HomeMy WebLinkAboutCapital Improvement Program Budget FY 2008-2013
ADOPTED
CAPITAL BUDGET
FISCAL YEARS 2008-2013
Board of Directors
Gary Croucher – President, Division 3
Jose Lopez - Vice President, Division 4
Jaime Bonilla - Treasurer, Division 2
Larry Breitfelder - Division 1
Mark Robak - Division 5
Management
Mark Watton - General Manager
German Alvarez - Assistant General Manager, Finance and Administration
Manny Magaña - Assistant General Manager, Engineering and Operations
Joseph R. Beachem - Chief Financial Officer
ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET
FISCAL YEARS 2008-2013
TABLE OF CONTENTS
Page
Letter of Transmittal ii
GENERAL INFORMATION
Budget Guide 1
Otay Water District At-A-Glance 2
General Information 3
Awards 4
Current Economic Conditions 8
The Future 9
Demographics 10
Organization Chart 11
Budget Calendar 12
Budget Process 13
Resolution No. 4097 15
CAPITAL BUDGET SUMMARY
Capital Improvement Program Budget Narrative 16
Major CIP Projects 18
Flagship CIP Projects Completed 19
Flagship CIP Projects in Construction 21
Flagship CIP Project in Design 23
Progress on Major Projects 24
CIP Reserve Funds 25
CIP Funding Source and Category 26
Capital Improvement Program 27
CIP Justification and Impact on Operating Budget 29
CIP Project Schedule 31
Capital Purchases Budget 33
CIP PROJECTS
CIP Project Sheet Description 34
CIP Project Index 37
Capital Facility Projects 39
Replacement/Renewal Projects 119
Capital Purchase Projects 153
Developer Reimbursement Projects 167
APPENDIX
Water Meter Capacity Fees 203
Glossary 204
List of Acronyms 210
Index 214
i
September 1, 2007
Honorable Board of Directors
Otay Water District
I am pleased to present the Otay Water District Adopted Operating and Capital Budget for Fiscal
Year 2007-08. With the District’s mission to provide safe and reliable potable and recycled
water and sewer services, there is an emphasis on water resources, system reliability, and new
maintenance requirements. This year’s budget establishes the management plan to finance all of
the District’s services and programs during the 2008 Fiscal Year.
The District was formed in 1956 to serve as a public water and sewer agency, authorized as a
California special district by the State Legislature under the provisions of the Municipal Water
District Act of 1911. Its ordinances, policies, taxes, and rates for service are set by five
Directors, elected by voters in their respective divisions, to serve staggered four-year terms on its
Governing Board. The District is a “revenue neutral” public agency, meaning that each end-user
pays his or her fair share of the District’s costs of water acquisition and the operation and
maintenance of the public water and sewer facilities.
Since the District was formed in1956, it has grown from a
handful of customers and two employees to become an
organization operating a network with more than 763 miles
of pipelines, 42 reservoirs, a sewer treatment plant, and now
owns and operates one of the largest recycled water
distribution networks in San Diego County. The character of
the service area has also changed from predominantly dry-
land farming and cattle ranching, to businesses, high-tech
industries, and large master-planned communities.
Today, the District provides water service to nearly 47,030
potable and 585 recycled customers within approximately
125 square miles of southeastern San Diego County. In the
past, all of the potable water purchased by the District was
purchased from the San Diego County Water Authority
(CWA) who in turn purchases water from the region’s water
importer, the Metropolitan Water District of Southern California. Last year, the District began
purchasing raw water from CWA. The Otay Water District contracted with the City of San
Diego to treat this raw water giving the District a new source of potable water. There are ongoing
negotiations with the City of San Diego to expand water treatment services in the future through
a new connection. By taking raw water through CWA’s system there is increased reliability of
water supplied to the District.
ii
The District also owns and
operates a wastewater collection
and recycling system to provide
public sewer service to
approximately 4,630 homes and
businesses (or 6,620 Assigned
Service Units) within portions of
the communities of La Mesa,
Rancho San Diego, El Cajon,
Jamul, and Spring Valley.
Recycled water from the Ralph
W. Chapman Water Recycling
Facility (RWCWRF) is used to irrigate golf courses, schools, public parks, roadway landscapes,
and various other approved uses in eastern Chula Vista. The RWCWRF project is capable of
reclaiming wastewater at a rate of 1.3 million gallons per day.
On June 1, 2007, the District dedicated its new Supply Link Project connecting its recycled water
system to San Diego’s South Bay Water Reclamation Plant taking about six million gallons a
day of recycled water for irrigation purposes; this allows more potable water to be available for
human consumption. The purchase of this water allows the District to receive recycled financial
incentives from both MWD and CWA which help to offset the investment in capital necessary
to make this new source of water a reality.
BUDGET SUMMARY
For the first time in the District’s history, the fiscal year budget exceeds $100 million, with 2008
operating expenditures of $66.2 million and capital expenditures of $34.5 million. The District’s
goal is to provide the most effective and efficient service possible while maintaining
affordability of the water supply for the community.
The District’s operating expenditures are from its three major sectors: water, reclamation, and
sewer. Revenues from potable and recycled water for Fiscal Year 2008 are projected to be
$63,361,100 about $7.3 million (12.9%) greater than Fiscal Year 2007. Water sales are expected
to increase as a result of the slowing but continuing growth occurring within the District’s
service area. This growth should add over 1,030 new customer accounts and increase the
District’s assets by approximately $35 million for the year.
Significant aspects of the Operating Budget are:
• A balanced budget meeting the goals of the Strategic Plan.
• An updated a six-year Rate Model to ensure sound financial planning and reserve levels.
• Implemented rate increases in potable and reclaimed water and sewer. This included
pass-through rate increases from CWA, City of San Diego, and County of San Diego who
raised costs to the water and sewer customers.
• Of San Diego County’s 23 water agencies, Otay’s water rate is the eighth-lowest and
below the county-wide average.
Current Sources of Water
77%
12%
3%
8%
Imported Potable
Imported Raw Locally
Treated
Recycled Produced
Recycled Purchased
iii
• Issued $42 million in debt in Fiscal Year 2007 to fund the construction of new facilities,
and replacement or enhancement of existing facilities.
• Funding for the six million gallons per day recycled water purchase agreement with the
City of San Diego.
• Increased credits from MWD and CWA for recycled water purchases from the City of
San Diego.
• Expanded residential, landscape, and commercial water conservation programs.
• Funding the fifth year of a Five-Year Labor Agreement ending in Fiscal Year 2008.
The projected operating cost for salaries and benefits is $15.6 million, which is an increase of
$988,100 (6.8%) compared to Fiscal Year 2007. The increase in labor is predominately the
result of negotiated pay and benefit increases.
Estimated growth totaling 1,030 potable and recycled water accounts will bring the new
customer count to 48,030 potable and 615 recycled accounts by the end of Fiscal Year 2008, this
number of accounts equates to approximately 75,300 equivalent dwelling units (EDUs). The
ultimate population projection of 277,000 will total to an estimated 114,000 EDUs and an
average annual water demand of approximately 56 million gallons per day (MGD). To
accommodate this growth, the District will need to invest an estimated $500 million in capital
assets before ultimate build-out is realized. The Fiscal Year 2007-08 Capital Budget consists of
82 projects and a budget of $34.5 million. The budget emphasizes long-term planning for on-
going programs while functioning within fiscal constraints and population growth.
The District has begun to address the
transformation from a growth-centric to a
maintenance-based organization.
Developer fees support growth but
replacement and maintenance is supported
by rates and operating expenses. Otay has
been very successful in managing growth
and now needs to focus on managing long-
term maintenance and replacement of its
relatively new but aging infrastructure.
Time
STRATEGIC PLAN
To guide operations and planning efforts during this time of sustained growth, in 2001, the
District began developing a Strategic Plan. This plan was designed to address the unique
challenges and opportunities resulting from growth. It would also guide the District as it strives
to develop the necessary infrastructure and operational practices to perform its primary business
while ensuring that quality customer service and competitive rates are maintained.
The first multi-year Strategic Plan was adopted by the Board of Directors in 2002. Each year,
the Board of Directors reviews and updates the plan. While the first plan guided the District
through a period of record growth, the updated plan using a balanced scorecard method, looks
forward to a time when the majority of the requisite physical infrastructure is in place and the
iv
District begins to transform from a growth-centric entity to a maintenance-based organization.
The District has been very successful managing growth and recognizes that continued success is
predicated on developing reliable, long-term, water supplies as well as managing long-term
maintenance and replacement of its infrastructure. (A summary of the Balanced Scorecard is
provided on pages 8-12.)
One key to addressing the challenges is to capitalize on the significant investment that has been
made to implement an integrated information system. With the Otay Information System in
place, the District has focused on business process improvement utilizing best-in-class
technology. Other Strategic Plan objectives include: securing additional water sources,
continuing expansion of potable and recycled water networks, expanding use of recycled water,
and continuing efforts to promote conservation.
The current Strategic Plan identifies how the District needs to change in order to meet future
challenges and responsibilities. The plan is focused on all areas of the agency and describes
through cascading strategies, goals, and objectives, how it will achieve the desired changes.
Major themes in the updated plan are: 1) the movement toward improvement of maintenance
business practices so that the life of assets can be extended, 2) the development of improved and
more precise financial information to assist in management decisions, 3) the improvement of
customer service through enhanced customer knowledge and contact, and 4) the building of
critical assets on time and budget. As noted, the plan calls for the rapid adoption of
technological systems and the review of business practices that will yield increased productivity.
Part of the plan is a set of detailed performance measures which monitor the quarterly
productivity of the agency. This mix of long-term objectives and short-term measures of
productivity focuses the District on change while maintaining a high quality of customer service.
Putting the Strategic Plan to Work
Using the Strategic Plan as a guide and with the Board of Directors support, the District has been
able to put into place many substantial improvements. Some of the most significant
accomplishments are the integrated information system, the GIS system, and numerous policy
and procedure improvements. These accomplishments, along with the forward thinking
perspective of the District, paved the way for a thorough and persuasive presentation to two
rating agencies resulting in the positive outcome of a bond rating upgrade for Otay Water
District from an A+ to an AA-. Putting the Strategic Plan to work has resulted in operational
savings and in the case of the bond rating it has resulted in approximately $1.5 million of interest
expense savings.
Water Resources
The Strategic Plan drives advances in every aspect of District operations. For instance, the
Strategic Plan called for updating of the Urban Water Management Plan (UWMP) which was
completed in December 2005. The UWMP serves as a long-range planning document for water
supply and demand, and provides an overview of the District’s water supply and usage, recycled
water, and conservation programs. The UWMP works to ensure the District always has the
water resources it needs to meet the demands of a growing community.
v
Last year the District completed an
Integrated Water Resources Plan
(IRP). The mission of the IRP is to
find the optimal mix of imported
water, local supplies, and conservation
efforts to meet projected ultimate
supply requirements in a cost-effective
manner while also incorporating
environmental impacts,
implementation risks, and other
factors. The planning objectives are to
maintain affordability, meet water
quality standards, achieve supply reliability, increase system flexibility, increase supply
diversity, and address environmental and institutional constraints. The IRP identifies and
evaluates all potential water resource supply opportunities to arrive at a recommended diverse
water supply portfolio. The water supply portfolio will provide a strategic approach and focused
direction to be incorporated into the water resources master plan and the Capital Improvement
Program for the development of sufficient water supply to meet the planning objectives for long-
term sustainability. The water supply alternatives include all potential opportunities such as
desalination, groundwater, water transfers, recycled water supply development, and interagency
agreements. In the coming year, the District will begin facilities rehabilitation and replacement
assessment which will define expected capital outlays for future system replacements. This
approach is clearly focused on asset management as a core discipline.
Recycled Water
Included in the UWMP is the agreement with the City of San Diego which allows the District to
purchase recycled water from the City’s South Bay Reclamation Facility. This contract delivers
on average, more than six million gallons per day of recycled water to the District’s growing
population. Recycled water purchased from this facility is used to irrigate golf courses, parks,
open space, road medians, and other commercial processes. Using this resource to address
specific demands has resulted in the District reducing its potable water use by approximately
15%, maximizing the beneficial use of an alternative resource, which makes millions of gallons
per day of potable water available for higher quality and better purposes. On June 1, 2007, the
District dedicated the Supply Link Project connecting the recycled water system to the City of
San Diego’s South Bay Water Reclamation Plant. The District received $3.3 of a $4 million
grant from Proposition 50 and another $2.4 million from the State Water Resources Control
Board (SWRCB) for partial funding of this project.
The Future
The Otay Water District continues to use the
challenges presented by growth to create new
opportunities and new organizational efficiencies.
By utilizing and continuing to refine its Strategic
vi
Plan, the plan has captured the Board of Director’s vision and united its staff in a common
mission. The organization has achieved a number of significant accomplishments based on its
successful adherence to the plan. As a result, the District is poised to successfully continue
providing an affordable, safe, and reliable water supply for the people of its service area.
AWARDS AND ACKNOWLEDGMENTS
Because of the vision and years of hard work that went into the Supply Link Project connecting
our recycled water system to the City of San Diego’s South Bay Water Reclamation Plant, the
San Diego County Taxpayer’s Association awarded the District with the Golden Watchdog of the
Year Award for 2007, the American Society of Civil Engineers presented the District the Award
of Merit, and the WateReuse Association of California named Otay its Utility of the Year.
The Government Finance Officers Association (GFOA) awarded a Certificate of Achievement
for Excellence in Financial Reporting to the Otay Water District for its Comprehensive Annual
Financial Report (CAFR) for the fiscal year ended June 30, 2006. In order to be awarded a
Certificate of Achievement, a government agency must publish an easily readable and efficiently
organized Comprehensive Annual Financial Report. This report must satisfy both generally
accepted accounting principles and applicable legal requirements. In addition, the CAFR
received the Outstanding Financial Reporting Award from the California Society of Municipal
Finance Officers (CSMFO).
The District also received a Distinguished Budget Presentation Award from the GFOA for the
District’s Operating and Capital Budget for Fiscal Year beginning July 1, 2006, as well as three
awards from the CSMFO for Excellence in Budgeting, Excellence in Public Communications,
and Excellence in Capital Budgeting. These prestigious awards recognize conformance with the
highest standards for preparation of state and local government financial reports.
This budget reflects the Board of Directors’ vision for the District, management, and its
employees. We will continue to strive to make improvements in our budget process, including
an extensive review and analysis of projections for revenues, expenditures, capital projects, and
reserves. I would like to thank all of the staff involved in this process for the efforts put forth in
the preparation of this budget to ensure a successful outcome.
To the Board of Directors, we acknowledge and appreciate their continued support and direction
in achieving excellence in financial management.
__
Mark Watton, General Manager
vii
The District views the Capital Improvement Program (CIP) Budget as an essential tool for proper
financial management of the CIP projects. The District manages growth and maintenance of
assets through this program. This CIP budget is developed with input from the various project
managers throughout the organization and is adopted prior to the start of each fiscal year for the
current fiscal year and five additional years. It is designed and presented for the general needs of
the District, its staff, and citizens. It is a comprehensive and balanced financial plan. This plan
features the CIP budget based on demands for services and the impact on the District’s financial
status and future plans. The budget book is divided into the following sections:
General Information
This introductory section contains an overview and general information about the District
including the organization chart and awards received. Also included are the budget calendar, a
description of the budget process, and the resolution adopting the budget.
Capital Budget Summary
The Capital Budget Summary consists of an overview of the District’s Capital Improvement
Program (CIP) including the Water Resources Master Plan (WRMP) which is based on major
assumptions and criteria of the CIP program. Also included are highlights of the major CIP
projects completed, in construction, in design, and in progress. Additionally, this section
contains the CIP reserve funds and funding sources, a six-year listing of CIP project
expenditures, the project justification and impact on the Operating Budget, project schedules and
the capital purchases budget.
CIP Projects
This section contains a project sheet description along with each individual project sheet. These
sheets are developed by the project manager and contain critical information for the management
of these projects. The projects are divided into four categories: Capital Facility Projects,
Replacement/Renewal Projects, Capital Purchase Projects, and Developer Reimbursement
Projects.
Appendix
The last section consists of the Water Meter Capacity Fee Schedule, the Glossary of budget and
financial terms, a List of Acronyms used in this budget book, and an Index.
CIP BUDGET GUIDE
1
HISTORY
The Otay Water District was formed in January 1956 and joined the San Diego County Water
Authority (CWA) in September 1956 to acquire the right to purchase and distribute imported
water throughout its service area. The District is also responsible for the collection, treatment,
and disposal of wastewater from a portion of the northern region of the District. In 1980, the
District started operation of the Ralph W. Chapman Water Recycling Facility (RWCWRF), and
in June, 2007, a new source of recycled water from the City of San Diego was obtained, allowing
Otay Water District to supply 15 to 20 percent of total water demand with recycled water.
MISSION STATEMENT
The District’s mission is to provide safe and reliable water and wastewater services to its
community with innovation, in a cost efficient, water-wise, and environmentally responsible
manner.
SERVICE AREA
The District's boundaries encompass an area of approximately 125 square miles in San Diego
County, lying immediately east of the City of San Diego metropolitan area and running from the
City of El Cajon south to the international border.
GOVERNMENT
The Otay Water District was formed in 1956 to serve as a public water and sewer agency,
authorized as a California special district under the provisions of the Municipal Water District
Act of 1911. The District’s ordinances, policies, taxes, and rates for service are set by five
Directors, elected by voters in their respective geographic division, to serve staggered four-year
terms on its governing board. The District is a “revenue neutral” public agency, meaning that
each end-user pays only their fair share of the District’s costs of water acquisitions and the
operation and maintenance of the public facilities.
ORGANIZATIONAL STRUCTURE
The General Manager reports directly to the Board of Directors, and through two Assistant
General Managers and the District management, oversees day-to-day operations. One Assistant
General Manager oversees the departments of Administrative Services, Finance, Information
Technology and Strategic Planning while the other oversees the Water Operations and
Engineering departments. These and other lines of reporting are shown on the organization chart
on page 11.
OTAY WATER DISTRICT AT-A-GLANCE
2
For Fiscal Year 2008, the District will have a staff of 172.75 full-time equivalent employees
under the leadership of the General Manager. The District provides water service to
approximately 39% of its land area with a population of more than 190,000 people. This
percentage increases as the District's service area continues to grow to ultimate build-out. The
District is projected to deliver approximately 38,500 acre-feet of potable water to about 48,030
potable customer accounts and to ultimately deliver 62,700 acre-feet of potable water to serve
277,000 people or 50,300 accounts. The rate of growth, as projected by the San Diego
Association of Governments (SANDAG) for the Chula Vista area of San Diego County, is
approximately 4.3% per year over the next decade. Using historical data and considering current
economic conditions, staff has moderated this projection to a growth rate of 2.1% for Fiscal Year
2008.
Recycled water from the Ralph W. Chapman Water Recycling Facility (RWCWRF) is used to
irrigate golf courses, schools, public parks, roadway landscapes, and various other approved uses
in eastern Chula Vista. The RWCWRF is capable of reclaiming wastewater at a rate of 1.3
million gallons per day. The District is also in a partnership with the City of San Diego to
beneficially reuse an additional 6,720 acre-feet per year of recycled water beginning in Fiscal
Year 2007. This makes Otay Water District the largest retail provider of recycled water in the
county.
The District also owns and operates a wastewater collection system providing public sewer
service to approximately 4,630 customer accounts within the Jamacha drainage basin. The sewer
service area covers approximately 8,797 acres, which is about 11% of the District’s total service
area. Residential customers comprise 98% of the sewer customer base.
The District was formed in 1956 to serve as a public water and sewer agency authorized as a
California special district in 1956 by the state legislature under the provisions of the Municipal
Water District Act of 1911. Its ordinances, policies, taxes, and rates for service are set by its
Board of Directors.
Since 1956, the District has provided high quality water to an arid region of the southeastern San
Diego County. In 1971, the District constructed a small collection and treatment plant for sewer
in the northern section of the District, and in 1980 the District opened the Ralph W. Chapman
Water Recycling Facility. Finally in 1986, the District found a use for recycled water in the
construction industry for soil compression. For over 50 years, the available supply of water has
helped transform the District service area from a mostly scrub and cactus-covered backcountry
into a wonderful balance of diverse environments.
GENERAL INFORMATION
3
FINANCIAL AWARDS
The Government Finance Officers
Association of the United States and
Canada (GFOA) presented a
Distinguished Budget Presentation
Award to Otay Water District for its
annual budget for the fiscal year
beginning July 1, 2006. In order to
receive this award, a governmental unit
must publish a budget document that
meets program criteria as a policy
document, as an operations guide, as a
financial plan, and as a communications
device.
This award is valid for a period of one
year only. We believe our current budget
continues to conform to program
requirements, and we are submitting it to
GFOA to determine its eligibility for
another award.
The California Society
of Municipal Finance
Officers (CSMFO)
presented Otay Water
District the Certificate
of Award Excellence
in Operating
Budgeting for Fiscal
Year 2006 - 07.
4
FINANCIAL AWARDS
The California Society of
Municipal Finance
Officers (CSMFO)
presented Otay Water
District the Certificate of
Award Excellence in
Capital Budgeting for
Fiscal Year 2006 - 07.
The California Society
of Municipal Finance
Officers (CSMFO)
presented Otay Water
District the Certificate of
Award Excellence in
Public Communications
Budgeting for Fiscal
Year 2006 - 07.
5
AWARDS
The San Diego Taxpayers Association announced that the Otay Water
District’s Supply Link project is the recipient of its 2007 Golden Watchdog
Award.
The Supply Link project redirects millions of gallons of recycled water that
was released each day into the ocean, and instead uses it to irrigate golf
courses, freeway landscapes, and parks in eastern Chula Vista.
