HomeMy WebLinkAbout12-08-15 EO&WR Committee PacketOTAY WATER DISTRICT ENGINEERING, OPERATIONS & WATER RESOURCES COMMITTEE MEETING and SPECIAL MEETING OF THE BOARD OF DIRECTORS 2554 SWEETWATER SPRINGS BOULEVARD SPRING VALLEY, CALIFORNIA Board Room TUESDAY December 8, 2015 12:00 P.M. This is a District Committee meeting. This meeting is being posted as a special meeting in order to comply with the Brown Act (Government Code Section §54954.2) in the event that a quorum of the Board is present. Items will be deliberated, however, no formal board actions will be taken at this meeting. The committee makes recommendations to the full board for its consideration and formal action. AGENDA 1. ROLL CALL 2. PUBLIC PARTICIPATION – OPPORTUNITY FOR MEMBERS OF THE PUBLIC TO SPEAK TO THE BOARD ON ANY SUBJECT MATTER WITHIN THE BOARD'S JU- RISDICTION BUT NOT AN ITEM ON TODAY'S AGENDA DISCUSSION ITEMS 3. AWARD A CONSTRUCTION CONTRACT TO ADVANCED INDUSTRIAL SERVICES, INC. FOR THE 980-1 RESERVOIR INTERIOR/EXTERIOR COATINGS AND UP- GRADES PROJECT IN AN AMOUNT NOT-TO-EXCEED $876,500 (CAMERON) [5 min] 4. AWARD A PROFESSIONAL AS-NEEDED LAND SURVEYING SERVICES CON- TRACT TO HUNSAKER AND ASSOCIATES SAN DIEGO, INC. TO EXECUTE AN AGREEMENT WITH HUNSAKER IN AN AMOUNT NOT-TO-EXCEED $175,000 FOR A PERIOD OF THREE (3) FISCAL YEARS (FY 2016 THROUGH FY 2018, ENDING JUNE 20, 2019) (O’DONNELL) [5 min] 5. FIRST QUARTER OF FISCAL YEAR 2016 CAPITAL IMPROVEMENT PROGRAM UPDATE REPORT (MARTIN) [5 minutes] 6. SAN DIEGO COUNTY WATER AUTHORITY UPDATE (WATTON) [10 minutes] 7. ADJOURNMENT 2 BOARD MEMBERS ATTENDING: Gary Croucher, Chair Tim Smith All items appearing on this agenda, whether or not expressly listed for action, may be delib- erated and may be subject to action by the Board. The Agenda, and any attachments containing written information, are available at the Dis- trict’s website at www.otaywater.gov. Written changes to any items to be considered at the open meeting, or to any attachments, will be posted on the District’s website. Copies of the Agenda and all attachments are also available through the District Secretary by contacting her at (619) 670-2280. If you have any disability that would require accommodation in order to enable you to partici- pate in this meeting, please call the District Secretary at 670-2280 at least 24 hours prior to the meeting. Certification of Posting I certify that on December 4, 2015 I posted a copy of the foregoing agenda near the regular meeting place of the Board of Directors of Otay Water District, said time being at least 24 hours in advance of the meeting of the Board of Directors (Government Code Section §54954.2). Executed at Spring Valley, California on December 4, 2015. /s/ Susan Cruz, District Secretary STAFF REPORT TYPE MEETING: Regular Board MEETING DATE: January 6, 2016 SUBMITTED BY: Kevin Cameron Associate Civil Engineer Bob Kennedy Engineering Manager PROJECT: P2545-001103 DIV. NO. 5 APPROVED BY: Rod Posada, Chief, Engineering German Alvarez, Assistant General Manager Mark Watton, General Manager SUBJECT: Award of a Construction Contract to Advanced Industrial Services, Inc. for the 980-1 Reservoir Interior/Exterior Coatings & Upgrades Project GENERAL MANAGER’S RECOMMENDATION: That the Otay Water District (District) Board of Directors (Board) award a construction contract to Advanced Industrial Services, Inc. (AIS) and to authorize the General Manager to execute a construction contract with AIS for the 980-1 Reservoir Interior/Exterior Coatings & Upgrades Project in an amount-not-to exceed $876,500 (see Exhibit A for Project location). COMMITTEE ACTION: Please see Attachment A. PURPOSE: To obtain Board authorization for the General Manager to enter into a construction contract with AIS for the 980-1 Reservoir Interior/ Exterior Coatings & Upgrades Project in an amount-not-to exceed $876,500. 2 ANALYSIS: The 980-1 Reservoir is one of two 5.0 million gallon potable water storage facilities in the 980 pressure zone that serve the Central Area of the District. The 980-1 Reservoir was originally constructed in 1986. In January 2015, the District’s staff identified excessive corrosion on one (1) of the five (5) roof vents on the 980-1 Reservoir. The vent was temporarily repaired, and District staff further investigated the tank’s condition and recoating schedule. The District’s corrosion consultant, HDR, Inc., maintains a Corrosion Control Program (CCP) that addresses the installation, maintenance, and monitoring of corrosion protection systems for the District’s steel reservoirs and buried metallic piping. The CCP included a reservoir maintenance schedule that showed the 980-1 Reservoir was due to be recoated on both the interior and exterior surfaces in 2019. An in-service internal and external inspection was performed by Dive/Corr, Inc. which illustrated the interior roof coating was in fair to poor condition, and there were areas of blistering on the shell and floor beneath the waterline. The interior coating was replaced in 2001, and although blistering paint was still protecting the steel, blisters in the paint are the beginning signs of failure. The coating on the exterior has never been completely replaced, only spot repaired as needed. Given the condition of