Authority SVSD Spring Valley Sanitation District VCP Vitrified Clay Pipe WD Water District WRMP Water Resources Master Plan WTP Water Treatment Plant List of Acronyms 183 Index At-A-Glance 2 Awards 6 Capital Facility Projects 39-84 Capital Improvement Program Narrative 16-17 Capital Purchases Budget 30-31 Capital Purchase Projects 159-172 CIP Budget Calendar 11 CIP Budget Guide 1 CIP Budget Process 12-13 CIP Funding Source and Category 24 CIP Justification and Impact on Operating Budget 27 CIP Project Index 37-38 CIP Project Schedule 28-33 CIP Project Sheet Description 35-36 CIP Projects 25-26 CIP Projects in Construction 19-22 CIP Reserve Funds 23 Current Economic Conditions 7 Demographics 9 Developer Reimbursement Projects 173-178 Financial Awards 4-5 General Information 3 Glossary 180-182 Index 184 Letter of Transmittal ii-vi List of Acronyms 183 Major CIP Projects 18 Organization Chart 10 Replacement/Renewal Projects 85-172 Resolution No. 4195 14-15 The Future 8 Water Meter Capacity Fees 179 184