6
AWARDS
The Otay Water District has been named the Recycled
Water Agency of the Year for 2006 by the WateReuse
Association of California. This prestigious award
recognizes the District’s commitment to recycled water
use, its extensive recycled water network, and its new
Supply Link Project to connect with the City of San
Diego’s South Bay Water Reclamation Plant.
7
Currently, the District services the needs of a growing population by purchasing water from the
San Diego County Water Authority (CWA). CWA purchases its water from the Metropolitan
Water District of Southern California (MWD) and the Imperial Irrigation District. Otay takes
delivery of the water through several connections of large diameter pipelines owned and
operated by CWA. In Fiscal Year 2007, the District began purchasing raw water from CWA and
having the City of San Diego treat the water at the Lower Otay Pump Station. The District is in
negotiations with the City of San Diego to increase its raw water purchases and treatment in a
new connection called SD17. These new water sources will help take pressure off the potable
system and increase the reliability through diversifying the District’s supply.
For almost as long as it has been delivering potable water, the Otay Water District has collected
and reclaimed wastewater generated within the Jamacha drainage basin and pumped the recycled
water south to the Salt Creek basin where it is used for irrigation and other non-potable uses.
However, the demand for recycled water out-paced the supply, requiring the District to
supplement the limited supply of recycled water with potable water. Through the new agreement
with the City of San Diego, the District has discontinued supplementing its recycled demand
with potable water. Once again, this decreases the demand on the potable supply and increases
the reliability of the District’s supply.
The District’s sewer service area is growing at a slow but steady rate of approximately 1.2%
each year. Most of this growth is from small development projects or homeowners converting
their septic system into sewer because of environmental issues.
The District’s service area is in one of the fastest growing regions in the nation. During the past
decade, the population of the service area has nearly doubled. The phenomenal growth has
slowed slightly in the past few years, and is continuing at a slower pace. It is estimated that the
District is currently serving approximately 190,000 residents. In just the past five years, the
District has added more than 7,600 new customer connections. This is reflected internally as the
District’s Development Services Department approved on average 35 permits per month, and
sold 800 water meters in Fiscal Year 2006-2007.
CURRENT ECONOMIC CONDITIONS
8
The Otay Water District continues to use the challenges presented by growth to create new
opportunities and new organizational efficiencies. By utilizing and continuing to refine its
Strategic Business Plan, it has captured the Board of Director’s vision and united its staff in a
common mission. The organization has achieved a number of significant accomplishments
based on its successful adherence to its Strategic Business Plan. The Otay Water District is not
only poised to continue successfully providing an affordable, safe, and reliable water supply for
the people of its service area, but is set to reap the rewards of greater efficiencies and economies
of scale.
2326
1397
835 869
1030
1227
1392 1529
1795 1995
-
500
1,000
1,500
2,000
2,500
FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13
METER SALES
Actual Projected
The Engineering Department projects that over the next six years the District will sell another
8,960 meters. The San Diego Association of Governments (SANDAG), the regional planning
agency, shows a slowing of growth for the City of Chula Vista after 2010, and an increase in
growth in the unincorporated areas of the region through 2020.
THE FUTURE
9
The Otay Water District boundaries shown in the chart below encompass an area of
approximately 125 square miles in San Diego County, located immediately east of the City of
San Diego metropolitan area and running from the City of El Cajon south to the international
boarder.
The San Diego Association of Governments (SANDAG), the regional planning agency, creates
and maintains a tremendous quantity of demographic, economic, land use, transportation and
criminal justice information about the San Diego region. The demographic data includes
population characteristics like age, education, and employment. Because of the overlapping of
Otay’s service area with the cities of Chula Vista, La Mesa, El Cajon, and the unincorporated
areas of Spring Valley and Jamul, the following demographic data is from the City of Chula
Vista as it most closely represents the District.
The population of Chula Vista has grown from 83,927 in 1980, to 135,136 in 1990, to 173,556 in
2000, and in 2006 the population reached 223,423. This represents an increase of 139,496 in the
past 26 years or a 166.2% increase, which correlates to the Districts rapid growth for the same
period.
The racial make up of Chula Vista is 50% Hispanic, 29% White, 13% Asian, 4% Black, and the
remaining 4% is all other groups. The median household income for Chula Vista was $68,497 in
2006, and 97% of Chula Vista’s housing units were occupied.
DEMOGRAPHICS
10
ORGANIZATION CHART
BOARD OF DIRECTORS
GENERAL MANAGER
FINANCEADMINISTRATIVE
SERVICES INFORMATION
TECHNOLOGY
AND STRATEGIC
PLANNING
ENGINEERING WATER
OPERATIONS
Controller and
Budgetary Services
Treasury and
Accounting
Services
Customer
Service
Payroll and
Accounts Payable
Human
Resources
Purchasing and
Facilities
Safety and Risk
Administration
Water
Conservation
IT
Application
Public Services
Construction
Survey
Environmental
Water System
Operations
Utility
Maintenance/
Construction
Collection/
Treatment/
Recycle
Operations
GIS
ASSISTANT GENERAL MANAGER ASSISTANT GENERAL MANAGER
IT
Operations Water Resources
Design
Planning
11
Each year, the Engineering Department prepares budget instructions for distribution to the
departments. These instructions give direction and deadlines for each phase of the CIP
budgeting process. The CIP Budget Process is explained on pages 13 and 14.
January 29, 2007 Budget workbooks and instructions for the Operating and Capital Budget
are distributed to departments.
February 1, 2007
to
February 16, 2007
Departments begin CIP Budget Process which includes:
• Review existing FY 2006 CIP projects.
• Remove any CIPs that are complete or will not be budgeted in
the CIP budget the next six years.
• Estimate the total project-to-date expenditures through 6/30/07
for each CIP.
• Adjust the annual amount for the remaining CIPs when
appropriate and include justification for the changes to each
year’s changes.
• Develop CIP project cost and schedules, unless more specific
information is available.
• Submit new CIP projects for consideration.
March 7, 2007 Engineering Department reviews all CIP budget requests with Assistant
General Manager and adjusts, if necessary.
March 14, 2007 Engineering reviews and prepares CIP budget and submits to Finance for
review and to incorporate into rate model to determine proposed rates.
March 27, 2007 CIP budget presented to the General Manager for review and comments.
April 18, 2007 General Manager performs preliminary review of budget.
May 15, 2007 Final review of proposed budget and rates is done by the General
Manager.
May 29, 2007 Board of Directors adopts Fiscal Year 2008 Operating and Capital
Budget.
CIP BUDGET CALENDAR
12
The District has integrated the Capital Improvement Program (CIP) Budget and the Operating
Budget. These budgets are developed based on the District's Water Resources Master Plan and
Strategic Business Plan. Appropriate budget amounts are determined by using the historical data
of operations, growth, developers' input, SANDAG projections, and economic outlook. The
District is accounted for and budgeted as an enterprise fund and conforms to the guidelines of
generally accepted accounting principles (GAAP).
To assure reliable, high-quality service to the growing customer base, the District has committed
to a number of long-range strategies that drive the budgeting process. The strategies and
assumptions used to develop the District's integrated budget are:
• an average projected long-term growth rate of 2%
• pass-through rate increases for costs imposed on the District by the wholesale
water providers
• to accurately project capital budget needs (including replacement needs)
• reserve funding in accordance with the Reserve Policy to meet future growth
demands
• to fund Strategic Plan initiatives categorized into the Balanced Scorecard
perspectives
• avoid rate spikes by leveling rate increases over a six-year period
The Engineering Department issues budget instructions for the CIP budget process. Each
project manager receives a report of year-to-date project expenses and then estimates cost to the
end of the fiscal year, plus future costs, including inflation, to complete the project. Costs are
adjusted for scope changes as well as construction cost increases. Engineering then compiles the
CIP Budget and submits it to the Assistant General Managers and the General Manager for
review prior to presentation to the Board of Directors.
Once all of these budgets have been calculated, the Finance Department inputs all of the
operating revenues and expenses, CIP expenses, reserve funding, and reserve levels into the
District’s Rate Model. Inflators for cost and volume changes are input into the Rate Model and
cost and rates are calculated for the current fiscal year plus five subsequent years. Using this
comprehensive modeling tool, the District is able to smooth future rate increases, determine
when debt should be issued, and monitor all of the reserve levels in accordance with the Reserve
Policy.
In the spring, the Strategic Plan is presented to the Board of Directors for adoption. This is
followed by the Finance and the Engineering Departments presenting to the Board of Directors
their recommendations at a special budget meeting in May of each year. The adoption of the
Strategic Plan and budget on an annual basis gives the District its direction for the following
fiscal year.
CIP BUDGET PROCESS
13
During the year, each project manager receives monthly budget and cost reports on their
assigned CIP projects. These reports are essential to monitor and control costs. As events occur
or conditions change, modifications to or deviations from the original budget may be necessary.
In the event the General Manager determines that an emergency exists which requires immediate
action, he may transfer appropriation within the budget allocations, or request that the Board of
Directors increase the current budgeted funds.
All CIP budget adjustments and requests are submitted to the Engineering Department. The
budgets are reviewed for accuracy, categorized into the appropriate project types and funding
sources and then prioritized based on need and timing of projects. Projects are reviewed to see if
any grant funding is available, and if so, estimated amounts are included as a funding source to
these projects.
Engineering submits the consolidated CIP list to the Assistant General Managers and General
Manager for review and approval. After any necessary adjustments, the CIP budget is submitted
to the Board of Directors for approval each fiscal year along with the Operating Budget.
The Budget Report is intended as a financial guide and may be modified by the Board of
Directors during Fiscal Year 2008.
14
15
The District provides water service to a population of approximately 190,000 which is
expected to ultimately increase to 277,000. The growth rate projected by the San Diego
Association of Governments (SANDAG) and incorporated in the Water Resources Master Plan
is nearly 2.7% per annum for the next 10-15 years. However, based on current economic
conditions, staff is projecting a 2.1% growth rate in population and equivalent dwelling units
(EDUs) for Fiscal Year 2008. The EDU is the demand created by a typical single-family
dwelling requiring a 3/4" water meter. A business creates a demand equivalent to several
single-family dwellings, thus the term equivalent dwelling unit. Presently, our projected
48,650 customer accounts equate to a projected 75,301 EDUs. The ultimate population of
277,000 will result in an estimated 114,000 EDUs and an average annual water demand of
approximately 56 million gallons per day (MGD).
To accommodate this growth requires that the District invest $500 million in capital assets
through ultimate build-out. The Fiscal Year 2008 Capital Budget is $34.5 million and the five-
year Capital Improvement Program (CIP) totals $157 million. A separate CIP Budget
Notebook contains the descriptions, justifications, expenditures, and funding for all the
identified projects to ultimate build-out.
Assumptions and Criteria
The Water Resources Master Plan was based on several major assumptions and design criteria
as follows:
1. Utilizing historical water demands for each land use type in the District to calculate future
demands;
2. Using maximum day peaking factors that vary with demand level;
3. Utilizing land use as planned by the City of Chula Vista;
4. Providing ten days of emergency water supply through a maximum of five days in covered
reservoirs and a minimum of five days from interconnections with adjacent agencies;
5. Inclusion of emergency operational storage to meet the five-day covered storage
requirement into the ten-day outage supply requirement.
In summary, the CIP is developed based on the District's Water Resources Master Plan,
incorporating historical data, growth, developers' input, SANDAG projections, and long-term
economic outlook.
Justification for Project and Impact on Operating Budget
The justification for each project is determined by whether it is required due to growth
(Expansion), improvements or upgrades (Betterment), or to replace an existing asset
(Replacement). As these projects are completed and placed into service, there may be an
impact on the Operating Budget by increasing cost in the areas of maintenance, energy or
chemicals as shown on the justification and impact pages in this section.
CAPITAL IMPROVEMENT PROGRAM
16
Capital Purchases and Facilities
This year, all capital expenditures are in the CIP. This includes capital facilities and capital
purchases. Capital purchases are non-recurring operating expense items for District-wide use
that cost more than $10,000 each and have an estimated useful life of two years or more. The
Capital Purchase Projects include Vehicle, Office Equipment and Furniture, and Field
Equipment purchases, the details of which can be found on page 223. Capital facility projects
are items that exceed $10,000 or $20,000 for infrastructure related items and have a useful life
of at least two years.
The Capital Improvement Program (CIP) projects identified are prioritized based on the
following criteria:
1. Safety, restoration of service, immediate obligation, Board directed or critical system need.
2. System upgrades or requirements to maintain system reliability in the next few fiscal years.
3. Need to meet the future growth of the system.
4. Project requirement may be reduced in capacity or may have low probability of need in the
future.
The Capital Improvement Program includes the following three categories of improvement
projects:
Expansion
Facilities required to support new or future users which are funded from capacity fees.
Betterment
Facilities required because of inadequate capacity or new requirements that benefit existing
users and funded from availability and betterment fees.
Replacement
Facilities required to renew or replace existing facilities that have deteriorated or have
exceeded their useful life and are funded from user rates.
Capital Improvement Projects
The 2008 Fiscal Year CIP Budget contains 82 projects. The cost of the work planned for
Fiscal Year 2008 is $34.5 million. Of the 82 projects planned for Fiscal Year 2008, 27 are
designated as reimbursable projects, totaling $1.5 million. These projects are built by
developers and reimbursed by the District.
CAPITAL IMPROVEMENT PROGRAM
17
The following shows how the $34.5 million of projects are broken down into four categories:
1. Capital facilities $ 24.9 million
2. Replacement or renewal projects $ 6.7 million
3. Capital purchase projects $ 1.4 million
4. Developer reimbursement projects $ 1.5 million
The Five-Year CIP and Fiscal Year 2008 Capital Budgets
are consistent with the District's Water Resources Master
Plan, current capacity fees, and the District's strategic
financial objectives.
MAJOR CIP PROJECTS
18
Key Component:
12,000 GPM (17.3 MGD) pump station delivering recycled water from
450-1 Reservoir to the 680 and 944 recycled water pressure zones.
Schedule:
Construction started in late November 2005. Original contract
completion date was April 1, 2007.
Cost: The construction project budget was $18.3 million and the amount spent
to complete this project was $17.7 million.
Significant
Issues:
Construction was accepted in June 2007 and the pump station is in use.
FLAGSHIP CIP PROJECTS COMPLETED
450-1 Reservoir /
680-1 Pump Station
Reservoir and the Pump
Station were completed in
April 2007.
19
Key
Component:
Approximately 6 miles of 30” pipeline for recycled water from City of
San Diego’s South Bay Water Reclamation Plant (SBWRP) to Otay’s
450-1 Reservoir and 680-1 Pump Station.
Schedule:
Full Notice to Proceed given on September 28, 2005. Contract
completion date was December 23, 2006.
Cost:
The construction project budget was $23.6 million and the amount spent
to complete this project was $22.9 million.
Significant
Issues:
Construction was accepted in May 2007 and the pipeline is in use.
30” Recycled Water
Pipeline Project
Project was awarded
for construction in
May 2005. This
pipeline will deliver
recycled water from
South Bay to the 450/
680 Reservoir and
Pump Station. Project
is expected to be
completed in the fall
of 2006.
20
SR-905 Utility Relocations
Project started on
September 7, 2006 and is
expected to be completed in
the winter of 2007. This
project includes the
relocation of three pipelines
crossing under SR-905 and
the reconditioning of two
seismic valve vaults.
Telegraph Canyon Road
Paving Project
Project started on June 6,
2007 and is expected to be
completed in early August
2007. The project includes
numerous trench line
pavement rehabilitations
along Telegraph Canyon
Road and repaving
excavations at the 980-2
Pump Station site.
FLAGSHIP CIP PROJECTS IN CONSTRUCTION
21
Key Component:
Construction for two (2) 10-MG prestressed circular reservoirs and
associated piping.
Schedule:
Notice to Proceed was issued in January 2007. Project completion date
is expected to be in November 2008.
Cost: The construction project budget is 29% spent - $7.3 million out of a
total budget of $24.9 million. The total project budget is $29.5 million,
of which $9.4 million or 32%, has been spent.
Significant
Issues:
640-1; Installed 42” outlet piping and poured concrete encasement
under first reservoir. 640-2; Placed 10’ surcharge over the engineering
fill of the second reservoir. Began laying the inlet and outlet piping.
640-1 and 640-2
Reservoirs Project
(20.0 MG)
This project was
awarded to Pacific
Hydrotech and was
started in January
2007. Expected
completion is late
2008. Project consists
of two 10 million
gallon circular
concrete reservoirs,
11,000 feet of large
diameter pipe, several
valve and control
vaults and demolition
of the 520-1 Concrete
Reservoir.
Site Grading
Inlet/Outlet Valve Vault
22
36-Inch Pipeline From FCF No. 14 to Regulatory Site Project
Key
Component:
Approximately 5 miles of 36-Inch pipeline for potable water from Otay’s FCF
No. 14 to the Regulatory Site.
Schedule:
Preparing preliminary design report and reviewing alternative alignments.
The construction project budget is $18.5 million.
Cost:
Significant
Issues:
District received final draft of the preliminary design report and design is on
schedule.
FLAGSHIP CIP PROJECT IN DESIGN
23
City of San Diego’s Water Treatment Plant, Capacity
Key
Component:
Acquire at least 30 MGD and up to 50 MGD of local treatment capacity from
City of San Diego (City).
Schedule:
Otay Board approved the SD17 POU with the City, SDCWA and Otay. Draft
SD17 Agreement under negotiation.
Cost:
Only staff time has been budgeted; project cost is dependent upon negotiations
outcome.
Significant
Issues:
The City will supply “Surplus Water” from Otay WTP to Otay per the current
1999 Agreement.
The City has an opportunity to obtain a $6,500,000 Matching Proposition 50
Grant for SD17 consisting of a pump station at the Alvarado WTP to pump up
to 60 MGD into SDCWA Pipeline No. 4.SD17 is estimated to cost
$20,000,000. The District desires to acquire 50 MGD capacity. This project
will provide an opportunity to the City to generate revenue from surplus
capacity. For the District, this is an opportunity to save cost on water treatment
while providing an additional source of water supply.
PROGRESS ON MAJOR PROJECT
24
(Thousand $000s) FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 Total
Capacity Fees 7,448$ 8,652$ 9,560$ 9,804$ 13,009$ 13,472$ 61,945$
Debt financing - 29,970 - 26,570 - - 56,540
Grants 2,300 4,550 4,750 1,450 250 250 13,550
Interest 2,771 2,833 2,774 2,847 3,164 2,920 17,310
Betterment Charges 1,056 1,078 1,100 1,123 1,146 1,170 6,673
Temporary Meters 1,204 1,209 1,212 1,215 1,220 1,223 7,283
Availability (Betterment Portion) 558 569 581 593 605 618 3,524
Transfer from General Fund 14,145 6,930 8,335 9,245 11,030 13,555 63,240
Interfund Transfers 1,140 435 144 419 195 181 2,514
Total Sources 30,621 56,227 28,457 53,266 30,619 33,389 232,578
CIP Projects 34,463 38,442 34,769 28,334 29,787 25,723 191,518
Betterment Fees for Maintenance 73 76 78 80 83 85 474
Debt Service 3,331 5,658 6,450 7,754 8,496 8,580 40,268
Developer Services 1,415 1,420 1,425 1,427 1,433 1,437 8,557
Interfund Transfers 1,140 435 144 419 195 181 2,514
Total Uses 40,422 46,031 42,865 38,014 39,993 36,006 243,331
Net Sources (Uses)(9,800)$ 10,196$ (14,408)$ 15,252$ (9,375)$ (2,617)$ (10,753)$
CIP RESERVE FUNDS
The CIP Reserve Funds presentation, shown on the following pages, is designed to provide an understanding of how the
funding of CIPs is expected to financially influence the District over the next six years. The financial impacts are based on
the CIP program and its funding sources, including fund transfers in accordance with the District’s Reserve Policy, and
planned debt issuances. This data is captured in the District’s Rate Model on an annual basis in order to make these
projections.