the interior coating, the age of the exterior coating, along with replacement of the existing roof vents, and a number of other structural upgrades, the tank recoating was accelerated. In addition to replacing the coatings and structural upgrades, safety items will be installed to comply with current safety and health requirements. During construction, service in the 980 pressure zone will be provided by the 980-2 Reservoir. The recommended structural upgrades, developed with input from Engineering and Operations staff, are as follows: replace the coating on the interior and exterior surfaces, replace the existing level indicators, install new fall prevention devices on the interior and exterior ladders, modify anode access ports, replace all cathodic anodes, replace all five (5) roof vents, install new safety cable lanyards for roof access, and add multiple tank penetrations for chlorination and sampling. These upgrades will ensure compliance with American Water Works Association (AWWA) and the Occupational Safety and Health Administration Standards for both Federal (OSHA) and State (Cal-OSHA) as well as upgrade antiquated equipment on the tank. The Project was advertised on October 9, 2015 on the District’s website and several other publications including the San Diego Union 3 Tribune. A Pre-Bid Meeting was held on October 20, 2015, which was attended by two (2) contractors. By request, an additional site visit was held on October 21, 2015, and one (1) contractor attended. One (1) addendum was sent out to all bidders and plan houses to address questions and clarifications to the contract documents during the bidding period. Bids were publicly opened on October 29, 2015, with the following results: CONTRACTOR TOTAL BID AMOUNT 1 Advanced Industrial Services, Inc. Los Alamitos, CA $876,500.00 2 Blastco, Inc. Downey, CA $1,031,240.00 3 Simpson Sandblasting & Special Coatings, Inc. Fontana, CA $1,050,039.00 The Engineer's Estimate is $1,077,000. The evaluation process included reviewing all bids submitted for conformance to the contract documents. The lowest bidder, AIS, submitted a responsible bid and holds a Class A Contractor’s license which expires on January 31, 2016. AIS also holds a current QP-2 certification from the Society for Protective Coatings, which was also a requirement. The District has previously worked with AIS on the following interior and exterior reservoir coating projects; 803-3, 832-2, and the 624-2 Reservoir in 2014, which were completed on time and under budget. Staff checked three new references, and the response from other agencies indicated AIS has an excellent performance rating on similar projects. The proposed Project Manager has experience throughout California on similar projects and received excellent recommendations. AIS was also awarded the 711-1 & 711-2 Reservoir coating at the October 7, 2015 Board Meeting. Including the references from the previous projects, the District has contacted twelve other agencies to ask about AIS’ performance, and all have had very good responses. A background search of the company was performed on the internet and revealed no outstanding issues with this company. AIS submitted the Company Background and Company Safety Questionnaires, as required by the Contract Documents. Staff confirmed that AIS is registered with the Department of Industrial Relations, as required by Senate Bill SB 854. Staff has verified that the bid bond provided by Travelers Casualty and Surety Company of America is valid. Once AIS signs the contract, they will furnish the performance bond and labor and materials bond. Staff will verify both bonds prior to executing the contract. 4 FISCAL IMPACT: Joe Beachem, Chief Financial Officer The total budget for CIP P2529, as approved in the FY 2016 budget, is $1,495,000. Total expenditures, plus outstanding commitments and forecast, are $1,258,240. See Attachment B for the budget detail. Based on a review of the financial budget, the Project Manager anticipates that the budget is sufficient to support the Project. The Finance Department has determined that, under the current rate model, 100% of the funding will be available from the Replacement Fund. STRATEGIC GOAL: This Project supports the District’s Mission statement, “To provide high value water and wastewater services to the customers of the Otay Water District in a professional, effective, and efficient manner” and the General Manager’s Vision, “A District that is at the forefront in innovations to provide water services at affordable rates, with a reputation for outstanding customer service.” LEGAL IMPACT: None. KC/BK:jf P:\WORKING\CIP P2545 - 980-1 Reservoir Int-Ext Coating\Staff Reports\01-06-16, Staff Report 980-1 Reservoir Coating(KC-BK).docx Attachments: Attachment A – Committee Action Attachment B – Budget Detail Exhibit A – Location Map ATTACHMENT A SUBJECT/PROJECT: P2545-001103 Award of a Construction Contract to Advanced Industrial Services, Inc. for the 980-1 Reservoir Interior/Exterior Coatings & Upgrades Project COMMITTEE ACTION: The Engineering, Operations, and Water Resources Committee (Committee) reviewed this item at a meeting held on December 8, 2015. The Committee supported Staff's recommendation. NOTE: The “Committee Action” is written in anticipation of the Committee moving the item forward for Board approval. This report will be sent to the Board as a Committee approved item, or modified to reflect any discussion or changes as directed from the Committee prior to presentation to the full Board. ATTACHMENT B – Budget Detail for P2545 SUBJECT/PROJECT: P2545-001103 Award of a Construction Contract to Advanced Industrial Services, Inc. for the 980-1 Reservoir Interior/Exterior Coatings & Upgrades Project Date Updated: 11/10/15 Budget 1,495,000 Planning Standard Salaries - - - - Consultant Contracts 2,750 2,750 - 2,750 DIVE/CORR INC Total Planning 2,750 2,750 - 2,750 Design Standard Salaries 40,000 24,689 15,311 40,000 Service Contracts 1,500 977 523 1,500 MAYER 500 407 93 500 SAN DIEGO UNION TRIBUNE Total Design 42,000 26,073 15,927 42,000 Construction Standard Salaries 150,000 811 149,189 150,000 Construction Contract 876,500 - 876,500 876,500 ADVANCED INDUSTRIAL SERVICES Service Contracts 60,000 - 60,000 60,000 SPECIALTY INSPECTION 40,000 - 40,000 40,000 ALYSON CONSULTING-CM 150 - 150 150 CLARKSON LAB & SUPPLY 35,000 - 35,000 35,000 WATCHLIGHT CORPORATION Professional Legal Fees 5,000 - 5,000 5,000 STUTZ ARTIANO SHINOFF Equipment Rental 15 15 - 15 EQUIPMENT RENTAL CO Project Closeout 3,000 - 3,000 3,000 CLOSEOUT Project Contingency 43,825 - 43,825 43,825 5% CONTINGENCY Total Construction 1,213,490 826 1,212,664 1,213,490 Grand Total 1,258,240 29,649 1,228,591 1,258,240 Vendor/Comments Otay Water District P2545-980-1 Reservoir Interior/Exterior Coating CommittedExpenditures Outstanding Commitment & Projected Final Cost OTAY WATER DISTRICT980-1 Reservoirs Interior/Exterior Coating & UpgradesLocation Map EXHIBIT A F P:\\WORKING\CIP P2545 - 980-1 Reservoir Int-Ext Coating\Graphics\Exhibits-Figures\Reservoir Location Map Exhibit CIP P2545 980-1 Reservoir SALT CREEKGOLF CLUB !\ VICINITY MAP PROJECT SITE NTSDIV 5 DIV 1 DIV 2 DIV 4 DIV 3 ?ò Aä%&s ?p ?Ë F 944-1R 980-2 927-1R STAFF REPORT TYPE MEETING: Regular Board MEETING DATE: January 6, 2016 SUBMITTED BY: Michael O’Donnell Supervising Land Surveyor Brandon DiPietro Field Services Manager PROJECT: VARIOUS DIV. NO. ALL APPROVED BY: Rod Posada, Chief, Engineering German Alvarez, Assistant General Manager Mark Watton, General Manager SUBJECT: Award of As-Needed Land Surveying Services Contract to Hunsaker & Associates San Diego, Inc. for Fiscal Years 2016 through 2018 GENERAL MANAGER’S RECOMMENDATION: That the Otay Water District (District) Board of Directors (Board) award a professional As-Needed Land Surveying Services contract to Hunsaker & Associates San Diego, Inc. (Hunsaker) and to authorize the General Manager to execute an agreement with Hunsaker in an amount not-to-exceed $175,000 for a period of three (3) fiscal years, FY 2016 through FY 2018 (ending June 30, 2019). COMMITTEE ACTION: Please see Attachment A. PURPOSE: To obtain Board authorization for the General Manager to enter into a professional As-Needed Land Surveying Services agreement with Hunsaker in an amount not-to-exceed $175,000 for three (3) fiscal years, FY 2016 through FY 2018(ending June 30, 2019). 2 ANALYSIS: The District will require the services of a professional land surveying consultant on an as-needed basis for three (3) fiscal years to support the following:  District’s Capital Improvement Program (CIP)  Cadastral Base Mapping Program  Right-of-Way Management Program  USA Mark-Out Program The District has used an as-needed contract for land surveying services over the previous two (2) fiscal years to augment existing staff and for tasks that require specialty services. The annual effort of the As-Needed Land Surveying services, used to support the District’s CIP, Cadastral Base Mapping, Right-of-Way Management, and USA Mark-Out programs from October 2013 through October 2015, averaged hours that equated to less than a full-time employee (FTE) at a rate of 0.13 FTE per year. An analysis of land surveying workload for FY 2016 through FY 2018 indicates an increasing level of effort from prior years will be needed with averaged hours that equate at a rate of 0.40 FTE per year. The District’s experience has demonstrated that it is efficient and cost effective to issue an as-needed contract for land surveying services which will provide the District with the ability to obtain consulting services in a timely and cost efficient manner. In addition to land surveying services, this concept has also been used in the past for other disciplines such as engineering design, construction management, electrical, and environmental services. The District will issue task orders to the consultant for specific projects during the contract period based on a detailed scope of work. The consultant will then prepare a schedule and fee estimate for each task order assigned under the contract. Upon written task order authorization from the District, the consultant shall then proceed with the project, as described in the scope of work. This As-Needed Land Surveying Services contract does not commit the District to any expenditure until a task order is approved to perform work on a project. The District does not guarantee work to the consultant, nor does the District guarantee that it will expend all of the funds authorized by the contract on professional services. The District solicited for Land Surveying Services by placing an advertisement on the District’s website on August 27, 2015 and with various other publications including the San Diego Daily Transcript. 