$3,483
$29,361
$16,931
$1,291
$30,890
$27,791
$1,535
$32,369
$11,660
$1,750
$34,764
$24,302
$1,549
$35,039
$14,853
$2,029
$35,957
$10,838
$0
$10,000
$20,000
$30,000
$40,000
$50,000
$60,000
Th
o
u
s
a
n
d
s
FY09 FY10 FY11 FY12 FY13
Fiscal Year
RESERVE FUND BALANCES
Betterment Replacement Expansion
25
CIP FUNDING SOURCE AND CATEGORY
(Thousands $000s)FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 TOTAL
Expansion 16,600$ 27,040$ 29,764$ 23,273$ 24,507$ 21,683$ 142,866$
Betterment 9,599 6,371 1,259 1,066 1,276 166 19,737
Replacement 8,265 5,032 3,746 3,995 4,004 3,874 28,916
TOTAL 34,463$ 38,442$ 34,769$ 28,334$ 29,787$ 25,723$ 191,518$
(Thousands $000s)FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 TOTAL
Capital Facility Projects 24,901$ 32,441$ 28,777$ 15,180$ 15,350$ 5,800$ 122,449$
Maintenance Projects 6,645 3,581 3,045 3,849 3,845 3,720 24,685
Capital Purchase Projects 1,406 870 320 320 320 320 3,556
Developer Reimbursement Projects 1,511 1,150 1,215 800 800 1,825 7,301
Subtotal 34,463 38,042 33,357 20,149 20,315 11,665 157,991
FY 2009 Through FY 2013 Projects - 400 1,412 8,185 9,472 14,058 33,527
TOTAL 34,463$ 38,442$ 34,769$ 28,334$ 29,787$ 25,723$ 191,518$
$0
$10,000
$20,000
$30,000
$40,000
FY09 FY10 FY11 FY12 FY13
SIX-YEAR CIP BY FUNDING SOURCE
Expansion
Replacement
Betterment
$0
$10,000
$20,000
$30,000
$40,000
FY09 FY10 FY11 FY12 FY13
SIX-YEAR CIP BY CATEGORY
Capital Facility Projects Maintenance Projects
Capital Purchase Projects Developer Reimbursement Projects
26
CIP No. Description FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 Total
CAPITAL FACILITY PROJECTS
P2009 PL - 36-Inch, SDCWA Otay FCF No. 14 to Regulatory Site 1,150$ 9,770$ 6,865$ 45$ -$ -$ 17,830$
P2033 PL - 16-Inch, 1296 Zone, Melody Road - Campo/Presilla 5 185 1,160 470 - - 1,820
P2037 Res - 980-3 Reservoir 15 MG 200 200 800 4,500 7,825 50 13,575
P2038 PL - 12-Inch, 978 Zone, Jamacha, Hidden Mesa, and Chase Upsize and Replacements 980 505 - - - - 1,485
P2040 Res - 1655-1 Reservoir 0.5 MG 1 1 85 700 795 - 1,582
P2129 Groundwater Exploration Program 10 10 15 25 630 1,280 1,970
P2143 Res - 1296-3 Reservoir 2 MG 1,200 1,800 50 - - - 3,050
P2172 PS - 1485-1 Pump Station Replacement 200 1,200 500 - - - 1,900
P2185 Res - 640-1 Reservoir 20.0 MG 15,000 6,000 500 - - - 21,500
P2190 PL - 10-Inch, 1485 Zone, Jamul Highlands Road to Presilla Drive 5 5 120 95 - - 225
P2191 Res - 850-4 Reservoir 2.2 MG 750 1,800 100 - - - 2,650
P2258 PS - Lower Otay Pump Station Phase 1 (9,000 GPM) 50 - - - 2,000 3,670 5,720
P2267 36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations 150 - - - - - 150
P2295 624-1 Reservoir Disinfection Facility, Inlet/Outlet/Bypass and 613-1 Reservoir Demoli 550 - - - - - 550
P2318 PL - 20-Inch, 657 Zone, Summit Cross-Tie and 36-Inch Main Connections - 200 345 - - - 545
P2370 Res - Dorchester Reservoir and Pump Station Demolition - - - 65 70 - 135
P2387 PL - 12-Inch, 832 Zone, Steele Canyon Road - Via Caliente/Campo 270 185 - - - - 455
P2450 Otay River Groundwater Well Demineralization/Development 115 85 800 3,600 400 - 5,000
P2451 Rosarito Desalination Facility Conveyance System 5 5 15 80 95 800 1,000
P2457 Otay Mountain Groundwater Well Development 10 290 6,000 200 - - 6,500
P2460 I.D. 7 Trestle and Pipeline Demolition 20 55 300 - - - 375
P2462 Otay River Demineralization Feasibility Study 200 - - - - - 200
P2463 South Bay Regional Concentrate Conveyance Feasibility Study 25 100 - - - - 125
P2464 San Diego 17 Pump Station and Flow Control Facility 750 7,500 8,000 - - - 16,250
P2465 Regulatory Site Material Storage Bins 30 220 - - - - 250
P2466 Regional Training Facility 100 100 - - - - 200
P2467 San Diego Formation Groundwater Feasibility Study 800 800 - - - - 1,600
R2001 RecRes - 450-1 Reservoir 12 MG 50 - - - - - 50
R2004 RecPS - 680-1 Pump Station (11,500 GPM) 50 - - - - - 50
R2034 RecRes - 860-1 Reservoir 4 MG - 100 395 1,800 1,500 - 3,795
R2053 RWCWRF - R.O. Building Remodel and Office Furniture 305 50 - - - - 355
R2077 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway 50 50 378 1,000 1,500 - 2,978
R2081 RecPL - 20-Inch, 944 Zone, Lane Avenue - Proctor Valley/Pond No. 1 900 300 - - - - 1,200
R2087 RecPL - 20-Inch, 944 Zone, Wueste Road - Olympic/Otay WTP 50 50 2,000 1,400 85 - 3,585
R2088 RecPL - 20-Inch, 860 Zone, County Jail - Roll Reservoir/860-1 Reservoir 50 50 149 1,000 250 - 1,499
R2089 North District Recycled Water Regulatory Compliance 195 - - - - - 195
R2090 MBR Water Recycling Facility Feasibility Study 40 - - - - - 40
R2091 RecPS - 944-1 Pump Station Upgrade 325 - - - - - 325
R2092 Dis - 450-1 Reservoir Disinfection Facility 300 800 - - - - 1,100
S2016 Solar Panel Installation Phase I 10 25 200 200 200 - 635
40 Total Capital Facility Projects 24,901 32,441 28,777 15,180 15,350 5,800 122,449
REPLACEMENT/RENEWAL PROJECTS
P2356 PL - 12-Inch, 803 Zone, Jamul Drive Permastran Pipeline Replacement 420 266 - - - - 686
P2366 APCD Engine Replacements and Retrofits 160 170 180 190 220 - 920
P2382 Safety and Security Improvements 90 90 90 89 - - 359
P2416 SR-125 Utility Relocations 190 - - - - - 190
P2422 Agency Interconnections 300 300 300 300 300 300 1,800
P2440 I-905 Utility Relocations 360 300 - - - - 660
P2441 NG/RAMAR Meter Replacements 100 - - - - - 100
CAPITAL IMPROVEMENT PROGRAM ($1,000s)
The 2008 Fiscal Year CIP Budget contains 82 projects. The costs for the work planned for Fiscal Year
2008 is $34.5 million. Of the 82 projects planned for Fiscal Year 2008, 18 are designated as reimbursable
projects with estimated costs of $1.5 million. These projects are built by developers and reimbursed by the
District.
27
CAPITAL IMPROVEMENT PROGRAM ($1,000s)
CIP No. Description FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 Total
REPLACEMENT/RENEWAL PROJECTS
P2447 Information Technology Meter Routing 80 - - - - - 80
P2453 SR-11 Utility Relocations 5 165 125 680 655 670 2,300
P2455 Data Cleansing Project 160 - - - - - 160
P2456 Air and Vacuum Valve Upgrades 520 550 580 600 620 640 3,510
P2458 AMR Manual Meter Replacement 1,250 1,375 1,500 1,650 1,700 1,750 9,225
P2459 Olive Vista Drive Utility Relocations 1,100 - - - - - 1,100
P2468 Finance Department Office Remodel 50 - - - - - 50
R2086 RWCWRF Force Main AirVac Replacements and Road Improvements 670 - - - - - 670
S2012 SVSD Outfall and RSD Replacement and OM Reimbursement 605 365 270 340 350 360 2,290
S2015 Calavo Lift Station Replacement 585 - - - - - 585
17 Total Replacement/Renewal Projects 6,645 3,581 3,045 3,849 3,845 3,720 24,685
CAPITAL PURCHASE PROJECTS
P2282 Vehicle Capital Purchases 210 220 220 220 220 220 1,310
P2286 Field Equipment Capital Purchases 91 100 100 100 100 100 591
P2353 Information Technology System Enhancements and Replacements 365 350 - - - - 715
P2361 Information Technology GIS Enhancements 150 100 - - - - 250
P2363 Information Technology Utility Billing, Data Management, and Financial System 200 100 - - - - 300
P2443 Information Technology Mobile Services 240 - - - - - 240
P2461 Records Management System Upgrade 150 - - - - - 150
7 Total Capital Purchase Projects 1,406 870 320 320 320 320 3,556
DEVELOPER REIMBURSEMENT PROJECTS
P2070 PL - 16-Inch, 980 Zone, Pacific Bay Homes Road- Proctor Valley/Rolling Hills Hydro 550 - - - - - 550
P2121 PL - 16-Inch, 711 Zone, Hunte Parkway - Olympic/EastLake 1 - - - - - 1
P2133 PL - 16-Inch, 711 Zone, EastLake Parkway - Olympic/Birch 1 - - - - - 1
P2164 PL - 20-Inch, 980 Zone, EastLake Parkway - Olympic/Birch 1 - - - - - 1
P2169 PL - 20-Inch, 980 Zone, EastLake Parkway - Birch/Rock Mountain 325 - - - - - 325
P2325 PL - 10" to 12" Oversize, 1296 Zone, PB Road - Rolling Hills Hydro PS/PB Bndy 130 - - - - - 130
P2367 PL - 16-Inch, 980 Zone, Olympic Parkway - East Palomar/EastLake - 850 415 - - - 1,265
P2397 PL - 12-Inch, 711 Zone, EastLake Parkway - Birch/Rock Mountain 175 - - - - - 175
P2414 PL - 12" to 16" Oversize, 803 Zone, Dehesa Road - Dehesa Meadow/OWD Bndy 10 - - - - - 10
P2435 PL - 16-Inch, 711 Zone, Birch Road - La Media/SR-125 30 - - - - - 30
R2031 RecPL - 12-Inch, 944 Zone, EastLake Parkway - Olympic/Birch 1 - - - - - 1
R2033 RecPL - 12-Inch, 944 Zone, Birch Road - La Media/EastLake 50 - - - - - 50
R2040 RecPL - 12-Inch, 680 Zone, Hunte Parkway - Olympic/EastLake 1 - - - - - 1
R2041 RecPL - 8-Inch, 944 Zone, EastLake Parkway - Birch/Rock Mountain 1 - - - - - 1
R2043 RecPL - 8-Inch, 944 Zone, Rock Mountain Road - La Media/SR-125 235 - - - - - 235
R2058 RecPL - 16-Inch, 860 Zone, Airway Road - Otay Mesa/Alta - 300 300 300 300 480 1,680
R2082 RecPL - 24-Inch, 680 Zone, Olympic Parkway - Village 2/Heritage - - 500 500 500 246 1,746
R2084 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media - - - - - 1,099 1,099
18 Total Developer Reimbursement Projects 1,511 1,150 1,215 800 800 1,825 7,301
82 Total - FY 2008 Projects 34,463 38,042 33,357 20,149 20,315 11,665 157,991
12 FY 2009 Through FY 2013 Projects - 400 1,412 8,185 9,472 14,058 33,527
Grand Totals 34,463$ 38,442$ 34,769$ 28,334$ 29,787$ 25,723$ 191,518
28
CIP No. Description J/FS (2)Total FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 Total
P2009 PL - 36-Inch, SDCWA Otay E 8,700$ -$ -$ 4,400$ 8,700$ 9,000$ 9,300$ 31,400$
P2033 PL - 16-Inch, 1296 Zone E 2,200 - - - - 2,200 2,300 4,500
P2037 Res - 980-3 Reservoir E 28,200 - - - - - 28,200 28,200
P2038 PL - 12-Inch, 978 Zone B/R 1,500 - - 1,500 1,500 1,500 1,500 6,000
P2040 Res - 1655-1 Reservoir B 900 - - - - 500 900 1,400
P2143 Res - 1296-3 Reservoir E 3,800 - - 1,900 3,800 3,900 4,000 13,600
P2172 PS - 1485-1 Pump Station B/R 7,400 - - 7,400 7,600 7,800 8,000 30,800
P2185 Res - 640-1 Reservoir E/B 37,600 - - 18,800 37,600 38,700 39,900 135,000
P2190 PL - 10-Inch, 1485 Zone B 400 - - - - 400 400 800
P2191 Res - 850-4 Reservoir E/B 4,200 - - 4,200 4,300 4,400 4,500 17,400
P2295 624-1 Reservoir Disinfect E/B/R 8,400 8,400 8,700 9,000 9,300 9,600 9,900 54,900
P2318 PL - 20-Inch, 657 Zone B 100 - - - 100 100 100 300
P2357 PS - 657-1/850-1 Pump Station B (44,400) - - - - - (44,400) (44,400)
P2370 Res - Dorchester Reservoir B (4,800) - - - - - (4,800) (4,800)
P2387 PL - 12-Inch, 832 Zone B 600 - - 600 600 600 600 2,400
P2447 IT Meter Routing E/R 3,600 - 3,600 3,700 3,800 3,900 4,000 19,000
P2450 Otay River Groundwater Well E 27,900 - - - - - 27,900 27,900
P2457 East Otay Mesa Groundwater E 11,200 - - - - 11,200 11,500 22,700
P2458 AMR Retrofit B/R (226,400) (36,500) (34,500) (34,700) (39,300) (40,400) (41,000) (226,400)
P2464 San Diego 17 PS and Flow Control Facility E 308,200 - - - 308,200 317,400 326,900 952,500
R2001 RecRes - 450-1 Reservoir E 11,800 11,800 12,200 12,600 13,000 13,400 13,800 76,800
R2004 RecPS - 680-1 Pump Station E 170,100 170,100 175,200 180,500 185,900 191,500 197,200 1,100,400
R2034 RecRes - 860-1 Reservoir E 7,500 - - - - - 7,500 7,500
R2077 RecPL - 24-Inch, 860 Zone E 2,700 - - - - - 2,700 2,700
R2081 RecPL - 16-Inch, 944 Zone E 2,700 - 2,700 2,800 2,900 3,000 3,100 14,500
R2087 RecPL - 16-Inch, 944 Zone E 1,500 - - - - 1,500 1,500 3,000
R2088 RecPL - 24-Inch, 860 Zone E 2,400 - - - - 2,400 2,500 4,900
R2091 RecPS - 944-1 Pump Station Upgrade E/B 107,900 - 107,900 111,100 114,400 117,800 121,300 572,500
R2092 Dis - 450-1 Res Disinfection Facility B 10,700 - - 10,700 11,000 11,300 11,600 44,600
Total Capital Facility Projects 704,800$ 153,800$ 275,800$ 334,500$ 673,400$ 711,700$ 750,900$ 2,900,100$
(1)O&M costs include labor and benefits, materials, and overhead.
(2)J/FS - Justification and Funding Source - Some projects have multiple funding sources as indicated by a slash (/):
E - Expansion
B - Betterment
R - Replacement
Note:See pages 27-28 for complete description of CIP projects.
CAPITAL FACILITY PROJECTS
CIP JUSTIFICATION AND IMPACT ON OPERATING BUDGET
As the District grows and constructs new capital assets, the cost to maintain these new assets will be
added to the operating budget as they are brought into service. To determine the cost to maintain these
new assets, the District looks at the cost of maintaining similar assets through the Infrastructure
Management System and financial system. Costs are tracked by three main infrastructure asset groups
of pipes, pump stations and reservoirs, as well as capital purchases and other types. Pipes typically
have only operation and maintenance (O&M) costs associated with them, pump stations have O&M as
well as power cost, and reservoirs have O&M and chemical cost. Each of the capital purchases and
other types has its own unique O&M cost (1).
When the new assets are built or acquired for expansion or betterment, it is assumed that there will be
new operating costs associated with them. Some projects such as the Automated Meter Reading
program actually reduce operating costs through the automation process.
Projected Incremental Operating Expenditures
29
CIP JUSTIFICATION AND IMPACT ON OPERATING BUDGET
CIP No. Description J/FS
(2)Total FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 Total
P2286 Field Equipment Capital Purch R 1,500$ 800$ 2,000$ 4,100$ 8,400$ 17,300$ 35,600$ 68,200$
P2443 IT Mobile Services E/R 18,000 - 18,000 18,500 19,100 19,700 20,300 95,600
Total Capital Purchase Projects 19,500 800 20,000 22,600 27,500 37,000 55,900 163,800
P2070 PL - 16-Inch, 980 Zone E 1,000 - 1,000 1,000 1,000 1,000 1,000 5,000
P2107 PL - 12-Inch, 711 Zone E 1,700 - - - - - 1,700 1,700
P2121 PL - 16-Inch, 711 Zone E 2,900 2,900 3,000 3,100 3,200 3,300 3,400 18,900
P2133 PL - 16-Inch, 711 Zone E 1,900 1,900 2,000 2,100 2,200 2,300 2,400 12,900
P2134 PL - 16-Inch, 711 Zone E 1,000 - - - 1,000 1,000 1,000 3,000
P2164 PL - 20-Inch, 980 Zone E 900 900 900 900 900 900 900 5,400
P2169 PL - 20-Inch, 980 Zone 900 - 900 900 900 900 900 4,500
P2325 PL - 10" to 12" Oversize E 2,300 - 2,300 2,400 2,500 2,600 2,700 12,500
P2367 PL - 16-Inch, 980 Zone E 3,300 - - 1,700 3,300 3,400 3,500 11,900
P2397 PL - 12-Inch, 711 Zone 300 - 300 300 300 300 300 1,500
P2402 PL - 12-Inch, 624 Zone E 1,000 - - - - 1,000 1,000 2,000
P2414 PL - 12" to 16" Oversize E 2,400 2,400 2,500 2,600 2,700 2,800 2,900 15,900
P2435 PL - 16-Inch, 711 Zone E 1,400 - 1,400 1,400 1,400 1,400 1,400 7,000
R2028 RecPL - 8-Inch, 680 Zone 2,400 - - - - 2,400 2,500 4,900
R2031 RecPL - 12-Inch, 944 Zone E 900 900 900 900 900 900 900 5,400
R2033 RecPL - 12-Inch, 944 Zone E 2,100 - 2,100 2,200 2,300 2,400 2,500 11,500
R2040 RecPL - 12-Inch, 680 Zone E 2,900 2,900 3,000 3,100 3,200 3,300 3,400 18,900
R2041 RecPL - 8-Inch, 944 Zone E 1,400 1,400 1,400 1,400 1,400 1,400 1,400 8,400
R2042 RecPL - 8-Inch, 944 Zone E 900 - - - 500 900 900 2,300
R2043 RecPL - 8-Inch, 944 Zone E 1,200 - 1,200 1,200 1,200 1,200 1,200 6,000
R2047 RecPL - 12-Inch, 680 Zone E 1,400 - - - 700 1,400 1,400 3,500
R2058 RecPL - 16-Inch, 860 Zone E 5,400 - - - - - 5,400 5,400
R2082 RecPL - 24-Inch, 680 Zone E 3,100 - - - - - 3,100 3,100
R2083 RecPL - 20-Inch, 680 Zone E 700 - 700 700 700 700 700 3,500
R2085 RecPL - 20-Inch, 680 Zone E 900 - - - - - 900 900
Total Developer Reimbursement Projects 51,400 13,300 23,600 25,900 30,300 35,500 47,400 176,000
Total Operating Budget Cost Impact 775,700$ 167,900$ 319,400$ 383,000$ 731,200$ 784,200$ 854,200$ 3,239,900$
FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 Total
13,700$ 68,700$ 95,900$ 163,700$ 189,700$ 241,900$ 773,600$
144,800 241,000 254,500 524,500 549,100 547,100 2,261,000
9,400 9,700 32,600 43,000 45,400 65,200 205,300
167,900$ 319,400$ 383,000$ 731,200$ 784,200$ 854,200$ 3,239,900$
Operations and Maintenance
Energy
Chemical
Total Operating Budget Cost Impact
Cost Category
CAPITAL PURCHASE PROJECTS
DEVELOPER REIMBURSEMENT PROJECTS
The preceding schedule shows anticipated operating costs associated with each project in the CIP, and
below is a summary of each category of new costs that will be impacted. No additional revenues are
associated with the individual projects, as revenues
Projected Incremental Operating Expenditures
30
ID CIP Task Name Start Finish
Project Category: Capital Facility Projects 7/3/89 6/30/13
1 P2009 PL - 36-Inch, SDCWA Otay FCF No. 14 to Regula 7/3/97 7/30/10
34 P2033 PL - 16-Inch, 1296 Zone, Hillsdale Drive - Campo 7/5/05 6/30/11
2 P2037 Res - 980-3 Reservoir 15.0 MG 7/3/89 6/28/13
3 P2038 PL - 12-Inch, 978 Zone, Jamacha and Hidden Me 7/5/05 3/30/09
4 P2040 Res - 1655-1 Reservoir 0.5 MG 7/6/93 12/30/11
5 P2129 Groundwater Exploration Program 7/4/95 6/30/13
6 P2143 Res - 1296-3 Reservoir 2.0 MG 11/5/01 12/30/09
7 P2172 PS - 1485-1 Pump Station Replacement 7/4/01 7/30/09
8 P2185 Res - 640-1 Reservoir 20.0 MG 11/7/91 2/28/10
9 P2190 PL - 10-Inch, 1485 Zone, Jamul Highlands Road 7/5/05 6/30/11
41 P2191 Res - 850-4 Reservoir 2.2 MG 7/3/03 7/30/09
42 P2258 PS - Lower Otay Pump Station Phase 1 (9,000 G 9/19/97 6/30/13
43 P2267 36-Inch Main Pumpouts and Air/Vacuum Ventilati 7/3/97 6/30/08
10 P2295 624-1 Reservoir Disinfection Facility, Inlet/Outlet/ 7/6/94 6/30/08
46 P2318 PL - 20-Inch, 657 Zone, Summit Cross-Tie and 36 11/5/97 6/30/10
54 P2370 Res - Dorchester Reservoir and Pump Station De 7/5/05 6/30/12
56 P2387 PL - 12-Inch, 832 Zone, Steele Canyon Road - Vi 7/5/05 3/30/09
65 P2450 Otay River Groundwater Well Demineralization/D 7/1/07 6/28/12
66 P2451 Rosarito Desalination Facility Conveyance System 7/4/06 6/30/13
70 P2457 Otay Mountain Groundwater Well Development 7/4/06 6/30/11
73 P2460 I.D. 7 Trestle and Pipeline Demolition 7/2/07 6/30/10
75 P2462 Otay River Demineralization Feasibility Study 7/2/07 6/30/08
76 P2463 South Bay Regional Concentrate Conveyance Fe 7/2/07 6/30/09
77 P2464 San Diego 17 Pump Station and Flow Control Fac 7/2/07 6/30/10
78 P2465 Regulatory Site Material Storage Bins 7/2/07 12/31/08
79 P2466 Regional Training Facility 8/2/06 1/30/09
80 P2467 San Diego Formation Groundwater Feasibility Stu 7/2/07 6/30/09
11 R2001 RecRes - 450-1 Reservoir 12.0 MG 12/1/00 8/29/07
12 R2004 RecPS - 680-1 Pump Station (11,500 GPM) 12/4/00 8/30/08
15 R2034 RecRes - 860-1 Reservoir 4 MG 9/4/06 6/30/12
19 R2053 RWCWRF - R.O. Building Remodel and Office Fu 7/3/97 7/30/08
21 R2077 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate 9/4/06 6/30/12
22 R2081 RecPL - 20-Inch, 944 Zone, Lane Avenue - Proct 7/4/06 8/30/08
26 R2087 RecPL - 20-Inch, 944 Zone, Wueste Road - Olym 9/4/06 9/30/11
27 R2088 RecPL - 20-Inch, 860 Zone, County Jail - Roll Re 9/4/06 9/30/11
28 R2089 North District Recycled Water Regulatory Complia 5/1/07 6/27/08
29 R2090 MBR Water Recycling Facility Feasibility Study 7/4/06 8/3/07
30 R2091 RecPS - 944-1 Pump Station Upgrade 7/2/07 6/30/08
31 R2092 Dis - 450-1 Reservoir Disinfection Facility 7/2/07 6/30/09
81 S2016 Pilot Study Solar Panel Installation 7/4/06 12/30/11
Project Category: Capital Purchase Projects 7/3/96 6/30/13
44 P2282 Vehicle Capital Purchases 12/5/00 6/30/13
45 P2286 Field Equipment Capital Purchases 12/5/00 6/30/13
48 P2353 Information Technology System Enhancements a 7/3/96 6/30/09
90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12 13 1
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Otay WaterDistrict FY 2008 Plus Five Year CIP Project Schedues
This schedule provides the start and finish dates of each project,
including all relevant prior years up through FY 2013.
19
Project: OWD FY 08 CIP ScheduleDate: 9/7/07
31
ID CIP Task Name Start Finish
50 P2361 Information Technology GIS Enhancements 7/5/00 6/30/09
51 P2363 Information Technology Utility Billing, Data Manag 7/5/00 6/30/09
63 P2443 Information Technology Moblie Services 7/5/05 6/30/08
74 P2461 Records Management System Upgrade 7/2/07 6/30/08
Project Category: Developer Reimbursement 7/4/01 6/30/13
35 P2070 PL - 16-Inch, 980 Zone, Pacific Bay Homes Road 7/3/03 6/30/08
37 P2121 PL - 16-Inch, 711 Zone, Hunte Parkway - Olympic 7/3/03 8/30/07
38 P2133 PL - 16-Inch, 711 Zone, EastLake Parkway - Olym 7/3/02 8/30/07
39 P2164 PL - 20-Inch, 980 Zone, EastLake Parkway - Olym 7/3/03 8/30/07
40 P2169 PL - 20-Inch, 980 Zone, EastLake Parkway - Birc 7/2/07 6/30/08
47 P2325 PL - 10" to 12" Oversize, 1296 Zone, PB Road - R 7/5/04 6/30/08
53 P2367 PL - 16-Inch, 980 Zone, Olympic Parkway - East 7/3/02 6/30/09
57 P2397 PL- 12 Inch, 711Zone, EastLake Parkway - Birch/7/1/07 6/27/08
58 P2414 PL - 12" to 16" Oversize, 803 Zone, Dehesa Road 8/5/02 12/30/07
36 P2435 PL - 16-Inch, 711 Zone, Birch Road - La Media/S 7/3/03 6/30/08
13 R2031 RecPL - 12-Inch, 944 Zone, EastLake Parkway - 7/3/02 12/30/07
14 R2033 RecPL - 12-Inch, 944 Zone, Birch Road - La Med 7/3/03 6/30/08
16 R2040 RecPL - 12-Inch, 680 Zone, Hunte Parkway - Oly 7/5/04 12/30/07
17 R2041 RecPL - 8-Inch, 944 Zone, EastLake Parkway - B 7/4/06 12/30/07
18 R2043 RecPL - 8-Inch, 944 Zone, Rock Mountain Road -7/4/06 6/30/08
20 R2058 RecPL - 16-Inch, 860 Zone, Airway Road - Otay M 7/4/01 6/30/12
23 R2082 RecPL - 24-Inch, 680 Zone, Olympic Parkway - V 7/5/04 8/30/12
24 R2084 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/L 7/5/04 6/30/13
Project Category: Replacement/Renewal Proj 12/5/00 6/30/13
49 P2356 PL - 12-Inch, 803 Zone, Jamul Drive Permastran 7/5/05 3/30/09
52 P2366 APCD Engine Replacements and Retrofits 12/5/00 6/30/12
55 P2382 Safety and Security Improvements 7/3/02 6/30/11
59 P2416 SR-125 Utility Relocations 10/3/02 3/30/08
60 P2422 Agency Interconnections 7/2/03 6/30/13
61 P2440 I-905 Utility Relocations 1/3/03 6/30/09
62 P2441 NG/RAMAR Meter Replacements 12/4/06 6/30/08
64 P2447 Information Technology Meter Routing 7/4/05 6/30/08
67 P2453 SR-11 Utility Relocations 7/4/06 6/30/13
68 P2455 Data Cleansing Project 7/4/06 6/30/08
69 P2456 Air and Vacuum Valve Upgrades 7/4/06 6/30/13
71 P2458 AMR Manual Meter Replacement 7/4/06 6/30/13
72 P2459 Olive Vista Drive Utility Relocations 1/2/06 1/1/08
82 P2468 Finance Department Office Remodel 7/1/07 6/30/08
25 R2086 RWCWRF Force Main AirVac Replacements and 7/5/05 5/30/08
32 S2012 SVSD Outfall and RSD Replacement and OM Re 7/3/03 6/30/13
33 S2015 Calavo Lift Station Replacement 7/5/05 6/30/08
90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12 13 1
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Otay WaterDistrict FY 2008 Plus Five Year CIP Project Schedues
This schedule provides the start and finish dates of each project,
including all relevant prior years up through FY 2013.
20
Project: OWD FY 08 CIP ScheduleDate: 9/7/07
32
Item# Description Amount Type
Field Equipment
Engineering Development
1 GPS Survey Equipment based on an estimate from Trimble $ 54,000 N
Total Field Equipment - Engineering Development 54,000
Operations
9 Valve exercise machine for the valve program $ 15,000 N
11 John Deere Backhoe Hydraulic Hammer with installation and attachments 21,500 N
Total Field Equipment - Operations 36,500
Total Field Equipment 90,500
Vehicles
Operations
10 2008 Mid-size Super Cab 4 door pickup truckor equivalent. 25,000 R
2 2008 Full-size Superduty 4 door Supercab diesel or equivalent. 30,000 R
3 2008 Full-size Superduty 4 door Supercab diesel or equivalent. 30,000 R
4 2008 Mid-size Super Cab 4 door or equivalent. 25,000 R
5 2008 Mid-size Super Cab 4 door or equivalent. 25,000 R
6 2008 Mid-size Super Cab 4 door or equivalent. 25,000 R
7 2008 Mid-size Super Cab 4 door or equivalent. 25,000 R
8 2008 Mid-size Super Cab 4 door or equivalent. 25,000 R
Total Vehicles 210,000
Total Field Equipment and Vehicles Budget 300,500$
N -New
R -Replacement
FY 2008 CAPITAL PURCHASES
Capital purchases are non-recurring operating expense items for District-wide use that cost more than $10,000 each and have
an estimated useful life of two years or more. The Capital Purchase Projects include Vehicle, Office Equipment and
Furniture, and Field Equipment purchases.
33
The following pages describe each information item on the individual CIP project sheets
included in this section.
CIP Number: The CIP project number for all projects is assigned by the Engineering Project
Manager.
Project Title: Project titles follow a set format as described herein. The type of project should
be identified first. For example, if a project were a 711 Pressure Zone 24-inch pipeline, the title
would read “PL - 24-Inch, 711 Zone, Location - From A to B.” Pump stations and reservoirs are
identified similarly with abbreviations for type and size.
Work Order Number: A work order number is assigned to a CIP project once it is approved by
the Board of Directors. If more than one work order number is assigned to the project, then the
word “various” is used and all the various work order numbers shall be identified in the
comments field.
Director Division: All projects are located within a Board of Director’s division boundary unless
they apply to the entire District or are outside of the District boundaries. The Director division
where the majority of the physical project is located is listed. If it is a District-wide project it is
listed as “District-wide.” If it is outside the District boundary it is listed as “None.”
Project Manager: The person responsible for managing the project from inception through
completion.
I.D. Location: Most projects are located within one or more improvement districts. The I.D.
location listed is where the majority of the physical project is located. However, projects located
in portions of the District which have not yet been annexed into an improvement district are
listed as “None.”.
Original Approved Date: The date the project was originally approved with budget expenditures
for the corresponding fiscal year by the Board of Directors.
Priority: The priority of the project is listed in this field as one of the following:
1. HIGH: Safety, restoration of service to customers, obligation that requires
immediate action, directed by the Board of Directors, and/or critical system need.
2. MEDIUM: Upgrade of system or expansion requirement to maintain system
reliability not critical. Identified through planning effort as required within next
few fiscal years.
3. LOW: Identified through planning effort as required in future years to support
development; not anticipated in the immediate future.
4. VERY LOW: Requirement may have low probability of need in the future.
CIP PROJECT SHEET DESCRIPTION
34
Related CIP Projects: A maximum of three CIP project numbers that affect the scheduling
and/or is related to the subject project and/or could provide important information.
Budget Amount: The estimated budget includes all costs needed to complete a project including
land, right-of-way, consultants, contractors, District staff time, etc. All prior years’ costs are part
of the total cost and dollars are rounded up to the nearest $1,000.
Description of Project: A brief description of a project which typically includes size, length,
capacity, etc.
Justification of Project: A brief explanation of why a project is required which addresses
flexibility, reliability, water quality, safety, contractual obligation, immediate growth, etc., as
appropriate.
Comments: Pertinent information that should be known about a project that is not shown
elsewhere on the project sheet.
Funding Detail: The funding sources are listed along with the percentage of distribution to
expansion, betterment, and/or replacement.
Expenditure Schedule: The breakdown of a project’s expenditures by fiscal year. Prior years’
cost along with a six-year budget schedule. Included in each year are all costs to complete the
work scheduled in that year rounded up to the nearest $1,000.
Project Schedule: The schedule of the primary project phase shown with the estimated start date
(month/year) and finish date (month/year). The schedule time frames must correspond with the
expenditure schedule information.
Project Incremental Operation Expenditures: To determine the cost to maintain these new assets,
the District looks at the cost of maintaining similar assets through the Infrastructure Management
System and financial system. Costs are tracked by three main infrastructure asset groups of
pipes, pump stations, and reservoirs, as well as capital purchases and other types. Pipes typically
have only operation and maintenance (O&M) costs associated with them, pump stations have
O&M as well as power cost, and reservoirs have O&M and chemical cost. Each of the capital
purchases and other types has its own unique O&M cost.
Project Location: A vicinity map is drawn in AutoCAD format using the GIS database as the
foundation showing the approximate location and limits of a project within the District. Some
projects do not have a specific location and apply District-wide. In this case, a map of the entire
District will then be shown as the project location.
Thomas Bros. Map: The Thomas Brothers’ map page is inserted in this field to show where the
project is primarily located. Some projects do not have a specific location in which case the
words “District-wide” will be shown.
35
OWD Map Book: The page in the District’s facility map book where a project is primarily
located. Some projects do not have a specific location in which case the words “District-wide”
will be shown.
Submitted By: The project manager who originally submitted or the project manager who
revised the project sheet along with the date of submittal or last revision date of the CIP project
sheet.
36
CIP No. PROJECT DESCRIPTION PAGE
CAPITAL FACILITY PROJECTS
P2009 PL - 36-Inch, SDCWA Otay FCF No. 14 to Regulatory Site 39
P2033 PL - 16-Inch, 1296 Zone, Melody Road - Campo/Presilla 41
P2037 Res - 980-3 Reservoir 15 MG 43
P2038 PL - 12-Inch, 978 Zone, Jamacha, Hidden Mesa, and Chase Upsize and Replacements 45
P2040 Res - 1655-1 Reservoir 0.5 MG 47
P2129 Groundwater Exploration Program 49
P2143 Res - 1296-3 Reservoir 2 MG 51
P2172 PS - 1485-1 Pump Station Replacement 53
P2185 Res - 640-1 Reservoir 20.0 MG 55
P2190 PL - 10-Inch, 1485 Zone, Jamul Highlands Road to Presilla Drive 57
P2191 Res - 850-4 Reservoir 2.2 MG 59
P2258 PS - Lower Otay Pump Station Phase 1 (9,000 GPM) 61
P2267 36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations 63
P2295 624-1 Reservoir Disinfection Facility, Inlet/Outlet/Bypass and 613-1 Reservoir Demolition 65
P2318 PL - 20-Inch, 657 Zone, Summit Cross-Tie and 36-Inch Main Connections 67
P2370 Res - Dorchester Reservoir and Pump Station Demolition 69
P2387 PL - 12-Inch, 832 Zone, Steele Canyon Road - Via Caliente/Campo 71
P2450 Otay River Groundwater Well Demineralization/Development 73
P2451 Rosarito Desalination Facility Conveyance System 75
P2457 Otay Mountain Groundwater Well Development 77
P2460 I.D. 7 Trestle and Pipeline Demolition 79
P2462 Otay River Demineralization Feasibility Study 81
P2463 South Bay Regional Concentrate Conveyance Feasibility Study 83
P2464 San Diego 17 Pump Station and Flow Control Facility 85
P2465 Regulatory Site Material Storage Bins 87
P2466 Regional Training Facility 89
P2467 San Diego Formation Groundwater Feasibility Study 91
R2001 RecRes - 450-1 Reservoir 12 MG 93
R2004 RecPS - 680-1 Pump Station (11,500 GPM)95
R2034 RecRes - 860-1 Reservoir 4 MG 97
R2053 RWCWRF - R.O. Building Remodel and Office Furniture 99
R2077 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway 101
R2081 RecPL - 20-Inch, 944 Zone, Lane Avenue - Proctor Valley/Pond No. 1 103
R2087 RecPL - 20-Inch, 944 Zone, Wueste Road - Olympic/Otay WTP 105
R2088 RecPL - 20-Inch, 860 Zone, County Jail - Roll Reservoir/860-1 Reservoir 107
R2089 North District Recycled Water Regulatory Compliance 109
R2090 MBR Water Recycling Facility Feasibility Study 111
R2091 RecPS - 944-1 Pump Station Upgrade 113
R2092 Dis - 450-1 Reservoir Disinfection Facility 115
S2016 Solar Panel Installation Phase I 117
CIP PROJECT INDEX
37
CIP No. PROJECT DESCRIPTION PAGE
CIP PROJECT INDEX
REPLACEMENT/RENEWAL PROJECTS
P2356 PL - 12-Inch, 803 Zone, Jamul Drive Permastran Pipeline Replacement 119
P2366 APCD Engine Replacements and Retrofits 121
P2382 Safety and Security Improvements 123
P2416 SR-125 Utility Relocations 125
P2422 Agency Interconnections 127
P2440 I-905 Utility Relocations 129
P2441 NG/RAMAR Meter Replacements 131
P2447 Information Technology Meter Routing 133
P2453 SR-11 Utility Relocations 135
P2455 Data Cleansing Project 137
P2456 Air and Vacuum Valve Upgrades 139
P2458 AMR Manual Meter Replacement 141
P2459 Olive Vista Drive Utility Relocations 143
P2468 Finance Department Office Remodel 145
R2086 RWCWRF Force Main AirVac Replacements and Road Improvements 147
S2012 SVSD Outfall and RSD Replacement and OM Reimbursement 149
S2015 Calavo Lift Station Replacement 151
CAPITAL PURCHASE PROJECTS
P2282 Vehicle Capital Purchases 153
P2286 Field Equipment Capital Purchases 155
P2353 Information Technology System Enhancements and Replacements 157
P2361 Information Technology GIS Enhancements 159
P2363 Information Technology Utility Billing, Data Management, and Financial System 161
P2443 Information Technology Mobile Services 163
P2461 Records Management System Upgrade 165
DEVELOPER REIMBURSEMENT PROJECTS
P2070 PL - 16-Inch, 980 Zone, Pacific Bay Homes Road- Proctor Valley/Rolling Hills Hydro PS 167
P2121 PL - 16-Inch, 711 Zone, Hunte Parkway - Olympic/EastLake 169
P2133 PL - 16-Inch, 711 Zone, EastLake Parkway - Olympic/Birch 171
P2164 PL - 20-Inch, 980 Zone, EastLake Parkway - Olympic/Birch 173
P2169 PL - 20-Inch, 980 Zone, EastLake Parkway - Birch/Rock Mountain 175
P2325 PL - 10" to 12" Oversize, 1296 Zone, PB Road - Rolling Hills Hydro PS/PB Bndy 177
P2367 PL - 16-Inch, 980 Zone, Olympic Parkway - East Palomar/EastLake 179
P2397 PL - 12-Inch, 711 Zone, EastLake Parkway - Birch/Rock Mountain 181
P2414 PL - 12" to 16" Oversize, 803 Zone, Dehesa Road - Dehesa Meadow/OWD Bndy 183
P2435 PL - 16-Inch, 711 Zone, Birch Road - La Media/SR-125 185
R2031 RecPL - 12-Inch, 944 Zone, EastLake Parkway - Olympic/Birch 187
R2033 RecPL - 12-Inch, 944 Zone, Birch Road - La Media/EastLake 189
R2040 RecPL - 12-Inch, 680 Zone, Hunte Parkway - Olympic/EastLake 191
R2041 RecPL - 8-Inch, 944 Zone, EastLake Parkway - Birch/Rock Mountain 193
R2043 RecPL - 8-Inch, 944 Zone, Rock Mountain Road - La Media/SR-125 195
R2058 RecPL - 16-Inch, 860 Zone, Airway Road - Otay Mesa/Alta 197
R2082 RecPL - 24-Inch, 680 Zone, Olympic Parkway - Village 2/Heritage 199
R2084 RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media 201
38
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 25,500 feet of 36-inch pipeline from SDCWA Otay FCF No. 14 to the
Regulatory Site and fund 50% of the cost to upgrade FCF No. 14 to a capacity of 16 mgd.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$660
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,150 $9,770 $6,865 $45
TOTAL
$18,490
FUND DETAIL:
FUNDING SOURCE:
North District Storage 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The East County Regional Treated Water Improvement Program(ECRTWIP) Agreement was
approved by Otay WD Board in December 2005 and by the SDCWA Board in February 2006. Per
terms of the agreement Otay WD is obligated to construct the pipeline by March 1, 2010 and
SDCWA is have operational FCF No. 14 as well.
Various
PL - 36-Inch, SDCWA Otay FCF No. 14 to Regulatory Site
WORK ORDER NO:
PROJECT TITLE:
7/16/1997ORIGINAL APPROVED DATE:
P2038RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$18,490,000BUDGET AMOUNT:
3I.D. LOCATION:
COMMENTS:
SDCWA will provide $4.2 million in funds towards construction the pipeline. The cost estimate
includes the payment of $775,000 to SDCWA. See Work Order Nos. 2102 and 30136.
P2009CIP Number:
39
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:P2009
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/97
11/07
11/08 07/10
10/07
10/08DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$4,400 $8,700 $9,000 $9,300
PROJECT LOCATION:1272Thomas Bros. Map:OWD Map Book:356
40
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 6,400 feet of 16-inch main within the 1296 Pressure Zone generally
along the direction of Melody Road from Campo Road to Presilla Drive.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$6
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$5 $185 $1,160 $470
TOTAL
$1,826
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development within the Rancho Jamul Estates and
surrounding areas within the 1296 and higher pressure zones.
n/a
PL - 16-Inch, 1296 Zone, Melody Road - Campo/Presilla
WORK ORDER NO:
PROJECT TITLE:
5/23/2005ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
5DIRECTOR DIVISION:
2PRIORITY
$1,826,000BUDGET AMOUNT:
9I.D. LOCATION:
COMMENTS:
This project will be coordinated with the proposed Peaceful Valley Ranch development project.
P2033CIP Number:
41
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2033
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/05
11/08
07/10 06/11
10/08
06/10DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$2,200 $2,300
PROJECT LOCATION:1293Thomas Bros. Map:OWD Map Book:309
42
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a 15 MG reservoir adjacent to the existing 980-1 and 980-2 Reservoirs located within
the District's Use Area.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$630
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$200 $200 $800 $4,500 $7,825 $50
TOTAL
$14,205
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This reservoir will be needed to meet a portion of the projected operational, emergency, and fire flow
storage requirements in the 980 Pressure Zone as a result of the ongoing development of the Otay
Ranch, EastLake Woods, EastLake Vistas, etc. development projects.
Various
Res - 980-3 Reservoir 15 MG
WORK ORDER NO:
PROJECT TITLE:
6/4/2003ORIGINAL APPROVED DATE:
P2008, P2272, P2399,
P2431
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
4DIRECTOR DIVISION:
3PRIORITY
$14,205,000BUDGET AMOUNT:
I.D. LOCATION:
COMMENTS:
See Work Order Nos. 2118 and 30116.