3 Twelve (12) firms submitted a Letter of Interest and a Statement of Qualifications. The Request for Proposal (RFP) for As-Needed Land Surveying Services was sent to the twelve (12) firms resulting in nine (9) proposals received by September 30, 2015.  Hunsaker & Associates San Diego, Inc., San Diego, CA  Project Design Consultants, San Diego, CA  D. Woolley and Associates, Tustin, CA  O’Day Consultants, Inc., San Diego, CA  San Dieguito Engineering, Inc., Encinitas, CA  Alyson Consulting, San Diego, CA  Towill, Inc., San Diego, CA  TSAC Engineering, San Diego, CA  PSOMAS, San Diego, CA The three (3) firms that chose not to propose are NV5, Calvada Surveying, Inc., and Dennis Janda, Inc. In accordance with the District’s Policy 21, staff evaluated and scored all written proposals. Hunsaker received the highest score for their services based on their experience, understanding of the scopes of work, proposed method to accomplish the work, and their composite hourly rate. Hunsaker was the most qualified consultant with the best overall rating or ranking score. A summary of the complete evaluation is shown in Attachment B. Hunsaker submitted the Company Background Questionnaire, as required by the RFP, and staff did not find any outstanding issues. In addition, staff checked their references and performed an internet search on the company. Staff found the references to be excellent and did not find any outstanding issues with the internet search. FISCAL IMPACT: Joe Beachem, Chief Financial Officer The funds for this contract will be expended from the Fiscal Years 2016, 2017, and 2018 budgets for various projects or programs. This contract is for professional as-needed land surveying consulting services based on the District's need and schedule, and expenditures will not be made until a task order is approved by the District for the consultant's services on a specific project or program. Based on a review of the financial budgets, the Project Manager anticipates that the budgets will be sufficient to support the professional as-needed land surveying consulting services required for various projects and the programs noted above. 4 The Finance Department has determined that under the current rate model, the funds to cover this contract will be available as budgeted for these projects or programs. STRATEGIC GOAL: This Project supports the District’s Mission statement, “To provide high value water and wastewater services to the customers of the Otay Water District in a professional, effective, and efficient manner” and the District’s Vision, “A District that is innovative in providing water services at affordable rates, with a reputation for outstanding customer service.” LEGAL IMPACT: None. MO:jf P:\WORKING\As Needed Services\Land Surveying\FY 2016-2018\Staff Report\Staff Report As-Needed Land Surveying Services.docx Attachments: Attachment A – Committee Action Attachment B – Summary of Proposal Rankings ATTACHMENT A SUBJECT/PROJECT: Various Award of As-Needed Land Surveying Services Contract to Hunsaker & Associates San Diego, Inc. for Fiscal Years 2016 through 2018 COMMITTEE ACTION: The Engineering, Operations, and Water Resources Committee reviewed this item at a meeting held on December 8, 2015. The Committee supported Staff’s recommendation. NOTE: The “Committee Action” is written in anticipation of the Committee moving the item forward for Board approval. This report will be sent to the Board as a Committee approved item, or modified to reflect any discussion or changes as directed from the Committee prior to presentation to the full Board. Qualifications of Team Responsiveness and Project Understanding Technical and Management Approach INDIVIDUAL SUBTOTAL - WRITTEN AVERAGE SUBTOTAL - WRITTEN Proposed Rates* Consultant's Commitment to DBE TOTAL SCORE 30 25 30 85 85 15 Y/N 100 Poor/Good/ Excellent Brandon DiPietro 27 20 21 68 Chad Thompson 26 20 25 71 Dan Martin 25 22 23 70 Jeff Marchioro 26 22 21 69 Kevin Cameron 24 20 25 69 Brandon DiPietro 30 24 28 82 Chad Thompson 29 24 28 81 Dan Martin 29 24 28 81 Jeff Marchioro 29 24 29 82 Kevin Cameron 29 24 28 81 Brandon DiPietro 28 22 26 76 Chad Thompson 28 24 27 79 Dan Martin 28 24 27 79 Jeff Marchioro 29 22 28 79 Kevin Cameron 28 23 28 79 Brandon DiPietro 29 23 27 79 Chad Thompson 28 24 28 80 Dan Martin 27 24 24 75 Jeff Marchioro 28 23 24 75 Kevin Cameron 27 22 27 76 Brandon DiPietro 28 21 24 73 Chad Thompson 27 23 26 76 Dan Martin 27 24 27 78 Jeff Marchioro 28 23 26 77 Kevin Cameron 27 22 27 76 Brandon DiPietro 27 21 24 72 Chad Thompson 26 22 24 72 Dan Martin 25 22 22 69 Jeff Marchioro 28 21 22 71 Kevin Cameron 25 23 25 73 Brandon DiPietro 26 20 22 68 Chad Thompson 26 21 24 71 Dan Martin 25 23 23 71 Jeff Marchioro 27 22 22 71 Kevin Cameron 23 20 24 67 Brandon DiPietro 26 24 26 76 Chad Thompson 27 23 24 74 Dan Martin 27 23 23 73 Jeff Marchioro 28 23 25 76 Kevin Cameron 27 22 27 76 Brandon DiPietro 26 19 22 67 Chad Thompson 25 20 23 68 Dan Martin 24 23 24 71 Jeff Marchioro 26 22 21 69 Kevin Cameron 24 21 23 68 Rate Score 1 $1,387 8 2 $1,020 15 3 $1,365 8 4 $1,714 1 5 $1,420 7 6 $1,317 9 7 $1,626 3 8 $1,190 12 9 $1,675 2 *The fees were evaluated by comparing rates for nine (9) positions. The sum of these rates are noted in the above table. Note: Review Panel does not see or consider rates when scoring other categories. Rates are scored by the PM, who is not on Review Panel. Towill TSAC Engineering O'Day Consultants Alyson Consulting SDE, Inc Consultant D.Woolley and Associates, Inc. Hunsaker & Associates San Diego, Inc. Project Design Consultants Psomas ATTACHMENT BSUMMARY OF PROPOSAL RANKINGS As-Needed Land Surveying Services 9 SDE, Inc. 69 2 Y 71 8 Alyson Consulting 75 12 Y 87 7 O'Day Consultants 70 3 Y 73 6 TSAC Engineering 71 9 Y 80 5 Towill 76 7 Y 83 4 Psomas 77 1 Y 78 Excellent 3 Project Design Consultants 78 8 Y 86 Y77 2 Hunsaker & Associates San Diego, Inc. 81 15 Y 96 RATES SCORING CHART WRITTEN REFERENCES MAXIMUM POINTS 1 D.Woolley and Associates, Inc.69 8 P:\WORKING\As Needed Services\Land Surveying\FY 2016-2018\Staff Report\Attachment B - Summary of Proposal Rankings.xls STAFF REPORT TYPE MEETING: Regular Board MEETING DATE: January 6, 2016 SUBMITTED BY: Dan Martin Engineering Manager PROJECT: VARIOUS DIV. NO. ALL APPROVED BY: Rod Posada, Chief of Engineering German Alvarez, Assistant General Manager Mark Watton, General Manager SUBJECT: Informational Item – First Quarter Fiscal Year 2016 Capital Improvement Program Report GENERAL MANAGER’S RECOMMENDATION: No recommendation. This is an informational item only. COMMITTEE ACTION: Please see Attachment A. PURPOSE: To update the Board about the status of all CIP project expenditures and to highlight significant issues, progress, and milestones on major projects. ANALYSIS: To keep up with growth and to meet our ratepayers' expectations to adequately deliver safe, reliable, cost-effective, and quality water, each year the District staff prepares a Six-Year CIP Plan that identifies the District’s infrastructure needs. The CIP is comprised of four categories consisting of backbone capital facilities, replacement/renewal projects, capital purchases, and developer's reimbursement projects. The First Quarter Fiscal Year 2016 update is intended to provide a detailed analysis of progress in completing these projects within the allotted time and budget of $11.4 million. Expenditures through the First Quarter totaled approximately $2.1 million. Approximately 18% of the Fiscal Year 2016 expenditure budget was spent (see Attachment B). FISCAL IMPACT: Joe Beachem, Chief Financial Officer No fiscal impact as this is an informational item only. STRATEGIC GOAL: The Capital Improvement Program supports the District’s Mission statement, “To provide high value water and wastewater services to the customers of the Otay Water District, in a professional, effective, and efficient manner” and the General Manager’s Vision, “A District that is at the forefront in innovations to provide water services at affordable rates, with a reputation for outstanding customer service.” LEGAL IMPACT: None. DM/RP: P:\Forms\D-Construction\CIP Quarterly Reports\CIP Qtr Reports\FY 2016\Q1\Staff Report\BD 12-02-15, Staff Report, First Quarter FY 2016 CIP Report, (DM-RP).docx Attachments: Attachment A – Committee Action Attachment B - Fiscal Year 2016 First Quarter CIP Expenditure Report Attachment C – Presentation ATTACHMENT A SUBJECT/PROJECT: VARIOUS Informational Item – First Quarter Fiscal Year 2016 Capital Improvement Program Report COMMITTEE ACTION: The Engineering, Operations, and Water Resources Committee (Committee) reviewed this item at a Committee Meeting held on December 8, 2015. The Committee supported Staff’s recommendation. NOTE: The “Committee Action” is written in anticipation of the Committee moving the item forward for Board approval. This report will be sent to the Board as a Committee approved item, or modified to reflect any discussion or changes as directed from the Committee prior to presentation to the full Board. FISCAL YEAR 2016 FIRST QUARTER REPORT (Expenditures through 09/30/2015) ($000) Attachment B 2016 09/30/15 CIP No.Description Project Manager FY 2016 Budget Expenses Balance Expense to Budget %Budget Expenses Balance Expense to Budget %Comments CAPITAL FACILITY PROJECTS - P2040 Res - 1655-1 Reservoir 0.5 MG Cameron 25$ -$ 25$ 0%2,200$ 478$ 1,722$ 22%Planning for this project has just begun.1 P2083 PS - 870-2 Pump Station Replacement Marchioro 350 50 300 14%15,000 1,370 13,630 9% On target. Q1 expense slower compared to Q2 through Q4 since consultant (Carollo) amendment processed during Q1. P2267 36-Inch Main Pumpouts and Air/Vacuum Ventilation Installations Marchioro 50 11 39 22%735 421 314 57%On target. P2325 PL-10" to 12" Oversize, 1296 Zone, PB Road-Rolling Hills Hydro PS/PB Bndy Beppler 1 1 - 100%22 1 21 5% Developer reimbursement request associated with this project under review in Q1. P2451 Otay Mesa Desalination Conveyance and Disinfection System Posada 350 105 245 30%30,000 3,364 26,636 11% Expect to spend 75% of Fiscal Year budget or $265,000 total for the Fiscal Year. P2466 Regional Training Facility Coburn-Boyd 8 1 7 13%300 288 12 96%On track. P2469 Information Technology