P2037CIP Number:
43
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2037
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/89
02/05
11/11 06/13
01/05
10/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$28,200
PROJECT LOCATION:1291Thomas Bros. Map:OWD Map Book:172
44
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 8,600 feet of 12-inch pipeline located within Jamacha Road, Hidden
Mesa Road, and Chase Avenue. This project includes construction of a looped system between
Hidden Mesa Road and Penasco Road.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$115
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$980 $505
TOTAL
$1,600
FUND DETAIL:
FUNDING SOURCE:
I.D. 3
General Fund
50%
50%
50%
Expansion Betterment Replacement Total
TOTAL 50%50%100%
JUSTIFICATION OF PROJECT:
The existing pipelines in Chase Avenue and Jamacha Boulevard are undersized and the existing
pipeline in Hidden Mesa Road is deteriorated steel pipe that needs to be replaced and located within
the roadway right-of-way away from the existing residences.
n/a
PL - 12-Inch, 978 Zone, Jamacha, Hidden Mesa, and Chase Upsize and
Replacements
WORK ORDER NO:
PROJECT TITLE:
7/16/1997ORIGINAL APPROVED DATE:
P2009RELATED CIP PROJECTS:
KayPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$1,600,000BUDGET AMOUNT:
3I.D. LOCATION:
COMMENTS:
The Jamacha Road portion of this project is intended to be designed and constructed as part of CIP
project P2009.
P2038CIP Number:
45
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:P2038
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/05
07/06
11/07 03/09
06/06
10/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,500 $1,500 $1,500 $1,500
PROJECT LOCATION:1272Thomas Bros. Map:OWD Map Book:368
46
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a 0.5 MG reservoir and approximately 1,500 feet of 12-inch pipeline to connect to the
existing system in Presilla Drive. These improvements are located within the Rancho Jamul Estates
area.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$473
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1 $1 $85 $700 $795
TOTAL
$2,055
FUND DETAIL:
FUNDING SOURCE:
I.D. 9 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The project will increase system reliability, increase service capabilities, and provide adequate fire
protection for the Rancho Jamul Estates area within the 1655 Pressure Zone. The existing system is
currently served with a hydropneumatic pump station.
Various
Res - 1655-1 Reservoir 0.5 MG
WORK ORDER NO:
PROJECT TITLE:
8/19/1992ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
5DIRECTOR DIVISION:
2PRIORITY
$2,055,000BUDGET AMOUNT:
I.D. LOCATION:
COMMENTS:
See Work Order Nos. 2106 and 8893.
P2040CIP Number:
47
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2040
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/93
07/97
07/10 12/11
06/97
06/10DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$500 $900
PROJECT LOCATION:1293Thomas Bros. Map:OWD Map Book:310
48
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project funds the planning, exploration, and preliminary investigation of groundwater wells,
pumping, treatment requirements, etc., throughout the District. Once specific projects are
established for design and construction, they will be set up as separate CIP projects.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$560
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$10 $10 $15 $25 $630 $1,280
TOTAL
$2,530
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
Groundwater wells may play an important role in the District''''s water supply diversification and
reliability goals. They can also reduce the District''''s dependence on imported water by creating a
local source of irrigation and/or potable water.
Various
Groundwater Exploration Program
WORK ORDER NO:
PROJECT TITLE:
6/15/1994ORIGINAL APPROVED DATE:
P2348, P2434, P2450,
P2457
RELATED CIP PROJECTS:
PeasleyPROJECT MANAGER:
District WideDIRECTOR DIVISION:
2PRIORITY
$2,530,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
See Work Order Nos. 2354, 8399, 8415, 8911, and 9155.
P2129CIP Number:
49
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Jim Peasley 2/28/2007Date:Submitted By:
CIP Number:P2129
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/95 06/13
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
50
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a 2 MG steel reservoir on District property adjacent to the District's existing 1296-1
and 1296-2 Reservoirs at the west terminus of Bear Mountain Way.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$290
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,200 $1,800 $50
TOTAL
$3,340
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide additional storage in the 1296 Pressure Zone. The 1296 Pressure Zone has
an existing storage deficiency of about 0.3 million gallons. An additional 12 million gallons of storage
is projected to be required at ultimate development.
Various
Res - 1296-3 Reservoir 2 MG
WORK ORDER NO:
PROJECT TITLE:
5/17/1995ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
KayPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$3,340,000BUDGET AMOUNT:
9I.D. LOCATION:
COMMENTS:
See Work Order Nos. 2394 and 30106.
P2143CIP Number:
51
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:P2143
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
11/01
06/07
12/07 12/09
05/07
11/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,900 $3,800 $3,900 $4,000
PROJECT LOCATION:1292Thomas Bros. Map:OWD Map Book:307
52
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a new pump station to replace the existing pump station and to expand capacity as
projected within the Water Resources Master Plan.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$325
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$200 $1,200 $500
TOTAL
$2,225
FUND DETAIL:
FUNDING SOURCE:
I.D. 9
General Fund
50%
50%
50%
Expansion Betterment Replacement Total
TOTAL 50%50%100%
JUSTIFICATION OF PROJECT:
The existing pump station is near capacity, and has reached the end of its useful life. The improved
pump station systems and additional capacity are required to meet projected demands of the 1485
and higher pressure zones.
Various
PS - 1485-1 Pump Station Replacement
WORK ORDER NO:
PROJECT TITLE:
6/16/1993ORIGINAL APPROVED DATE:
P2028RELATED CIP PROJECTS:
KayPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$2,225,000BUDGET AMOUNT:
9I.D. LOCATION:
COMMENTS:
See Work Order Nos. 8212 and 30138.
P2172CIP Number:
53
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:P2172
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/01
07/07
10/07 07/09
06/07
09/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$7,400 $7,600 $7,800 $8,000
PROJECT LOCATION:1272Thomas Bros. Map:OWD Map Book:323
54
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project consists of two 10 mg structures where one will provide operational storage for ultimate
projected demand conditions for the planned La Presa System 640 Pressure Zone. The other 10 mg
reservoir will provide emergency storage for the North District systems.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$8,000
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$15,000 $6,000 $500
TOTAL
$29,500
FUND DETAIL:
FUNDING SOURCE:
General Fund
North District Storage
I.D. 1
3%
50%
47%
3%
Expansion Betterment Replacement Total
TOTAL 53%47%100%
JUSTIFICATION OF PROJECT:
Storage for the La Presa System is needed to correct existing substantial deficiencies and to operate
in conjunction with the existing 36-inch transmission pipeline to prevent depressurization of the La
Presa System. The reservoirs will provide higher suction pressures to the 803-1 Pump Station and
832-1 Pump Station resulting in significant energy savings. The 640 Reservoir storage is required to
be able to meet the 10,000 acre-feet per year demand from the Helix WD Levy WTP per terms of the
ECRTWIP agreement.
Various
Res - 640-1 Reservoir 20.0 MG
WORK ORDER NO:
PROJECT TITLE:
8/19/1992ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$29,500,000BUDGET AMOUNT:
20I.D. LOCATION:
COMMENTS:
See Work Order Nos. 2107, 2807, and 30018.
P2185CIP Number:
55
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2185
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
11/91
09/04
12/06 02/10
08/04
11/06DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$18,800 $37,600 $38,700 $39,900
PROJECT LOCATION:1271Thomas Bros. Map:OWD Map Book:343
56
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 1,300 feet of 10-inch pipeline located within Jamul Highlands Road to
the future extension of Presilla Drive.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$3
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$5 $5 $120 $95
TOTAL
$228
FUND DETAIL:
FUNDING SOURCE:
I.D. 9 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The project will increase system reliability by providing a loop system, increase service capabilities,
and insure adequate fire protection for the Rancho Jamul Estates area. The project is planned to
coincide with the development of Rancho Jamul Estates Unit No. 3 and surrounding land areas.
n/a
PL - 10-Inch, 1485 Zone, Jamul Highlands Road to Presilla Drive
WORK ORDER NO:
PROJECT TITLE:
5/23/2005ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
5DIRECTOR DIVISION:
3PRIORITY
$228,000BUDGET AMOUNT:
9I.D. LOCATION:
COMMENTS:
This project is to coincide with development of Rancho Jamul Estates Unit No. 3 and/or other nearby
land areas.
P2190CIP Number:
57
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2190
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/05
07/07
07/10 06/11
06/07
06/10DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$400 $400
PROJECT LOCATION:1293Thomas Bros. Map:OWD Map Book:310
58
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a 2.2 million gallon steel reservoir on District property adjacent to the existing 850-2
Reservoir in the La Presa System 850 Pressure Zone. The project is located at the South terminus
of Ledge Avenue in Spring Valley.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$635
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$750 $1,800 $100
TOTAL
$3,285
FUND DETAIL:
FUNDING SOURCE:
General Fund
I.D. 20
27%
73%
27%
73%
Expansion Betterment Replacement Total
TOTAL 27%73%100%
JUSTIFICATION OF PROJECT:
This project is required to increase operational, emergency, and fire storage in the 850 Pressure
Zone. The 850 Pressure Zone storage is currently at capacity and will require this additional storage
volume to meet the projected ultimate storage volume.
Various
Res - 850-4 Reservoir 2.2 MG
WORK ORDER NO:
PROJECT TITLE:
7/16/1997ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
KayPROJECT MANAGER:
3DIRECTOR DIVISION:
1PRIORITY
$3,285,000BUDGET AMOUNT:
20I.D. LOCATION:
COMMENTS:
See Work Order Nos. 8808 and 8943.
P2191CIP Number:
59
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:P2191
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/03
01/05
12/07 07/09
12/04
11/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$4,200 $4,300 $4,400 $4,500
PROJECT LOCATION:1291Thomas Bros. Map:OWD Map Book:317
60
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of the Lower Otay Pump Station to obtain increased flows from the City of San Diego
Otay WTP and pump water into the Central Area System 624-3 Reservoir plus the Otay Mesa
System 571-1 Reservoir. An interim trailer mounted engine driven pump has been installed until the
permanent pump station is constructed and placed into operation.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$2,085
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$50 $2,000 $3,670
TOTAL
$7,805
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This pump station is required to obtain increased capacity from the City of San Diego Otay WTP to
meet water supply needs for the Central Area and Otay Mesa Systems. The minimum capacity of
the ultimate pump station is 30 mgd.
8696
PS - Lower Otay Pump Station Phase 1 (9,000 GPM)
WORK ORDER NO:
PROJECT TITLE:
6/3/1996ORIGINAL APPROVED DATE:
P2288, P2425RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$7,805,000BUDGET AMOUNT:
I.D. LOCATION:
COMMENTS:
P2258CIP Number:
61
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2258
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
09/97
01/03
11/06 06/13
12/02
10/06DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1332Thomas Bros. Map:OWD Map Book:70
62
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Installation of ventilation equipment on the existing pump out and air/vacuum vaults on 36-inch
transmission main from the SDCWA Otay FCF No. 11 to the Regulatory Site. This project also
includes upsizing the existing 2-inch air/vacuum valves to 6-inch.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$195
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$150
TOTAL
$345
FUND DETAIL:
FUNDING SOURCE:
North District Fee 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The vault openings do not stay in place when refilling because they lack ventilation. By installing
vents in these vaults, the lids will stay in place, thus eliminating a safety hazard. Draining and filling
the 36-inch main at higher flow rates is required to return the system to service in shorter periods of
time.
8660
36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations
WORK ORDER NO:
PROJECT TITLE:
6/3/1996ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
HendersonPROJECT MANAGER:
3DIRECTOR DIVISION:
1PRIORITY
$345,000BUDGET AMOUNT:
1I.D. LOCATION:
COMMENTS:
P2267CIP Number:
63
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Don Henderson 2/28/2007Date:Submitted By:
CIP Number:P2267
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:07/97 06/08
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1291Thomas Bros. Map:OWD Map Book:198
64
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of new inlet and outlet pipelines, a reservoir bypass pipeline, and a disinfection facility
for the 624-1 Reservoir. The project also includes the demolition of the 613-1 Reservoir.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$3,950
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$550
TOTAL
$4,500
FUND DETAIL:
FUNDING SOURCE:
General Fund
I.D. 10
I.D. 22
70%15%
6%
9%
85%
Expansion Betterment Replacement Total
TOTAL 70%30%100%
JUSTIFICATION OF PROJECT:
The 624-1 Reservoir requires these facilities to allow for parallel operation of the 624-3 Reservoir.
Construction of the disinfection facility is consistent with the recommendations made in the
Distribution Systems Disinfection Master Plan.
Various
624-1 Reservoir Disinfection Facility, Inlet/Outlet/Bypass and 613-1
Reservoir Demolition
WORK ORDER NO:
PROJECT TITLE:
6/15/1994ORIGINAL APPROVED DATE:
P2235RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
1DIRECTOR DIVISION:
1PRIORITY
$4,500,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
See Work Order Nos. 8199, 30004, and 30006.
P2295CIP Number:
65
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2295
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/94
08/01
01/03 06/08
07/01
12/02DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$8,400 $8,700 $9,000 $9,300 $9,600 $9,900
PROJECT LOCATION:1311Thomas Bros. Map:OWD Map Book:114
66
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a pipeline between the two existing 18-inch mains to allow for bypass of the existing
36-inch transmission main near the old SDCWA Otay FCF No. 5 that was on Pipeline No. 3. Also
includes construction of several system connections to the existing 36-inch transmission main within
the La Presa System.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$56
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$200 $345
TOTAL
$601
FUND DETAIL:
FUNDING SOURCE:
North District Fee 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This will provide adequate and enhanced pipeline transmission capacity, increase reliability, and
provide operational flexibility for the existing La Presa System network. This project is required when
the 640 Reservoirs become operational.
8692
PL - 20-Inch, 657 Zone, Summit Cross-Tie and 36-Inch Main Connections
WORK ORDER NO:
PROJECT TITLE:
7/16/1997ORIGINAL APPROVED DATE:
P2185, P2370RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
3DIRECTOR DIVISION:
2PRIORITY
$601,000BUDGET AMOUNT:
1I.D. LOCATION:
COMMENTS:
P2318CIP Number:
67
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:P2318
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
11/97
12/07
11/09 06/10
11/07
10/08DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$100 $100 $100
PROJECT LOCATION:1291Thomas Bros. Map:OWD Map Book:198
68
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Demolish the existing Dorchester Reservoir and hydropneumatic pump station located on the same
site on Dorchester Street.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$15
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$65 $70
TOTAL
$150
FUND DETAIL:
FUNDING SOURCE:
I.D. 1 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The existing reservoir and hydropneumatic pump station are no longer required to serve customers.
n/a
Res - Dorchester Reservoir and Pump Station Demolition
WORK ORDER NO:
PROJECT TITLE:
5/23/2005ORIGINAL APPROVED DATE:
P2318RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
3DIRECTOR DIVISION:
1PRIORITY
$150,000BUDGET AMOUNT:
1I.D. LOCATION:
COMMENTS:
This project will be included in the contract as for CIP P2318.
P2370CIP Number:
69
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:P2370
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/05
08/10
07/11 06/12
07/10
06/11DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$-4,800
PROJECT LOCATION:1290Thomas Bros. Map:OWD Map Book:301
70
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Replacement of the existing 12-inch pipeline along Steele Canyon Road with approximately 1,800
feet of 12-inch main within the 832 Pressure Zone
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$70
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$270 $185
TOTAL
$525
FUND DETAIL:
FUNDING SOURCE:
I.D. 2 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The existing pipeline is within existing front yards of several homes and it poses a potential threat to
cause property damage.
n/a
PL - 12-Inch, 832 Zone, Steele Canyon Road - Via Caliente/Campo
WORK ORDER NO:
PROJECT TITLE:
6/5/2002ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
KayPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$525,000BUDGET AMOUNT:
20I.D. LOCATION:
COMMENTS:
P2387CIP Number:
71
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:P2387
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/05
09/06
11/07 03/09
08/06
10/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$600 $600 $600 $600
PROJECT LOCATION:1272Thomas Bros. Map:OWD Map Book:321
72
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
The Sweetwater Authority and Otay WD are investigating the possibility to develop a brackish water
demineralization facility within the Otay River to produce say 5 mgd of potable water.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$115 $85 $800 $3,600 $400
TOTAL
$5,000
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide for a level of water supply independence from SDCWA.
n/a
Otay River Groundwater Well Demineralization/Development
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
P2129, P2462RELATED CIP PROJECTS:
PeasleyPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$5,000,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
The Sweetwater Authority was awarded a Proposition 50 grant to help pay for 50% of the cost of the
feasibility study.
P2450CIP Number:
73
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Jim Peasley 2/28/2007Date:Submitted By:
CIP Number:P2450
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07
07/09
01/11 06/12
06/09
12/10DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$27,900
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
74
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
The San Diego Region could potentially receive a potable water supply source from the planned
Rosarito Desalination Facility via a conveyance system or an exchange arrangement.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$5 $5 $15 $80 $95 $800
TOTAL
$1,000
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The conveyance system or exchange concept could provide for a independent water source to the
San Diego County Region.
n/a
Rosarito Desalination Facility Conveyance System
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
PeasleyPROJECT MANAGER:
District WideDIRECTOR DIVISION:
2PRIORITY
$1,000,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
P2451CIP Number:
75
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Jim Peasley 2/28/2007Date:Submitted By:
CIP Number:P2451
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/06 06/13
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
76
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is to provide funding for development of a potential groundwater production well on Otay
Mesa near the foot of Otay Mountain.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$10 $290 $6,000 $200
TOTAL
$6,500
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The potential of an agreement for the development of a potable water production well could provide
the possibility of an independent local water supply resource for the Otay WD.
n/a
Otay Mountain Groundwater Well Development
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
P2129RELATED CIP PROJECTS:
PeasleyPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$6,500,000BUDGET AMOUNT:
7I.D. LOCATION:
COMMENTS:
P2457CIP Number:
77
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Jim Peasley 2/28/2007Date:Submitted By:
CIP Number:P2457
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
12/07
07/08
10/09 06/11
06/08
09/09DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$11,200 $11,500
PROJECT LOCATION:1352Thomas Bros. Map:OWD Map Book:27
78
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
The proposed project is to remove the existing trestle and 24-inch pipeline that crosses the Otay
River valley. This pipeline was the transmission main to supply water to the Otay Mesa System.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$20 $55 $300
TOTAL
$375
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The existing pipeline is no longer in service and should be removed to address liability concerns.
The Central Area-Otay Mesa Interconnection Pipeline supplies water to the Otay Mesa System.
n/a
I.D. 7 Trestle and Pipeline Demolition
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$375,000BUDGET AMOUNT:
7I.D. LOCATION:
COMMENTS:
P2460CIP Number:
79
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2460
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07
11/07
07/09 06/10
10/07
06/09DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1332Thomas Bros. Map:OWD Map Book:71
80
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is a feasibility study of the concept to potentially develop a demineralization facility within
the Otay River valley. The project is being jointly funded by Sweetwater Authority and Otay.
Proposition 50 funding for 50% of the cost has been secured by Sweetwater Authority.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$200
TOTAL
$200
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The potential of an agreement for the development of a potable water production well could provide
the possibility of an independent local water supply resource for the Otay WD.
n/a
Otay River Demineralization Feasibility Study
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
P2450RELATED CIP PROJECTS:
PeasleyPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$200,000BUDGET AMOUNT:
I.D. LOCATION:
COMMENTS:
P2462CIP Number:
81
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Jim Peasley 2/28/2007Date:Submitted By:
CIP Number:P2462
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07 06/08
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
82
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is a feasibility study of the concept to potentially develop a South Bay regional
concentrate conveyance facility. The project is being jointly funded by San Diego County Water
Authority, Sweetwater Authority, the City of San Diego, and Otay. Proposition 50 funding for 50% of
the cost has been secured by the San Diego County Water Authority.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$25 $100
TOTAL
$125
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The potential of the development of a regional concentrate conveyance facility within the South Bay
would provide the region with the ability to dispose of brine concentrates into the ocean. The facility
could be an important element for the development of a potable water production wells that could
provide the possibility of an independent local water supply resource for the Otay WD and others.
n/a
South Bay Regional Concentrate Conveyance Feasibility Study
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
PeasleyPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$125,000BUDGET AMOUNT:
I.D. LOCATION:
COMMENTS:
P2463CIP Number:
83
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Jim Peasley 2/28/2007Date:Submitted By:
CIP Number:P2463
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07 06/09
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
84
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is for the construction of a pump station by the City of San Diego, known as SD17 at
their Alvarado Water Treatment Plant. The pump station capacity is 60 million gallons per day (mgd)
of which Otay may acquire up to 50 mgd. The City of San Diego has the potential to acquire
Proposition 50 funding for about $6,500,000 from construction of SD17 and is willing to share these
funds with Otay.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$750 $7,500 $8,000
TOTAL
$16,250
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
With the pending agreement approval with the City of San Diego and the San Diego County Water
Authority (SDCWA) and subsequent construction of SD17, Otay will be able to take water supply
from the Alvarado WTP at potentially reduced rates over the prevailing SDCWA rate for treated
water.
n/a
San Diego 17 Pump Station and Flow Control Facility
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
PeasleyPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$16,250,000BUDGET AMOUNT:
I.D. LOCATION:
COMMENTS:
P2464CIP Number:
85
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Jim Peasley 2/28/2007Date:Submitted By:
CIP Number:P2464
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07 06/10
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$308,200 $317,400 $326,900
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
86
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is to install material storage bins at the Regulatory Site.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$30 $220
TOTAL
$250
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The material storage bins will improve the efficiency of the District operations for their installation and
construction efforts.
n/a
Regulatory Site Material Storage Bins
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
P2185RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$250,000BUDGET AMOUNT:
20I.D. LOCATION:
COMMENTS:
P2465CIP Number:
87
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Rick Acuna 2/28/2007Date:Submitted By:
CIP Number:P2465
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07
10/07
02/08 12/08
09/07
01/08DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1271Thomas Bros. Map:OWD Map Book:343
88
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
The project is the construction of a Regional Training Facility at the Regulatory Site through a
partnership with the San Miguel Consolidated Fire Protection District.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$100 $100
TOTAL
$200
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
Otay needs a training center to train staff on trenching, shoring, fire safety, rescue, and confined
space. The San Miguel Consolidated Fire Protection District has secured funding for this project and
will be the lead agency in the development of the training facility.
n/a
Regional Training Facility
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$200,000BUDGET AMOUNT:
20I.D. LOCATION:
COMMENTS:
P2466CIP Number:
89
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:P2466
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
08/06
07/07
02/08 01/09
06/07
01/08DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1271Thomas Bros. Map:OWD Map Book:343
90
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is a research and data gathering effort to enhance the ongoing USGS study of the
concept to potentially develop a groundwater supply from the San Diego Formation. The project is
planned to be jointly funded by Sweetwater Authority and Otay. A proposal for the San Diego County
Water Authority LISA grant program is being developed and may fund up to 50% of the cost of the
effort.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$800 $800
TOTAL
$1,600
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The potential of an agreement for the development of a potable water production well within the San
Diego Formation could provide the possibility of an independent local water supply resource for the
Otay WD and others.
n/a
San Diego Formation Groundwater Feasibility Study
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
PeasleyPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$1,600,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
P2467CIP Number:
91
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Jim Peasley 2/28/2007Date:Submitted By:
CIP Number:P2467
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07 06/09
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
92
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a 12 MG reservoir for the 450 Pressure Zone within recycled water system. The final
agreement has been approved with the City of San Diego for recycled water supply from the South
Bay Water Reclamation Plant (SBWRP) for 6 mgd.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$9,917
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$50
TOTAL
$9,967
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will receive water from the pump station at the City of San Diego''s SBWRP to supply
demands in the Central Area System recycled water system. The facility will balance the 24-hour
supply rate with a peaking rate generated by demand.
30016
RecRes - 450-1 Reservoir 12 MG
WORK ORDER NO:
PROJECT TITLE:
6/17/1998ORIGINAL APPROVED DATE:
R2004, R2022RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
1DIRECTOR DIVISION:
1PRIORITY
$9,967,000BUDGET AMOUNT:
10I.D. LOCATION:
COMMENTS:
Steel prices have risen dramatically since January 2004 due to supply and demand conditions.
Additional costs for full time inspection and construction management consulting services have been
reflected in the budget.
R2001CIP Number:
93
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:R2001
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
12/00
12/03
01/06 08/07
11/03
12/05DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$11,800 $12,200 $12,600 $13,000 $13,400 $13,800
PROJECT LOCATION:1330Thomas Bros. Map:OWD Map Book:66
94
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of an 11,500 gpm pump station and 24-inch discharge transmission main to supply
recycled water to the 680 and 944 Pressure Zones from the planned 450-1 Reservoir. The final
agreement with the City of San Diego for recycled water supply from the SBWRP has been
approved for 6 mgd.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$8,283
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$50
TOTAL
$8,333
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project is required to pump recycled water from the 450-1 Reservoir to the 680 and 944
Pressure Zones in the Central Area System.
30015
RecPS - 680-1 Pump Station (11,500 GPM)
WORK ORDER NO:
PROJECT TITLE:
6/17/1998ORIGINAL APPROVED DATE:
R2001, R2022RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
1DIRECTOR DIVISION:
1PRIORITY
$8,333,000BUDGET AMOUNT:
10I.D. LOCATION:
COMMENTS:
Steel prices have risen dramatically since January 2004 due to supply and demand conditions.
Additional costs for full time inspection and construction management consulting services have been
reflected in the budget.
R2004CIP Number:
95
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:R2004
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
12/00
12/03
01/06 08/07
11/03
12/05DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$170,100 $175,200 $180,500 $185,900 $191,500 $197,200
PROJECT LOCATION:1330Thomas Bros. Map:OWD Map Book:66
96
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a 4 MG reservoir for the 860 Pressure Zone of the recycled water system with Otay
Mesa.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$5
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$100 $395 $1,800 $1,500
TOTAL
$3,800
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will receive water from the 944 Pressure Zone within the Central Area System to supply
demands in the Otay Mesa System recycled water system. The facility will balance the 24-hour
supply rate with a peaking rate generated by demand.
8693
RecRes - 860-1 Reservoir 4 MG
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
R2088RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$3,800,000BUDGET AMOUNT:
7I.D. LOCATION:
COMMENTS:
R2034CIP Number:
97
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:R2034
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
09/06
10/07
07/09 06/12
09/07
06/09DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$7,500
PROJECT LOCATION:1332Thomas Bros. Map:OWD Map Book:55
98
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Installation of offices and training room and purchasing of furniture upon the existing reverse
osmosis building site at the RWCWRF.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$140
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$305 $50
TOTAL
$495
FUND DETAIL:
FUNDING SOURCE:
I.D. 22 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will eliminate the rental costs for trailers that currently contain the required offices space.
The existing systems at the RWCWRF will be used in a more effective and cost efficient manner.
Various
RWCWRF - R.O. Building Remodel and Office Furniture
WORK ORDER NO:
PROJECT TITLE:
7/16/1997ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
3DIRECTOR DIVISION:
1PRIORITY
$495,000BUDGET AMOUNT:
20I.D. LOCATION:
COMMENTS:
See Work Order Nos. 8690 and 8760.
R2053CIP Number:
99
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:R2053
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/97
02/06
08/07 07/08
01/06
07/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1271Thomas Bros. Map:OWD Map Book:319
100
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a 24-inch pipeline within the 860 Pressure Zone in Alta Road from the Alta Gate
location to Airway Road. This project will be constructed as part of the Otay Mesa recycled water
system.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$22
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$50 $50 $378 $1,000 $1,500
TOTAL
$3,000
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Mesa and link the planned
860-1 Reservoir with the recycled water system in Otay Mesa.
30017
RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
R2058RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$3,000,000BUDGET AMOUNT:
7I.D. LOCATION:
COMMENTS:
R2077CIP Number:
101
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:R2077
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
09/06
10/07
07/09 06/12
09/07
06/09DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$2,700
PROJECT LOCATION:1332Thomas Bros. Map:OWD Map Book:39
102
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a 20-inch pipeline within the 944 Pressure Zone in Lane Avenue from Proctor Valley
Road to Pond No. 1 within the Use Area.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$90
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$900 $300
TOTAL
$1,290
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 944 Pressure Zone.
n/a
RecPL - 20-Inch, 944 Zone, Lane Avenue - Proctor Valley/Pond No. 1
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
KayPROJECT MANAGER:
4DIRECTOR DIVISION:
1PRIORITY
$1,290,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
R2081CIP Number:
103
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:R2081
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/06
09/06
08/07 08/08
08/06
07/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$2,700 $2,800 $2,900 $3,000 $3,100
PROJECT LOCATION:1311Thomas Bros. Map:OWD Map Book:159
104
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a 20-inch pipeline within the 944 Pressure Zone in Wueste Road from Olympic
Parkway to near the existing City of San Diego Otay WTP. This project will be constructed as part of
the Otay Mesa recycled water system supply link.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$13
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$50 $50 $2,000 $1,400 $85
TOTAL
$3,598
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Mesa and is a part of the link
to the 944 Pressure Zone supply to the planned 860-1 Reservoir within the Otay Mesa recycled
water system.
n/a
RecPL - 20-Inch, 944 Zone, Wueste Road - Olympic/Otay WTP
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$3,598,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
R2087CIP Number:
105
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:R2087
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
09/06
10/07
07/10 09/11
09/07
06/10DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,500 $1,500
PROJECT LOCATION:1312Thomas Bros. Map:OWD Map Book:85
106
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a 20-inch pipeline within the 860 Pressure Zone from the 571-1 Reservoir site to the
planned 860-1 Reservoir. This project will be constructed as part of the Otay Mesa recycled water
system supply link.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$1
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$50 $50 $149 $1,000 $250
TOTAL
$1,500
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Mesa and link the planned
944 Pressure Zone supply to the planned 860-1 Reservoir within the Otay Mesa recycled water
system.
n/a
RecPL - 20-Inch, 860 Zone, County Jail - Roll Reservoir/860-1 Reservoir
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
R2034RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$1,500,000BUDGET AMOUNT:
7I.D. LOCATION:
COMMENTS:
R2088CIP Number:
107
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:R2088
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
09/06
04/07
07/10 09/11
03/07
06/10DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$2,400 $2,500
PROJECT LOCATION:1332Thomas Bros. Map:OWD Map Book:55
108
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is to fund any RWQCB Basin Plan revisions, State Department of Health Services
reporting requirements addressing health, safety, institutional, and water quality concerns and
potential CEQA compliance requirements.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$5
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$195
TOTAL
$200
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
Regulatory and institutional requirements for recycled water use within the Jamacha Basin must be
addressed to further the vision for eventual development of recycled water infrastructure within the
North District.
n/a
North District Recycled Water Regulatory Compliance
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
PeasleyPROJECT MANAGER:
District WideDIRECTOR DIVISION:
2PRIORITY
$200,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
The necessary infrastructure of storage, transmission mains, and distribution pipelines for recycled
water will be budgeted under another CIP project once the regulatory and institutional issues resolve
into a successful outcome.
R2089CIP Number:
109
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Jim Peasley 2/28/2007Date:Submitted By:
CIP Number:R2089
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
05/07 06/08
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
110
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is to fund the joint water recycling facility feasibility study for future recycled water supply
needs. The partners for this effort are the City of Chula Vista, Sweetwater Authority, and Otay.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$60
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$40
TOTAL
$100
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project has a very good potential to create a new and much needed recycled water supply
source.
n/a
MBR Water Recycling Facility Feasibility Study
WORK ORDER NO:
PROJECT TITLE:
7/5/2006ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$100,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
Otay is participating in the feasibility study as a one third cost sharing partner.
R2090CIP Number:
111
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:R2090
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/06 08/07
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
112
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project consists of adding a new pump and modifying two existing pumps to operate within the
system at higher efficiencies.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$325
TOTAL
$325
FUND DETAIL:
FUNDING SOURCE:
General Fund
I.D. 22
50%
50%
50%
Expansion Betterment Replacement Total
TOTAL 50%50%100%
JUSTIFICATION OF PROJECT:
The overall operating conditions of the pump station have been modified as a result of the planned
service to the Otay Mesa System recycled water system from the Central Area System and the
conversion of a existing potable water pipeline within the Use Area for recycled water service.
n/a
RecPS - 944-1 Pump Station Upgrade
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
R2003RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
1DIRECTOR DIVISION:
1PRIORITY
$325,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
R2091CIP Number:
113
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:R2091
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07
11/07
01/08 06/08
10/07
12/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$107,900 $111,100 $114,400 $117,800 $121,300
PROJECT LOCATION:1311Thomas Bros. Map:OWD Map Book:115
114
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project consists of construction of a disinfection system facility at the 450-1 Reservoir.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$300 $800
TOTAL
$1,100
FUND DETAIL:
FUNDING SOURCE:
I.D. 22 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The recycled water received from the City of San Diego South Bay Water Reclamation Plant is not
planned to be disinfected with chemicals. The recycled water will be to disinfected prior to deliver to
the District customers.
n/a
Dis - 450-1 Reservoir Disinfection Facility
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
R2001, R2004RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
1DIRECTOR DIVISION:
1PRIORITY
$1,100,000BUDGET AMOUNT:
10I.D. LOCATION:
COMMENTS:
R2092CIP Number:
115
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:R2092
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07
11/07
04/08 06/09
10/07
03/08DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$10,700 $11,000 $11,300 $11,600
PROJECT LOCATION:1330Thomas Bros. Map:OWD Map Book:66
116
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
The solar panel installation of a 65 KW AC solar system at the roof of the operations building or on
the administration building.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$10
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$10 $25 $200 $200 $200
TOTAL
$645
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The installation of the solar panels will potentially assist in reducing electrical costs and aid in the
effort to provide a clean environment. The photovoltaic system can produce electricity from a clean,
renewable resource without noise or air pollution.
n/a
Solar Panel Installation Phase I
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
4DIRECTOR DIVISION:
1PRIORITY
$645,000BUDGET AMOUNT:
20I.D. LOCATION:
COMMENTS:
An average commercial photovoltaic system costs from about $8 to $10 per AC watt. The California
Public Utilities Commission approved the California Solar Initiative (CSI) in November 2006. The CSI
program pays the public sector owner such as Otay $0.50 per kwh generated every month to five
years.
S2016CIP Number:
117
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:S2016
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/06
10/07
01/10 12/11
09/07
12/09DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1271Thomas Bros. Map:OWD Map Book:318
118
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Replacement of the existing 12-inch permastran pipeline within Jamul Drive with approximately
3,600 feet of 12-inch main.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$79
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$420 $266
TOTAL
$765
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The existing permastran pipeline has experienced failures and is sensitive to the normally occurring
pressure changes.
n/a
PL - 12-Inch, 803 Zone, Jamul Drive Permastran Pipeline Replacement
WORK ORDER NO:
PROJECT TITLE:
5/23/2005ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
KayPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$765,000BUDGET AMOUNT:
20I.D. LOCATION:
COMMENTS:
P2356CIP Number:
119
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:P2356
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/05
09/06
11/07 03/09
08/06
10/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1272Thomas Bros. Map:OWD Map Book:332
120
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is to replace and/or retrofit 14 diesel fuel burning engines with best technology exhaust
gas control systems throughout the District to comply with APCD engine emission regulations. The
District also needs to replace, repower, and/or retrofit the heavy vehicle diesel fleet to comply with
upcoming emissions regulations.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$1,518
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$160 $170 $180 $190 $220
TOTAL
$2,438
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The District is required to replace and/or retrofit 14 of its engines to meet current APCD
requirements including the Air Toxics Control Measures, and to be consistent with the intended
operation of the engines to meet system demands. The District also needs to replace, repower,
and/or retrofit the heavy vehicle diesel fleet to meet future emissions requirements.
Various
APCD Engine Replacements and Retrofits
WORK ORDER NO:
PROJECT TITLE:
12/6/2000ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
RahdersPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$2,438,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
See Work Order Nos. 30034, 30043, and 30083.
P2366CIP Number:
121
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Lisa Coburn-Boyd 2/28/2007Date:Submitted By:
CIP Number:P2366
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
12/00
07/01
07/05 06/12
06/01
06/10DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
122
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is to improve the security of the District''s facilities by developing a response plan,
installing protection systems, and contracting with a protection monitoring and response service.
This project will also include additional safety and security improvements as required throughout the
District. The security improvements are a result of the District''s Vulnerability Assessment Report
completed in March 2003.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$958
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$90 $90 $90 $89
TOTAL
$1,317
FUND DETAIL:
FUNDING SOURCE:
General Fund 20%80%100%
Expansion Betterment Replacement Total
TOTAL 20%80%100%
JUSTIFICATION OF PROJECT:
Although existing facilities are relatively safe and secure, the Federal government may mandate that
security of water systems be improved by monitoring and response to intrusions. The security
improvements are in response to the September 11, 2001 incident and potential future acts of
terrorism.
Various
Safety and Security Improvements
WORK ORDER NO:
PROJECT TITLE:
6/5/2002ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
BurpeauPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$1,317,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
See Work Order Nos. 30074 and 30079.
P2382CIP Number:
123
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Dave Burpeau 2/28/2007Date:Submitted By:
CIP Number:P2382
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/02
09/03
08/04 06/11
08/03
06/09DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
124
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project provides funding for all utility relocations required due to construction of SR-125. Facility
relocations vary in size from 8-inch to 24-inch and they impact both the potable and recycled water
systems.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$619
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$190
TOTAL
$809
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
Otay River Constructors, under contract with California Transportation Ventures, is constructing SR-
125, which conflicts with existing District facilities at various locations. In some cases, the District
does have prior and superior rights; and the facilities must be relocated to avoid physical conflicts.
Various
SR-125 Utility Relocations
WORK ORDER NO:
PROJECT TITLE:
6/4/2003ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
KayPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$809,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
A master agreement has been signed with Otay River Constructors to define the relationship
between the two entities and outline the process for defining the scope and cost of each required
facility relocation. See Work Order Nos. 30094 and 30103.
P2416CIP Number:
125
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:P2416
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
10/02
01/04
10/04 03/08
12/03
12/05DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
126
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project will provide funding to improve the existing interconnections with the District''s
neighboring agencies. Some of these connections are very old and require the installation of meters,
pressure gauges, valves, air/vacuum valves, blow-offs, etc., to ensure efficient, effective, and reliable
operation.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$250
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$300 $300 $300 $300 $300 $300
TOTAL
$2,050
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The existing interconnections play a vital role in supplying the District with alternative water
resources during an outage or supply shortfall from the normal SDCWA facility, known as Pipeline
No. 4. Typically on an annual basis, the SDCWA shuts down Pipeline No. 4 for inspection,
maintenance, and/or installation of new system components.
30093
Agency Interconnections
WORK ORDER NO:
PROJECT TITLE:
6/4/2003ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$2,050,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
P2422CIP Number:
127
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:P2422
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/03
06/06
07/07 06/13
06/12
06/12DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
128
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project provides funding for all utility relocations required due to construction of I-905 on the
Otay Mesa. Pipeline relocations vary from 12-inch to 24-inch. Five locations have been identified as
in conflict with I-905.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$1,000
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$360 $300
TOTAL
$1,660
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
Caltrans will construct I-905, which will result in utility conflicts with District pipelines. In all cases, the
District has prior and superior rights. The facilities must be relocated prior to Caltrans construction of
I-905. The cost of the facilities relocations that have prior rights will be reimbursed by Caltrans.
Various
I-905 Utility Relocations
WORK ORDER NO:
PROJECT TITLE:
6/2/2004ORIGINAL APPROVED DATE:
P2454RELATED CIP PROJECTS:
KayPROJECT MANAGER:
2DIRECTOR DIVISION:
1PRIORITY
$1,660,000BUDGET AMOUNT:
7I.D. LOCATION:
COMMENTS:
Utility agreements were developed by Caltrans for each of the required facility relocations. Any
betterment work such as pipeline size increase and /or additional length are at the District expense.
See Work Order Nos. 30128, 30129, 30130, and 30131.
P2440CIP Number:
129
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:P2440
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
01/03
10/03
10/06 06/09
09/06
09/06DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1351Thomas Bros. Map:OWD Map Book:10
130
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is to replace the existing meters that were installed in recent years that have become
inoperable due to allowed frequencies by the Federal Communication Commission.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$1,832
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$100
TOTAL
$1,932
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The District is currently in pending litigation to recoup the cost of replacing the non functioning
NG/Ramar meters. The Board has directed staff to proceed with the replacements.
n/a
NG/RAMAR Meter Replacements
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
P2458RELATED CIP PROJECTS:
HendersonPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$1,932,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
P2441CIP Number:
131
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Don Henderson 2/28/2007Date:Submitted By:
CIP Number:P2441
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:12/06 06/08
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
132
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project will provide an automated and dynamic meter routing capabilities to District customer
service personnel.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$50
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$80
TOTAL
$130
FUND DETAIL:
FUNDING SOURCE:
General Fund 25%75%100%
Expansion Betterment Replacement Total
TOTAL 25%75%100%
JUSTIFICATION OF PROJECT:
With the advent of the Automated Meter Reading (AMR) meters, meter reading routes will be
changing on a routine basis. The use of GIS technology and Smart Route routing software will allow
for automated route revisions shifting from manual techniques. These improvements will lower costs
and leverage the AMR investment.
n/a
Information Technology Meter Routing
WORK ORDER NO:
PROJECT TITLE:
5/23/2005ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
StevensPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$130,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
P2447CIP Number:
133
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Goeff Stevens 2/28/2007Date:Submitted By:
CIP Number:P2447
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/05 06/08
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$3,600 $3,700 $3,800 $3,900 $4,000
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
134
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project provides funding for all utility relocations required due to construction of SR-11 on the
Otay Mesa. Facility relocations vary in size from 8-inch to 24-inch. Both the potable and recycled
water systems are impacted.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$5 $165 $125 $680 $655 $670
TOTAL
$2,300
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
Caltrans will construct SR-11, which will result in utility conflicts with existing District facilities at
various locations. In most cases, the District does have prior and superior rights. The facilities must
be relocated prior to Caltrans construction of SR-11. The cost of the facilities relocations that have
prior rights will be reimbursed by Caltrans.
n/a
SR-11 Utility Relocations
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
KayPROJECT MANAGER:
2DIRECTOR DIVISION:
1PRIORITY
$2,300,000BUDGET AMOUNT:
7I.D. LOCATION:
COMMENTS:
P2453CIP Number:
135
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:P2453
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/06
07/07
11/09 06/13
06/09
10/09DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1351Thomas Bros. Map:OWD Map Book:5
136
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project provides funding for clean up of inaccurate data in the District''s core customer,
permitting, and facilities databases. Through use of data analysis tools, inaccurate and corrupted
data will be eliminated from the OIS databases.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$190
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$160
TOTAL
$350
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The District''s information systems require accurate and functional data to operate efficiently and
achieve the benefits of integration. Through the process of implementation and the collection of
inaccurate data over time the District needs to correct bad data to achieve system benefits.
n/a
Data Cleansing Project
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
P2363RELATED CIP PROJECTS:
StevensPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$350,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
P2455CIP Number:
137
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Goeff Stevens 2/28/2007Date:Submitted By:
CIP Number:P2455
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/06 06/08
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
138
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is to provide funding for the upgrading of approximately 750 existing are and vacuum
valves that are currently below grade.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$234
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$520 $550 $580 $600 $620 $640
TOTAL
$3,744
FUND DETAIL:
FUNDING SOURCE:
General Fund
I.D. 1
I.D. 20
14%
12%
74%74%
14%
12%
Expansion Betterment Replacement Total
TOTAL 26%74%100%
JUSTIFICATION OF PROJECT:
The current Department if Health regulations requires that all potable air and vacuum valves be
installed above grade to eliminate the possibility of back siphoning ground water into the potable
water system in the event of pressure loss within the water system.
n/a
Air and Vacuum Valve Upgrades
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
HendersonPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$3,744,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
Some of the existing are and vacuum valves are located in streets and roadways. These facilities will
require extension of the plumping outside of the traveled way. It is planned to upgrade approximately
140 units per year.