Network and Hardware Kerr 175 - 175 0%1,684 1,887 (203) 112% For this Fiscal Year, $174,800 will be spent, then the CIP will be closed.1 P2470 Financial System Enhancements Kerr 100 26 74 26%1,765 1,693 72 96% Purchased software for Customer Service and anticipate spending $25K-$30K for Eden Payroll and Self-Service Module later this Fiscal Year. P2486 Asset Management Plan Condition Assessment and Data Acquisition Zhao 75 - 75 0%1,015 859 156 85%The hiring of a consultant has been put on hold. P2511 Otay Interconnect Pipeline Marchioro 50 413 (363) 826%2,601 2,498 103 96% FY 2016 expense currently projected at $420K rather than $50K. Purchase of Caltrans parcels was on hold during FY 2016 budget development cycle. P2537 Operations Yard Property Acquisition Improvements Beppler 450 25 425 6%775 191 584 25% Construction is expected to be completed this Fiscal Year and is estimated at $500K. P2540 Work Order Management System Replacement Kerr 60 146 (86) 243%500 443 57 89% Payment for work scheduled for Q4 FY 2015 held until Contractor completed delivery of system in Q1 of FY 2016. Overall project is within budget. P2541 624 Pressure Zone PRSs Marchioro 525 9 516 2%750 234 516 31% On target. Q1 expense slower compared to Q2 through Q4 since contractor (CCL) has not yet broken ground. Linked to R2108. P2547 District Administration Vehicle Charging Stations Beppler 1 - 1 0%60 11 49 18%Little activity expected this Fiscal Year. P2549 Fuel System Upgrade Payne 30 - 30 0%30 - 30 0%To be completed in the 3rd QTR. P2551 Blossom Lane Helix WD and Otay WD Interconnection Beppler 150 2 148 1%193 10 183 5% Construction completion anticipated in early 2016. Invoices from HWD may total $170K. P2552 South Barcelona Helix WD and Otay WD Interconnection Beppler 150 2 148 1%200 10 190 5% Construction completion anticipated in early 2016. Invoices from HWD may total $170K. P2554 640/340 PRS at Energy Way and Nirvana Avenue Marchioro 1 - 1 0%400 - 400 0%No progress anticipated in FY 2016. P2555 Administration and Operations Parking Lot Improvements Cameron 10 8 2 80%500 8 492 2%Project has been accelerated. P2561 Res - 711-3 Reservoir Cover/Liner Replacement Marchioro 5 - 5 0%1,800 - 1,800 0%No progress anticipated in FY 2016. P2562 Res - 571-1 Reservoir Cover/Liner Replacement Marchioro 1 - 1 0%2,600 - 2,600 0%No progress anticipated in FY 2016. P2563 Res - 870-1 Reservoir Cover/Liner Replacement Marchioro 1 - 1 0%1,000 - 1,000 0%No progress anticipated in FY 2016. P2568 Technology Business Processes Improvement Kerr 40 25 15 63%115 25 90 22% Anticipate spending another $10K-$20K for solutions for business process improvements. P2569 Metro Ethernet Implementation/ District Facilities - Pilot Kerr 100 - 100 0%100 - 100 0%This project will commence in the 3rd QTR. P2570 SCADA Equipment & Infrastructure Enhancement Kerr - - - 0%300 - 300 0%No expenditures anticipated in FY 2016. P2571 Datacenter Network Enhancement & Replacement of Infrastructure Componets Kerr - - - 0%200 - 200 0%No expenditures anticipated in FY 2016. P2572 Enterprise Resource Planning (ERP) Replacement Kerr - - - 0%250 - 250 0%No expenditures anticipated in FY 2016. R2077 RecPL - 24-Inch, 860 Zone, Alta Road - Alta Gate/Airway Beppler 5 - 5 0%2,850 2,810 40 99%Little activity scheduled this Fiscal Year. R2107 RWCWRF Screening Compactor and Chlorine Injectors Enclosure Vaclavek 7 3 4 43%215 180 35 84% No further expenses projected for FY 2016. Project is complete. R2108 Res - 927-1 Reservoir Cover Replacement Marchioro 10 - 10 0%1,090 1,082 8 99% On target. Final warranty inspection scheduled for 3rd QTR. R2110 RecPS - 944-1 Optimization and Pressure Zone Modifications Marchioro 25 4 21 16%200 88 112 44% FY 2016 expense currently projected at $45K rather than $25K. Linked to P2541. R2114 Large Recycle Pump Replacement at the RWCWRF 927-1 Pump Station Anderson 40 - 40 0%120 89 31 74%No additional funds will be spent this Fiscal Year. R2117 RWCWRF Disinfection System Improvements Beppler 110 5 105 5%2,500 109 2,391 4% Waiting on results of IPR/DPR study on plant before making a decision on next step. Do not expect to spend the full Fiscal Year budget. FISCAL YEAR-TO-DATE, 09/30/15 LIFE-TO-DATE, 09/30/15 Page 1 of 3 FISCAL YEAR 2016 FIRST QUARTER REPORT (Expenditures through 09/30/2015) ($000) Attachment B 2016 09/30/15 CIP No.Description Project Manager FY 2016 Budget Expenses Balance Expense to Budget %Budget Expenses Balance Expense to Budget %Comments FISCAL YEAR-TO-DATE, 09/30/15 LIFE-TO-DATE, 09/30/15 R2118 Steele Canyon Sewer PS Chopper Pump Beppler 40 - 40 0%40 - 40 0%Engineering/OPS working on pump selection. R2119 Treatment Plant Automation & Security Upgrades Beppler 50 - 50 0%200 - 200 0%No activity to date; budget still adequate. R2121 Res - 944-1 Reservoir Cover/Liner Replacement Marchioro 25 13 12 52%1,400 13 1,387 1%On target. R2122 Emergency Recycled Water Fire Hydrant Installations Cameron 75 11 64 15%75 11 64 15% Project is on schedule; gathering Agency requirements. S2043 RWCWRF Sludge Handling System Beppler 1 - 1 0%47 40 7 85%Little activity scheduled this Fiscal Year. Total Capital Facility Projects Total:3,096 860 2,236 28%73,832 18,213 55,619 25% REPLACEMENT/RENEWAL PROJECTS P2382 Safety and Security Improvements Ramirez 300 63 237 21%2,667 2,321 346 87% $63K in District-wide system upgrades were completed by the end of Q1 FY 2016. Project phases will continue into FY 2016. It is anticipated that the remaining balance of $237K will be expensed in phase projects during the remainder of FY 2016. P2453 SR-11 Utility Relocations Marchioro 5 97 (92) 1940%2,250 1,515 735 67% FY 2016 expense projected at $180K, rather than $5K. Construction contract not completed in FY 2015 as anticipated. Overall project within budget. P2485 SCADA Communication System and Software Replacement Segura 75 45 30 60%2,014 1,455 559 72% This project is on target. Estimated to expend 100% of the budgeted CIP. P2493 624-2 Reservoir Interior/Exterior Coating Cameron 55 2 53 4%1,675 1,538 137 92% Project is in the warranty period; expenditures planned for the 4th QTR. P2494 Multiple Species Conservation Plan Coburn-Boyd 87 2 85 2%950 848 102 89% Rate of contract completion estimated to increase in Q2, Q3, and Q4. P2495 San Miguel Habitat Management/Mitigation Area Coburn-Boyd 120 16 104 13%2,100 1,156 944 55%On track. P2496 Otay Lakes Road Utility Relocations Martin 20 - 20 0%325 282 43 87%Final punch list items pending from City. P2504 Regulatory Site Access Road and Pipeline Relocation Cameron 50 - 50 0%900 329 571 37%Project is driven by County Fire. P2507 East Palomar Street Utility Relocation Cameron 25 10 15 40%940 704 236 75%Project is complete; processing reimbursement. P2508 Pipeline Cathodic Protection Replacement Program Marchioro 150 4 146 3%725 188 537 26% Pace anticipated to accelerate during Q2 through Q3. P2515 870-1 Reservoir Paving Beppler 15 4 11 27%510 509 1 100% Project construction complete. Project was accepted on February 11, 2015 and has a one year warranty. P2518 803-3 Reservoir Interior/Exterior Coating Cameron 20 - 20 0%700 638 62 91% Project is in the warranty period, expenditures planned for the 3rd QTR. P2519 832-2 Reservoir Interior/Exterior Coating Cameron 20 1 19 5%750 663 87 88% Project is in the warranty period, expenditures planned for the 3rd QTR. P2520 Motorola Mobile Radio Upgrade Martinez 30 - 30 0%135 77 58 57%Anticipate spending in the 3rd QTR. P2529 711-2 Reservoir Interior & Exterior Coating Cameron 600 20 580 3%790 35 755 4% Project is on schedule, construction to begin in the 2nd QTR. P2530 711-1 Reservoir Interior & Exterior Coating Cameron 800 21 779 3%1,040 37 1,003 4% Project is on schedule, construction to begin in the 2nd QTR. P2531 944-1 Reservoir Interior & Exterior Coating Cameron 205 79 126 39%390 90 300 23% Project is behind schedule. Contractor is being assessed liquidated damages. P2532 944-2 Reservoir Interior & Exterior Coating Cameron 101 48 53 48%946 935 11 99% Reservoir in service. Contractor to complete punch list items; associated with P2531. P2533 1200-1 Reservoir Interior & Exterior Coating Cameron 5 - 5 0%565 - 565 0% Project is on schedule, expenditures planned for the 4th QTR. P2534 978-1 Reservoir Interior & Exterior Coating Cameron - - - 0%325 - 325 0%No expenditures for FY 2016. P2535 458-2 Reservoir Interior & Exterior Coating & Upgrades Cameron 294 205 89 70%839 579 260 69% Project is behind schedule. Contractor is being assessed liquidated damages. P2538 Administration and Operations Building Fire Sprinkler Replacement Program Cameron 5 1 4 20%110 65 45 59%Project is on schedule. P2539 South Bay Bus Rapid Transit (BRT) Utility Relocations Cameron 100 5 95 5%940 835 105 89%SANDAG driven project. P2542 850-3 Reservoir Interior Coating Cameron 230 240 (10) 104%530 385 145 73% Construction contract acceptance anticipated in Q2. P2543 850-1 Reservoir Interior/Exterior Coating Cameron - - - 0%575 - 575 0%No expenditures for FY 2016. Page 2 of 3 FISCAL YEAR 2016 FIRST QUARTER REPORT (Expenditures through 09/30/2015) ($000) Attachment B 2016 09/30/15 CIP No.Description Project Manager FY 2016 Budget Expenses Balance Expense to Budget %Budget Expenses Balance Expense to Budget %Comments FISCAL YEAR-TO-DATE, 09/30/15 LIFE-TO-DATE, 09/30/15 P2544 850-2 Reservoir Interior/Exterior Reservoir Coating Cameron 5 - 5 0%940 - 940 0% Project is on schedule, expenditures planned for the 4th QTR. P2545 980-1 Reservoir Interior Exterior Coating Cameron 950 9 941 1%1,495 9 1,486 1% Project is on schedule. Construction to begin in the 3rd QTR. P2546 980-2 Reservoir Interior/Exterior Coating Cameron - - - 0%1,450 - 1,450 0%No expenditures for FY 2016. P2550 Fuel Island Upgrade Payne 75 - 75 0%75 - 75 0%To be completed in the 3rd QTR. P2553 Heritage Road Bridge Replacement and Utility Relocation Cameron 10 - 10 0%1,200 - 1,200 0%City of Chula Vista driven project. P2557 520 Res Recirculation Pipeline Chemical Supply and Analyzer Feed Replacement Project Beppler 1 - 1 0%100 - 100 0%Little activity scheduled this Fiscal Year. P2558 Additional Pump Station Fuel Storage Rahders 25 - 25 0%25 - 25 0%Will be expensed by end of 3rd QTR. P2559 Pressure Vessel Repair and Replacement Program Marchioro 50 15 35 30%300 15 285 5%On target. P2564 Administration Carpet Replacement Program Payne 65 - 65 0%215 - 215 0%To be completed in the 3rd QTR. P2565 803-2 Reservoir Interior/Exterior Coating & Upgrades Cameron - - - 0%725 - 725 0%No expenditures for FY 2016. P2566 