P2456CIP Number:
139
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Don Henderson 2/28/2007Date:Submitted By:
CIP Number:P2456
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:07/06 06/13
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
140
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project will provide funding to replace all manually read meters with AMR meters. Approximately
34,700 existing manual 3/4-inch meters will be replaced with the AMR meter.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$143
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,250 $1,375 $1,500 $1,650 $1,700 $1,750
TOTAL
$9,368
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This program will benefit the District in the form of reducing manpower resources as the systems are
expanded.
n/a
AMR Manual Meter Replacement
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
P2441RELATED CIP PROJECTS:
HendersonPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$9,368,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
P2458CIP Number:
141
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Don Henderson 2/28/2007Date:Submitted By:
CIP Number:P2458
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:07/06 06/13
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$-36,500 $-34,500 $-34,700 $-39,300 $-40,400 $-41,000
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
142
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project provides funding for all utility relocations required due to the reconstruction and widening
of Olive Vista Drive.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$142
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,100
TOTAL
$1,242
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The County of San Diego is reconstructing and widening Olive Vista Drive and Jefferson Road in
Jamul. The District does not have prior and superior rights. Approximately 875 feet of 10-inch and
600 feet on 12-inch pipelines need to be relocated and lowered, along with the associated
appurtenances.
n/a
Olive Vista Drive Utility Relocations
WORK ORDER NO:
PROJECT TITLE:
5/23/2006ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
KayPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$1,242,000BUDGET AMOUNT:
9I.D. LOCATION:
COMMENTS:
P2459CIP Number:
143
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:P2459
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
01/06
07/06
07/07 01/08
06/06
06/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1292Thomas Bros. Map:OWD Map Book:322
144
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is to provide funding for additional offices and related improvements to the
Administration Building within the Finance Department.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$50
TOTAL
$50
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The new office spaces within the Finance Department are necessary to improve functionality. The
concept is to foster a teamwork atmosphere plus contribute to the sharing of information and skills
among staff.
n/a
Finance Department Office Remodel
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
4DIRECTOR DIVISION:
1PRIORITY
$50,000BUDGET AMOUNT:
20I.D. LOCATION:
COMMENTS:
P2468CIP Number:
145
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Jim Peasley 2/28/2007Date:Submitted By:
CIP Number:P2468
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07
10/07
03/08 06/08
09/07
02/08DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1291Thomas Bros. Map:OWD Map Book:318
146
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Replacement of 21 existing two inch air release and vacuum valves on the recycled water force main
from the RWCWRF to the Use Area with improved capacity and corrosion resistance features. The
existing seven isolation valves on the force main will be replaced. The existing roadway along the
force main will be improved.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$205
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$670
TOTAL
$875
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The existing air release and vacuum valves on the force main have failed frequently, which causes
unauthorized discharges of recycled water. The existing isolation valves are corroded and exhibit
signs of leakage. The existing access road along the force main is damaged and improvements will
increase safety for operations personnel.
n/a
RWCWRF Force Main AirVac Replacements and Road Improvements
WORK ORDER NO:
PROJECT TITLE:
5/23/2005ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
JuybariPROJECT MANAGER:
3DIRECTOR DIVISION:
1PRIORITY
$875,000BUDGET AMOUNT:
I.D. LOCATION:
COMMENTS:
R2086CIP Number:
147
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Hossein Juybari 2/28/2007Date:Submitted By:
CIP Number:R2086
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/05
08/06
03/07 05/08
07/06
02/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1271Thomas Bros. Map:OWD Map Book:319
148
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project provides funding for the District''s proportionate share of the SVSD total costs for
replacement of various system components of the existing Spring Valley and Rancho San Diego
Outfall Systems per terms of an existing agreement with the SVSD. The reimbursement also
includes a proportionate share of operating and maintenance costs.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$1,281
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$605 $365 $270 $340 $350 $360
TOTAL
$3,571
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
Various components of the SVSD Spring Valley Outfall and the Rancho San Diego Outfall are in
very bad condition and are need of repair and/or replacement.
n/a
SVSD Outfall and RSD Replacement and OM Reimbursement
WORK ORDER NO:
PROJECT TITLE:
6/4/2003ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
PeasleyPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$3,571,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
S2012CIP Number:
149
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Jim Peasley 2/28/2007Date:Submitted By:
CIP Number:S2012
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/03 06/13
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
150
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of a new sewer lift station to replace the existing lift station.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$141
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$585
TOTAL
$726
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
The existing lift station has no remaining useful life, has groundwater intrusion problems, and
replacement components are hard to find.
n/a
Calavo Lift Station Replacement
WORK ORDER NO:
PROJECT TITLE:
5/23/2005ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
KayPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$726,000BUDGET AMOUNT:
14I.D. LOCATION:
COMMENTS:
S2015CIP Number:
151
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Daniel Kay 2/28/2007Date:Submitted By:
CIP Number:S2015
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
12/05
09/06
10/07 06/08
08/06
09/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1271Thomas Bros. Map:OWD Map Book:342
152
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project provides funding for capital purchase of various vehicles for daily District functions.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$1,141
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$210 $220 $220 $220 $220 $220
TOTAL
$2,451
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
Replacements or newly acquired vehicles will be used for operational and administrative functions
throughout the entire District.
30012
Vehicle Capital Purchases
WORK ORDER NO:
PROJECT TITLE:
6/3/1996ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
PorrasPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$2,451,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
It is planned to purchase nine vehicles in fiscal year 2008.
P2282CIP Number:
153
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Pedro Porras 2/28/2007Date:Submitted By:
CIP Number:P2282
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
12/00 06/13
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
154
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project provides funding for capital purchase of various pieces of field equipment used for daily
District functions.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$611
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$91 $100 $100 $100 $100 $100
TOTAL
$1,202
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
Replacements or new acquisitions of field equipment will be used for operational and administrative
functions throughout the entire District.
30014
Field Equipment Capital Purchases
WORK ORDER NO:
PROJECT TITLE:
6/3/1996ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
PorrasPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$1,202,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
It is planned to purchase a hydraulic breaker and valve machine in fiscal year 2008.
P2286CIP Number:
155
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Pedro Porras 2/28/2007Date:Submitted By:
CIP Number:P2286
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
12/00 06/13
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$800 $2,000 $4,100 $8,400 $17,300 $35,600
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
156
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Regular and ongoing enhancement and replacement of Information Technologies (IT) systems
components. This includes the computer network, security services, network servers, personal
computers, computer software, printers, voicemail, and telecommunications.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$3,047
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$365 $350
TOTAL
$3,762
FUND DETAIL:
FUNDING SOURCE:
General Fund 33%67%100%
Expansion Betterment Replacement Total
TOTAL 33%67%100%
JUSTIFICATION OF PROJECT:
The useful life of IT systems components is about three years. Over this period, advances in
technology make older components obsolete, rendering them inadequate for business operations.
Constant improvements in network servers and infrastructure, personal computers, the Windows
operating systems, office applications, and telecommunications equipment mandate upgrades about
every three years. This program will ensure that we are able to implement new technology
architectures and platforms plus bring significant improvements in functionality on a regular ongoing
basis.
Various
Information Technology System Enhancements and Replacements
WORK ORDER NO:
PROJECT TITLE:
6/7/2000ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
StevensPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$3,762,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
See Work Order Nos. 8478, 8859, 8860, 9242, 30065, 30089, 30090, and 30097.
P2353CIP Number:
157
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Goeff Stevens 2/28/2007Date:Submitted By:
CIP Number:P2353
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/96 06/09
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
158
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project provides funding for capital purchases of software and installation services to support
the Geographic Information System (GIS).
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$1,695
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$150 $100
TOTAL
$1,945
FUND DETAIL:
FUNDING SOURCE:
General Fund 25%75%100%
Expansion Betterment Replacement Total
TOTAL 25%75%100%
JUSTIFICATION OF PROJECT:
The GIS project and systems have been deployed in both an intranet and a mobile application to
support facility mapping and utilization requirements. The GIS system needs to be expanded to
serve as a basis for infrastructure management systems and to prepare it to interface with the
customer billing and work order systems that are under development.
9219
Information Technology GIS Enhancements
WORK ORDER NO:
PROJECT TITLE:
6/7/2000ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
StevensPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$1,945,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
P2361CIP Number:
159
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Goeff Stevens 2/28/2007Date:Submitted By:
CIP Number:P2361
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/00 06/09
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
160
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project is to replace the current utility billing system, utility permitting system, public services
developer system, enterprise infrastructure management systems, financial systems, human
resource system, and payroll system. Also will provide web interface capabilities for District
customers.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$6,300
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$200 $100
TOTAL
$6,600
FUND DETAIL:
FUNDING SOURCE:
General Fund 25%75%100%
Expansion Betterment Replacement Total
TOTAL 25%75%100%
JUSTIFICATION OF PROJECT:
The current billing system is obsolete, can no longer be maintained, and operates on a platform that
no longer is supported by the vendor. The District''s permitting and infrastructure management
systems, which were developed ad-hoc, cannot be maintained or are non-existent; these must be
replaced by an enterprise system. To achieve a totally integrated system, the financial, human
resources, and payroll systems also need to be replaced.
Various
Information Technology Utility Billing, Data Management, and Financial
System
WORK ORDER NO:
PROJECT TITLE:
6/7/2000ORIGINAL APPROVED DATE:
P2455RELATED CIP PROJECTS:
StevensPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$6,600,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
The Board will be provided an opportunity to review the project prior to major expenditures of funds.
See Work Order Nos. 9220, 30052, 30053, 30054, 30055, 30056, and 30115.
P2363CIP Number:
161
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Goeff Stevens 2/28/2007Date:Submitted By:
CIP Number:P2363
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/00 06/09
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
162
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project will provide for the testing and integration of mobile data and information services to field
staff members.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$412
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$240
TOTAL
$652
FUND DETAIL:
FUNDING SOURCE:
General Fund 25%75%100%
Expansion Betterment Replacement Total
TOTAL 25%75%100%
JUSTIFICATION OF PROJECT:
The District is implementing new work processes that will require field access to GIS data. This
project will ensure that the technology is appropriate and implemented in a planned and cost
effective manner.
n/a
Information Technology Mobile Services
WORK ORDER NO:
PROJECT TITLE:
5/23/2005ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
StevensPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$652,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
P2443CIP Number:
163
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Goeff Stevens 2/28/2007Date:Submitted By:
CIP Number:P2443
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/05 06/08
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$18,000 $18,500 $19,100 $19,700 $20,300
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
164
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
This project will expand the scope of the current records management system to capture existing
paper records, scan and categorize, and expand scanning capabilities to all Otay departments.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$150
TOTAL
$150
FUND DETAIL:
FUNDING SOURCE:
General Fund 25%75%100%
Expansion Betterment Replacement Total
TOTAL 25%75%100%
JUSTIFICATION OF PROJECT:
This project is required to achieve strategic objectives for business process improvements. Also,
required to meet demands for business backup and recovery goals.
n/a
Records Management System Upgrade
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
JenkinsPROJECT MANAGER:
District WideDIRECTOR DIVISION:
1PRIORITY
$150,000BUDGET AMOUNT:
District WideI.D. LOCATION:
COMMENTS:
P2461CIP Number:
165
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Bill Jenkins 2/28/2007Date:Submitted By:
CIP Number:P2461
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07 06/08
DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:District WideThomas Bros. Map:OWD Map Book:District Wide
166
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 3,000 feet of 16-inch main within the 980 Pressure Zone located
within the Rolling Hills Ranch development from Proctor Valley Road to the Rolling Hills
Hydropneumatic Pump Station. This project will be constructed by the developer and is subject to
reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$550
TOTAL
$550
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project is needed to provide service to the higher portions of Rolling Hills Ranch and the
planned development east of Rolling Hills Ranch (Bella Lago).
n/a
PL - 16-Inch, 980 Zone, Pacific Bay Homes Road- Proctor Valley/Rolling
Hills Hydro PS
WORK ORDER NO:
PROJECT TITLE:
6/7/2000ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
4DIRECTOR DIVISION:
2PRIORITY
$550,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
P2070CIP Number:
167
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
David Charles 2/28/2007Date:Submitted By:
CIP Number:P2070
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/03
09/03
12/04 06/08
08/03
11/04DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,000 $1,000 $1,000 $1,000 $1,000
PROJECT LOCATION:1311Thomas Bros. Map:OWD Map Book:145
168
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 8,600 feet of 16-inch pipeline within the 711 Pressure Zone in the
Hunte Parkway from Olympic Parkway to EastLake Parkway. This project will be constructed by the
developer and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$550
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1
TOTAL
$551
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 711 and higher pressure zones.
n/a
PL - 16-Inch, 711 Zone, Hunte Parkway - Olympic/EastLake
WORK ORDER NO:
PROJECT TITLE:
6/2/2004ORIGINAL APPROVED DATE:
P2133RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$551,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
P2121CIP Number:
169
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2121
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/03
03/04
12/05 08/07
02/04
11/05DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$2,900 $3,000 $3,100 $3,200 $3,300 $3,400
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:100
170
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 5,600 feet of 16-inch pipeline within the 711 Pressure Zone in
EastLake Parkway from Olympic Parkway to Birch Road. This project will be constructed by the
developer and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$150
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1
TOTAL
$151
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 711 and higher pressure zones.
n/a
PL - 16-Inch, 711 Zone, EastLake Parkway - Olympic/Birch
WORK ORDER NO:
PROJECT TITLE:
6/4/2003ORIGINAL APPROVED DATE:
P2121RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$151,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
P2133CIP Number:
171
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2133
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/02
10/03
09/04 08/07
09/03
08/04DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,900 $2,000 $2,100 $2,200 $2,300 $2,400
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:84
172
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 2,500 feet of 20-inch pipeline within the 980 Pressure Zone in
EastLake Parkway from Olympic Parkway to Birch Road. This project will be constructed by the
developer and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$210
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1
TOTAL
$211
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 980 and higher pressure zones.
n/a
PL - 20-Inch, 980 Zone, EastLake Parkway - Olympic/Birch
WORK ORDER NO:
PROJECT TITLE:
6/2/2004ORIGINAL APPROVED DATE:
P2169RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
1PRIORITY
$211,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
P2164CIP Number:
173
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2164
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/03
02/04
09/04 08/07
01/04
08/04DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$900 $900 $900 $900 $900 $900
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:99
174
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 2,500 feet of 20-inch pipeline within the 980 Pressure Zone in
EastLake Parkway from Birch Road to Rock Mountain Road. This project will be constructed by the
developer and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$325
TOTAL
$325
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 980 and higher pressure zones.
n/a
PL - 20-Inch, 980 Zone, EastLake Parkway - Birch/Rock Mountain
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
P2164RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
1PRIORITY
$325,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
P2169CIP Number:
175
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2169
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07
10/07
02/08 06/08
09/07
01/08DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$900 $900 $900 $900 $900
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:84
176
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 6,900 feet of 12-inch pipeline from the Rolling Hills Hydropneumatic
Pump Station to the future 1296 Reservoir. A portion of the project will be constructed by the
developer and is subject to reimbursement at actual cost for the oversize portion per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$130
TOTAL
$130
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Rolling Hills Ranch, Bello Lago,
and possible future adjacent areas within the Rolling Hills Hydropneumatic Pressure Zone.
n/a
PL - 10" to 12" Oversize, 1296 Zone, PB Road - Rolling Hills Hydro PS/PB
Bndy
WORK ORDER NO:
PROJECT TITLE:
6/7/2000ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
4DIRECTOR DIVISION:
2PRIORITY
$130,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
P2325CIP Number:
177
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
David Charles 2/28/2007Date:Submitted By:
CIP Number:P2325
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/04
09/04
01/05 06/08
08/04
12/04DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$2,300 $2,400 $2,500 $2,600 $2,700
PROJECT LOCATION:1311Thomas Bros. Map:OWD Map Book:160
178
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 9,800 feet of 16-inch pipeline within the 980 Pressure Zone in Olympic
Parkway from East Palomar to Eastlake Parkway. This project will be constructed by the developer
and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$235
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$850 $415
TOTAL
$1,500
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 980 and higher pressure zones.
30051
PL - 16-Inch, 980 Zone, Olympic Parkway - East Palomar/EastLake
WORK ORDER NO:
PROJECT TITLE:
6/7/2000ORIGINAL APPROVED DATE:
P2164RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
1DIRECTOR DIVISION:
1PRIORITY
$1,500,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
P2367CIP Number:
179
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2367
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/02
10/02
06/03 12/09
09/02
05/03DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,700 $3,300 $3,400 $3,500
PROJECT LOCATION:1311Thomas Bros. Map:OWD Map Book:98
180
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 1,000 feet of 12-inch pipeline within the 711 Pressure Zone in
EastLake Parkway from Birch Road to Rock Mountain Road. This project will be constructed by the
developer and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$175
TOTAL
$175
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 711 and higher pressure zones.
n/a
PL - 12-Inch, 711 Zone, EastLake Parkway - Birch/Rock Mountain
WORK ORDER NO:
PROJECT TITLE:
ORIGINAL APPROVED DATE:
P2164, P2169RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
1PRIORITY
$175,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
P2397CIP Number:
181
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2397
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/07
10/07
01/08 06/08
09/07
12/07DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$300 $300 $300 $300 $300
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:99
182
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 7,200 feet of 16-inch pipeline within the 803 Pressure Zone in Dehesa
Road from the existing pipeline to the District boundary. This project will provide service to the
Dehesa Elementary School site; it is a school district project and is subject to reimbursement for the
oversize portion at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$142
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$10
TOTAL
$152
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project is required to provide water service to the property along Dehesa Road and possibly to
properties east of the existing District jurisdictional boundary.
Various
PL - 12" to 16" Oversize, 803 Zone, Dehesa Road - Dehesa Meadow/OWD
Bndy
WORK ORDER NO:
PROJECT TITLE:
6/4/2003ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
5DIRECTOR DIVISION:
1PRIORITY
$152,000BUDGET AMOUNT:
20I.D. LOCATION:
COMMENTS:
See Work Order Nos. 9454 and 30087.
P2414CIP Number:
183
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:P2414
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
08/02
01/03
08/03 12/07
12/02
07/03DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$2,400 $2,500 $2,600 $2,700 $2,800 $2,900
PROJECT LOCATION:1252Thomas Bros. Map:OWD Map Book:380
184
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 4,200 feet of 16-inch pipeline within the 711 Pressure Zone in Birch
Road between La Media Road and State Route 125. This project will be constructed by the
developer and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$250
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$30
TOTAL
$280
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 711 and higher pressure zones.
n/a
PL - 16-Inch, 711 Zone, Birch Road - La Media/SR-125
WORK ORDER NO:
PROJECT TITLE:
6/2/2004ORIGINAL APPROVED DATE:
P2104, P2134RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$280,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
P2435CIP Number:
185
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
David Charles 2/28/2007Date:Submitted By:
CIP Number:P2435
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/03
09/03
12/05 06/08
08/03
11/05DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,400 $1,400 $1,400 $1,400 $1,400
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:84
186
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 2,500 feet of 12-inch pipeline within the 944 Pressure Zone in
EastLake Parkway from Olympic Parkway to Birch Road. This project will be constructed by the
developer and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$124
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1
TOTAL
$125
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 944 Pressure Zone.
n/a
RecPL - 12-Inch, 944 Zone, EastLake Parkway - Olympic/Birch
WORK ORDER NO:
PROJECT TITLE:
6/2/2004ORIGINAL APPROVED DATE:
R2033RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$125,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
R2031CIP Number:
187
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:R2031
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/02
09/02
07/04 12/07
08/02
06/04DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$900 $900 $900 $900 $900 $900
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:99
188
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 6,300 feet of 12-inch pipeline within the 944 Pressure Zone in Birch
Road from La Media Road to EastLake Parkway. This project will be constructed by the developer
and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$250
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$50
TOTAL
$300
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 944 Pressure Zone.
n/a
RecPL - 12-Inch, 944 Zone, Birch Road - La Media/EastLake
WORK ORDER NO:
PROJECT TITLE:
6/4/2003ORIGINAL APPROVED DATE:
R2031RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$300,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
R2033CIP Number:
189
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
David Charles 2/28/2007Date:Submitted By:
CIP Number:R2033
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/03
12/04
06/05 06/08
11/04
05/05DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$2,100 $2,200 $2,300 $2,400 $2,500
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:84
190
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 8,600 feet of 12-inch pipeline within the 680 Pressure Zone in Hunte
Parkway from Olympic Parkway to EastLake Parkway. This project will be constructed by the
developer and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$449
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1
TOTAL
$450
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 680 and 944 Pressure Zones.
n/a
RecPL - 12-Inch, 680 Zone, Hunte Parkway - Olympic/EastLake
WORK ORDER NO:
PROJECT TITLE:
6/2/2004ORIGINAL APPROVED DATE:
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$450,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
R2040CIP Number:
191
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:R2040
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/04
03/05
05/06 12/07
02/05
04/06DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$2,900 $3,000 $3,100 $3,200 $3,300 $3,400
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:100
192
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 4,200 feet of 8-inch pipeline within the 944 Pressure Zone in EastLake
Parkway from Birch Road to Rock Mountain Road. This project will be constructed by the developer
and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$124
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1
TOTAL
$125
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 944 Pressure Zone.
n/a
RecPL - 8-Inch, 944 Zone, EastLake Parkway - Birch/Rock Mountain
WORK ORDER NO:
PROJECT TITLE:
6/2/2004ORIGINAL APPROVED DATE:
R2031, R2033, R2042,
R2043
RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$125,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
R2041CIP Number:
193
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:R2041
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/06
09/06
11/06 12/07
08/06
10/06DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,400 $1,400 $1,400 $1,400 $1,400 $1,400
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:84
194
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 3,600 feet of 8-inch pipeline within the 944 Pressure Zone in Rock
Mountain Road from La Media Road to State Route 125. This project will be constructed by the
developer and is subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$235
TOTAL
$235
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Ranch and other areas within
the 944 Pressure Zone.
n/a
RecPL - 8-Inch, 944 Zone, Rock Mountain Road - La Media/SR-125
WORK ORDER NO:
PROJECT TITLE:
6/2/2004ORIGINAL APPROVED DATE:
R2042RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
3PRIORITY
$235,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
R2043CIP Number:
195
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
David Charles 2/28/2007Date:Submitted By:
CIP Number:R2043
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/06
09/06
11/06 06/08
08/06
10/06DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,200 $1,200 $1,200 $1,200 $1,200
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:84
196
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 16,000 feet of 16-inch pipeline within the 860 Pressure Zone in Airway
Road from Otay Mesa Road to Alta Road. Portions of this project will be constructed by developers,
and these are subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$320
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$300 $300 $300 $300 $480
TOTAL
$2,000
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for development of Otay Mesa within the 860
Pressure Zone.
30088
RecPL - 16-Inch, 860 Zone, Airway Road - Otay Mesa/Alta
WORK ORDER NO:
PROJECT TITLE:
6/16/1999ORIGINAL APPROVED DATE:
R2073, R2077RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
2DIRECTOR DIVISION:
2PRIORITY
$2,000,000BUDGET AMOUNT:
7I.D. LOCATION:
COMMENTS:
R2058CIP Number:
197
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:R2058
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/01
10/07
07/09 07/12
09/07
06/09DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$5,400
PROJECT LOCATION:1351Thomas Bros. Map:OWD Map Book:12
198
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 9,000 feet of 24-inch pipeline within the 680 Pressure Zone in Olympic
Parkway through Village 2 to Heritage Road. Portions of this project will be constructed by
developers, and these are subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$1
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$500 $500 $500 $246
TOTAL
$1,747
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for the recycled water supply pumped from the 680-1
Pump Station to the 680 and higher pressure zones. Significant energy savings will occur due to
lower total dynamic head requirements for the 680-1 Pump Station.
n/a
RecPL - 24-Inch, 680 Zone, Olympic Parkway - Village 2/Heritage
WORK ORDER NO:
PROJECT TITLE:
6/2/2004ORIGINAL APPROVED DATE:
R2083RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
1DIRECTOR DIVISION:
3PRIORITY
$1,747,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
R2082CIP Number:
199
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:R2082
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/04
07/06
01/07 08/12
06/06
12/06DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$3,100
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:82
200
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
DESCRIPTION OF PROJECT
Construction of approximately 6,000 feet of 20-inch pipeline within the 680 Pressure Zone in Village
2 from Heritage Road to La Media Road. This project will be constructed by developers and is
subject to reimbursement at actual cost per Board policy.
EXPENDITURE SCHEDULE (X $1000):
PRIOR YEARS:
TOTAL
$1
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
$1,099
TOTAL
$1,100
FUND DETAIL:
FUNDING SOURCE:
General Fund 100%100%
Expansion Betterment Replacement Total
TOTAL 100%100%
JUSTIFICATION OF PROJECT:
This project will provide transmission capacity for the recycled water supply pumped from the 680-1
Pump Station to the 680 and higher pressure zones. Significant energy savings will occur due to
lower total dynamic head requirements for the 680-1 Pump Station.
n/a
RecPL - 20-Inch, 680 Zone, Village 2 - Heritage/La Media
WORK ORDER NO:
PROJECT TITLE:
6/2/2004ORIGINAL APPROVED DATE:
R2083, R2085RELATED CIP PROJECTS:
RippergerPROJECT MANAGER:
1DIRECTOR DIVISION:
3PRIORITY
$1,100,000BUDGET AMOUNT:
22I.D. LOCATION:
COMMENTS:
R2084CIP Number:
201
OTAY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Ron Ripperger 2/28/2007Date:Submitted By:
CIP Number:R2084
PROJECT SCHEDULE:ESTIMATED
START DATE:
ESTIMATED
FINISH DATE:
PROJECT
PHASE:
PLANNING:
CONSTRUCTION:
07/04
07/06
06/12 06/13
06/06
12/06DESIGN:
PROJECTED INCREMENTAL OPERATION EXPENDITURES SCHEDULE ($):
FY FY FY FY FY FY
2008 2009 2010 2011 2012 2013
PROJECT LOCATION:1331Thomas Bros. Map:OWD Map Book:82
202
Effective 7/1/07
IMPROVEMENT CAPACITY ZONE TOTAL
NAME DISTRICT (ID) FEE CHARGE CHARGE
Rancho Jamul Estates Units 1 & 2 ID 9 WITH 1655 ZONE FEE $4,928 $23,242 $21,784
Capacity Fee Section 28.01 1,2,3,4,9,10, 19, 20,22,25,27 $4,928 $0 $4,928
TRIAD CAPACITY FEE ID 22/27-BASE $3,710 $0 $3,710
Note: This is based on a 3/4 inch water meter.
WATER METER CAPACITY FEES
203
GLOSSARY
The Fiscal Budget contains terminology that is unique to public finance and budgeting. The
following budget glossary provides assistance in understanding these terms.
Accrual Basis of Accounting: The basis of accounting under which transactions are
recognized when they occur, regardless of the timing of cash receipts and disbursements.
Acre-Foot: The volume of water that will cover one acre to a depth of one foot. One acre-
foot equals 435.6 units or 325,850 gallons.
Additional Systems Fees: Effective May 1, 1986, each customer receiving water service in
the Improvement District 9 water service zone pays an additional monthly meter system
charge of $2.00 for each meter in service.
Annexation Fees: Whenever utility service is requested for land outside the boundaries of
an improvement district, the land to be serviced must first be annexed. The annexation fee
for water was set on May 30, 2006 at $1,411 per EDU. The fee for sewer annexation was
set at $3,819 on December 16, 1998. These base rates are adjusted quarterly according to a
cost of living index.
Assets: Resources owned or held by Otay Water District that have monetary value.
Availability Fees: The District levies charges each year in developed areas to be used for
general purposes for construction of facilities, and in undeveloped areas to provide a source
of funding for planning, mapping, and preliminary design of facilities to meet future
development. Current legislation provides that any availability charge in excess of $10.00
per acre shall be restricted only for the purpose of constructing facilities in the improvement
district for which it was assessed.
Balanced Budget: A balanced financial plan, for a specified period of time that matches all
planned revenues and expenditures with various services. The District uses a fiscal year
beginning each July 1 and ending each June 30 for budgetary and financial reporting
purposes.
Betterment Fees: In addition to other applicable water rates and charges, certain water
customers pay a fee based on water service zone or improvement district. These are
restricted for the use in the area where they are collected and may be used for the
construction and maintenance of facilities.
Bond: A written promise to pay a sum of money on a specific date at a specified interest
rate. The interest payments and the repayment of the principal are authorized in a District
bond resolution. The most common types of bonds are general obligation (GO) bonds and
Certificates of Participation (COPs). These are frequently used for construction of large
capital projects such as buildings, reservoirs, pipelines and pump stations.
204
Budget Basis: The budget and accounting basis for the District is recognized on an accrual
basis. Accrual basis means that revenues are recognized when earned and expenses are
recognized when incurred.
Capacity Reservation Charge: A Metropolitan Water District charge passed on by the San
Diego County Water Authority to individual agencies. This fee is paid based on the
District’s peak water demand.
Capital Budget: The portion of the annual budget that appropriates funds for the purchase
of capital equipment items and capital improvements. These expenditures are separated
from regular operating items, such as salaries, utilities and office supplies. The Capital
Budget includes funds for capital equipment purchases over $10,000, such as vehicles,
furniture, machinery, microcomputers and special tools or $20,000 for infrastructure related
items, which are distinguished from operating items according to their value and projected
useful life.
Capital Equipment: Fixed assets such as vehicles, marine equipment, computers, furniture,
technical instruments, etc. which have a life expectancy of more than two years and a value
over $10,000 or $20,000 for infrastructure related items.
Capital Improvement Program: A long-range plan of the District for the construction,
rehabilitation and modernization of the District-owned and operated infrastructure.
Class of Service: All customers are classified based on the type of service used. For
example, the water rate per unit is determined by a classification such as residential versus
business.
CWA: The County Water Authority was organized in 1944 under the State County Water
Authority Act for the primary purpose of importing Colorado River water to augment the
local water supplies of the Authority's member agencies. The Authority purchases water
from the Metropolitan Water District of Southern California (MWD) which imports water
from the Colorado River and the State Water Project.
Deannexation Fees: Each request for detachment of land from an improvement district is
reviewed on a case-by-case basis. The fees are determined based on the present value of
future debt service requirements.
Debt Service: The District's obligation to pay the principal and interest of bonds and other
debt instruments according to a predetermined payment schedule.
GLOSSARY
GLOSSARY
205
Energy Fees: Water customers are charged an energy pumping charge based on the
quantity of water used and the elevation to which the water has been lifted to provide
service. The energy pumping charge is the rate of $.032 per 100 cubic feet of water for each
100 feet of lift above the base elevation of 450 feet. All water customers are in one of 29
zones based on elevation.
Expenditures/Expenses: These terms refer to the outflow of funds paid or to be paid for an
asset, goods or services obtained regardless of when actually paid for. (Note: An
encumbrance is not an expenditure). An encumbrance reserves funds to be expended in a
future period.
Fire Service: Water service is provided by the District solely for use in fire hydrants or fire
sprinkler systems from lines or laterals connected to the District’s water mains. The
monthly system charge is $23.30 per month for each connection for fire protection service.
Fiscal Year: Twelve-month term designating the beginning and ending period for recording
financial transactions. The District has specified July 1 to June 30 as its fiscal year.
Fund Balance: The current funds on hand resulting from the historical collection and use of
monies. The difference between assets and liabilities reported in the District’s Operating
Fund plus residual equities or balances and changes therein, from the result of operations.
General Fund: The District’s general fund is an enterprise fund comprised of the District’s
three business lines Potable, Recycled and Sewer services. Each is an accounting entity
with a self-balancing set of accounts established to record the financial position and results
that pertain to a specific activity. The activities of enterprise funds closely resemble those
of ongoing businesses in which the purpose is to conserve and add to basic resources while
meeting operating expenses from current revenues. Enterprise funds account for operations
that provide services on a continuous basis and are substantially financed by revenues
derived from user charges.
Grants: Contributions or gifts of cash or other assets from another governmental agency to
be used or expended for a specified purpose, activity, or facility. Capital grants are
restricted by the grantor for the acquisition and/or construction of fixed assets. Operating
grants are restricted by the grantor for operating purposes or may be used for either capital
or operating purposes at the discretion of the grantee.
Infrastructure Access Charge (IAC): A pass-through charge from CWA to each member
agency. The charge is to finance a portion of CWA’s fixed annual costs including the
construction, operation and maintenance of aqueducts and emergency storage projects. The
fee was adopted in January of 1999.
GLOSSARY
206
Interest Income: Earnings from the investment portfolio. Per District Policy Number 25,
interest income will be allocated to improvement districts each month based upon each
fund’s prior month-ending balance.
Irrigation Penalties: Potable water service provided solely for irrigation of landscaping will
receive a seasonably-adjusted allotment of water equal to 48” per year for the actual area to
be irrigated. Use of water in excess of the allotment shall be subject to penalty pricing. The
first violation is no surcharge. The second violation is 100% surcharge on excess water
used. The third violation is 400% surcharge. The fourth and subsequent violations are
800% surcharge.
Late Charges/Penalties: Charges and penalties are imposed on delinquent accounts. A late
payment charge of 5% of the total delinquent amount is added to the account. Other
miscellaneous late fees and penalties are detailed in the District’s Code of Ordinances.
Meter and Lateral Fees: Charge includes the material costs for the meter, meter box, and
the labor cost for installation to connect a new service to the distribution system.
Metropolitan Water District (MWD) Standby Charges: Revenue generated from property
taxes by MWD to cover the Readiness-to-Serve (RTS) Charge for the new debt service for
construction projects necessary to meet reliability and quality needs. The RTS Charge was
adopted in 1996.
Multiple Unit Charges: In addition to the system fee, a monthly charge is made for service
provided through one meter to more than one occupant in a building. The rate is $3.21
($3.53 effective 1/1/07) per month for each unit in a multiple unit residential, commercial or
industrial building.
1% General Tax: In 1978, Proposition 13 limited general levy property tax rates for all
taxing authorities to a total rate of 1% of full cash value. Subsequent legislation, AB8,
established that the receipts from the 1% levy were to be distributed to taxing agencies
according to approximately the same proportions received prior to Proposition 13. Funds
received are to be used for facilities construction or debt service on bonds sold to build
facilities.
Operating Budget: The portion of the budget that pertains to daily operations that provide
basic governmental services. The operating budget contains appropriations for such
expenditures as personnel, supplies, utilities, materials, travel and fuel, and does not include
purchases of major capital plant or equipment which is budgeted for separately in the
Capital Budget.
GLOSSARY
207
Other Income: Revenues that are not directly related to the business of providing water and
sewer services. For example, contract billing service for the City of Chula Vista and the
City of San Diego to bill their sewer customers based on water consumption.
Property Rental Income: Rent or lease agreements for the use of District property.
Reclaimed Water Rates: Non-potable water service provided from water produced by the
District’s reclamation plant and other non-potable sources. Reclaimed water is not used for
domestic purposes and all other uses must comply with federal, state and local laws and
regulations regarding the use of reclaimed water.
Reserve Fund: The District maintains Reserve Funds per the District’s policy for both
designated and restricted balances. Designated Reserve Funds are “general use” funds
designated by the Board. Restricted reserves are those that are legally set aside for a
particular purposed and cannot be used for any other purpose.
Residential Conservation: The water rates for residential customers are based on an
accelerated block structure; as more units are consumed, a higher unit rate is charged. The
District has established a water conservation program to promote water conservation and
planning.
Revenue: Monies that the District receives as income. It includes such items as water sales
and sewer fees. Estimated revenues are those expected to be collected during the fiscal
year.
RTS: Readiness-to-Serve Charge was adopted by the Metropolitan Water District (MWD)
in Fiscal 1996. The charge will serve as a foundation of fixed revenue for MWD. It will
cover the new debt service for construction projects necessary to meet reliability and quality
needs of current water-users as opposed to new customers.
Sale of Fixed Assets: District equipment, which has been determined by the Board to be of
no use, obsolete and/or beyond the useful life and therefore, may be sold.
Set-up Fees for Accounts: A charge of $10 is added for each account transferred to another
customer.
System Fees: Each water service customer pays a monthly system charge for water system
replacement, maintenance and operation expenses. The charge is based on the size of the
meter and class of service.
GLOSSARY
208
Taxes: California Water Code Section 72091 authorizes the District, as a municipal water
district, to levy ad valorem property taxes which are equal to the amount required to make
annual payments for principal and interest on general obligation bonds approved by the
voters prior to July 1, 1978.
Temporary Water Charge: The rate for temporary water service is two times the rate for
permanent service. The additional charge is to offset the cost of construction of facilities for
larger capacity.
Tier 2 Charge: A Metropolitan Water District charge passed on by the San Diego County
Water Authority to individual agencies. This is an added charge on all water sales by CWA in
excess of the District’s 90% baseline water usage.
Usage Surcharge: In addition to the water rates, a surcharge is paid by each customer when
the number of units of water furnished in any month exceeds the monthly usage allowance
for the size of meter being used.
Water Capacity Fees: Charges paid by customers to connect to a District water system for
potable or reclaimed water service. Fees are determined by multiplying the demand factor
for the meter size by the total of the District-wide capacity fee and applicable zone charge.
Water Rates: Rates vary among classes of service and are measured in units. The water
rates for residential customers are based on an accelerated block structure. As more units
are consumed, a higher unit rate is charged. All non-residential customers are charged a flat
rate per unit. A unit of water is 100 cubic feet or 748 gallons of water.
GLOSSARY
209
AF Acre-Foot/Feet
AMR Automated Meter Reader/Reading
APCD Air Pollution Control District
ASCE American Society of Civil Engineers
ASU Assigned Service Unit
AWWA American Water Works Association
BIT Bi-annual Inspection Terminals
BMP Best Management Practices
BOD Biological Oxygen Demand
BRP Business Resumption Plan
CADD Computer Aided Design & Drafting
CARB California Air Resources Board
CAFR Comprehensive Annual Financial Report
CCV City of Chula Vista
CEQA California Environmental Quality Act
CFS Cubic Foot per Second
CHP California Highway Patrol
CIP Capital Improvement Program
CIS Customer Information System
CIT Collaborative Improvement Teams
CMOM Capacity, Management, Operations & Maintenance
CMTA California Municipal Treasurers Association
COD Chemical Oxygen Demand
COPs Certificates of Participation
CRC Capacity Reservation Charge
CSC Customer Service Charge
CSD City of San Diego
CSMFO California Society of Municipal Finance Officers
CWA County Water Authority (San Diego)
DBMS Database Management System
DBP Disinfectant By-Products
DEH Department of Environmental Health
DHS Department of Health Services
DVP Delivery-versus-Payment
EDU Equivalent Dwelling Unit
EIR Environmental Impact Review
EOC Equal Opportunity Commission
ESC Emergency Storage Charge
FCF Flow Control Facility
LIST OF ACRONYMS
210
LIST OF ACRONYMS
FHLMC Freddie Mac or Federal Home Loan Mortgage Corporation
FNMA Fannie Mae or Federal National Mortgage Association
FTE Full-time Equivalent
FY Fiscal Year
GASB Government Accounting Standards Board
GFOA Government Financial Officers Association
GIS Geographic Information System
GO General Obligation (bonds)
GPM Gallons per Minute
GPS Global Positioning System
HCF Hundred Cubic Foot
HMA Habitat Management Area
HR Human Resources
HRIS Human Resources Information System
IAC Infrastructure Access Charge
ID Improvement District
IID Imperial Irrigation District
IIPP Injury and Illness Prevention Program
IMS Infrastructure Management System
IRP Integrated Water Resources Plan
IRS Internal Revenue Service
IT Information Technology
IVR Interactive Voice Response
LAFCO Local Area Formation Commission
LAIF Local Agency Investment Fund
LMSE La Mesa Sweetwater Extension
LOPS Lower Otay Pump Station
MBR Membrane Bioreactor
MG Million Gallons
MGD Million Gallons per Day
MGP Million Gallons per
MH Man-hours
MOU Memorandum of Understanding
MSCP Multiple Species Conservation Program
MSRB Municipal Securities Rulemaking Board
MWD Metropolitan Water District
MWWD Metropolitan Waste Water Department (City of San Diego)
NCCP Natural Community Conservation Plan
NEPA National Environmental Protection Act
211
LIST OF ACRONYMS
NIMS National Incident Management System
NOC Notice of Completion
NOSC Notice of Substantial Completion
NPDES National Pollution Discharge Elimination System
O&M or O/M Operations and Maintenance
OIS Otay Information System
OWD Otay Water District
PB Pacific Bay
PDR Preliminary Design Report
PEIR Program Environmental Impact Report
PERS Public Employees' Retirement System
PL Pipeline
POU Principles of Understanding
PRS Pressure Reducing Station
PS Pump Station
PT Part-time
RFID Radio Frequency Identification
RFP Request for Proposal
RSD Rancho San Diego
RTS Readiness-to-Serve
R/W Right-of-Way
RWCWRF Ralph W. Chapman Water Recycling Facility
SAMP Sub-Area Master Plan
SANDAG San Diego Association of Governments
SCADA Supervisory Control and Data Acquisition
SBWRP South Bay Water Reclamation Plant
SDRMA San Diego Risk Management Association
SEC Securities and Exchange Commission
SHRM Society of Human Resources Management
SLMA Sallie Mae or Student Loan Marketing Association
SPSD Spring Valley Sanitation District
SS Suspended Solids
SSMP Sewer System Management Plan
SWA Sweetwater Authority
SWRCB State Water Resource Control Board
USBR U.S. Bureau of Reclamation
UWMP Urban Water Management Plan
WADG Water Agency Design Guideline
WD Water District
212
LIST OF ACRONYMS
WER Work Environment Review
WRMP Water Resources Master Plan
WTP Water Treatment Plant
213
Awards 4
Budget Calendar 12
Budget Guide 1
Budget Process 13
Capital Facility Projects 39
Capital Improvement Program 27
Capital Improvement Program Budget Narrative 16
Capital Purchases Budget 33
Capital Purchase Projects 153
CIP Funding Source and Category 26
CIP Justification and Impact on Operating Budget 29
CIP Project Index 37
CIP Project Schedule 31
CIP Project Sheet Description 34
CIP Projects in Construction 21
CIP Reserve Funds 25
Current Economic Conditions 8
Demographics 10
Developer Reimbursement Projects 167
Flagship CIP Projects Completed 19
Flagship CIP Projects in Construction 21
Flagship CIP Projects in Design 23
General Information 3
Glossary 204
Index 214
Letter of Transmittal ii
List of Acronyms 210
Major CIP Projects 18
Organization Chart 11
Otay Water District At-A-Glance 2
Progress on Major Projects 24
Replacement/Renewal Projects 119
Resolution No. 4097 15
The Future 9
Water Meter Capacity Fees 203
INDEX
214