520-2 Reservoir Interior/Exterior Coating & Upgrades Cameron - - - 0%1,790 - 1,790 0%No expenditures for FY 2016. P2567 1004-2 Reservoir Interior/Exterior Coating & Upgrades Cameron - - - 0%565 - 565 0%No expenditures for FY 2016. R2109 Sweetwater River Wooden Trestle Improvement for the Recycled Water Forcemain Beppler 400 15 385 4%516 135 381 26% Construction to begin in Q2. Construction completion anticipated in Q4 of FY 2016. R2111 RWCWRF - RAS Pump Replacement Beppler 250 23 227 9%600 173 427 29% Construction completion anticipated in Q2 of FY 2016. Projected to exceed FY 2016 budget, but not total project budget. R2112 450-1 Disinfection Facility Rehabilitation Cameron 40 56 (16) 140%265 207 58 78%Project is in the Warranty period. R2116 RecPL - 14-Inch, 927 Zone, Forcemain Assessment and Repair Marchioro 225 39 186 17%1,750 405 1,345 23%On target. R2120 RWCWRF Filtered Water Storage Tank Improvements Beppler 10 - 10 0%500 - 500 0% No activity to date; budget appears to be adequate. S2012 San Diego County Sanitation District Outfall and RSD Outfall Replacement Beppler 50 - 50 0%1,935 1,020 915 53% District will receive invoice from the County late in the 4th QTR. S2024 Campo Road Sewer Main Replacement Beppler 500 172 328 34%5,500 776 4,724 14% Completion of design services expected this Fiscal Year. Estimated costs are within budget. S2027 Rancho San Diego Pump Station Rehabilitation Beppler 320 5 315 2%3,500 78 3,422 2% Project design is complete. Expect to see invoices for design only from County this Fiscal Year. S2033 Sewer System Rehabilitation Beppler 900 58 842 6%6,000 1,629 4,371 27% Rancho San Diego-Phase 1 project is out for bids in Q1. Construction scheduled for Q3 and Q4. Expect to spend allocated budget. Total Replacement/Renewal Projects Total:7,188 1,255 5,933 17%53,137 19,631 33,506 37% CAPITAL PURCHASE PROJECTS P2282 Vehicle Capital Purchases Rahders 556 - 556 0%5,191 3,105 2,086 60% $405K encumbered which will be expensed in 3rd QTR. $151K will be expensed by end of 4th QTR. P2285 Office Equipment and Furniture Capital Purchases Payne 15 - 15 0%589 536 53 91%To be completed by the end of the 4th QTR. P2286 Field Equipment Capital Purchases Rahders 50 - 50 0%1,808 1,303 505 72%Will be expensed by end of 3rd QTR. P2366 APCD Engine Replacements and Retrofits Rahders 535 - 535 0%3,835 2,535 1,300 66% Anticipate a 10% savings. CP 22 will be purchased in 2nd QTR; CP17 will be purchased during the 4th QTR. - Total Capital Purchase Projects Total:1,156 - 1,156 0%11,423 7,479 3,944 65% DEVELOPER REIMBURSEMENT PROJECTS P2556 HWY 94 Upsized Utility Relocations at Melody Lane Beppler 1 - 1 0%250 - 250 0%Little activity scheduled this Fiscal Year. Total Developer Reimbursement Projects Total:1 - 1 0%250 - 250 0% 89 GRAND TOTAL 11,441$ 2,115$ 9,326$ 18%138,642$ 45,323$ 93,319$ 33% Page 3 of 3 Otay Water District Capital Improvement Program Fiscal Year 2016 First Quarter (through September 30, 2015) Attachment C 850-3 (3.0 MG) New Center Support Structure 08/29/15 Background The approved CIP Budget for Fiscal Year 2016 consists of 80 projects that total $11.4 million. These projects are broken down into four categories. 1.Capital Facilities $ 3.1 million 2.Replacement/Renewal $ 7.2 million 3.Capital Purchases $ 1.1 million 4.Developer Reimbursement $ 1.0 thousand Overall expenditures through the First Quarter of Fiscal Year 2016 totaled $2.1 million, which is approximately 18% of the Fiscal Year budget. 2 Fiscal Year 2016 First Quarter Update ($1,000) CIP CAT Description FY 2016 Budget FY 2016 Expenditures % FY 2016 Budget Spent Total Life-to- Date Budget Total Life-to-Date Expenditures % Life-to- Date Budget Spent 1 Capital Facilities $3,096 $860 28%$73,832 $18,213 25% 2 Replacement/ Renewal $7,188 $1,255 17%$53,137 $19,631 37% 3 Capital Purchases $1,156 $0 0%$11,423 $7,479 65% 4 Developer Reimbursement $1 $0 0%$250 $0 0% Total: $11,441 $2,115 18%$138,642 $45,323 33% 3 Fiscal Year 2016 First Quarter CIP Budget Forecast vs. Expenditures 4 $11,441,000 $2,115,000 $- $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000 $14,000,000 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun FISCAL YEAR PERIOD IN MONTHS Budget Forecast Total Expenditures District Map of Major CIP Projects 5 CIP Projects in Construction 850-3 Reservoir Interior Coating & Upgrades (P2542) Remove and Replace Deteriorating Reservoir Coatings. Structural Modifications to Increase Service Life. $0.53M Budget Start: May 2015 Estimated Completion: November 2015 6 850-3 (3.0 MG) Completed Interior Coating 850-3 (3.0 MG) Door Sheet Installation 09/27/15 09/05/15 CIP Projects in Construction 944-1, 944-2, & 458-2 Reservoir Interior/Exterior Coating & Upgrades (P2531, P2532, P2535) Remove and Replace Deteriorating Reservoir Coatings. Structural Modifications to Increase Service Life. $2.18M Budget Start: November 2014 Estimated Completion: December 2015 7 458-2 (1.75 MG) Blasting Roof In Containment 944-1 (0.3 MG) Interior Reservoir Blasting Progress 06/29/1509/14/15 09/28/15 CIP Projects in Construction RWCWRF –Return Activated Sludge (RAS) Pump Replacement (R2111) Replace 3 RAS Pumps, motors, variable frequency drives, and associated electrical and piping work. $0.60M Budget Start: February 2015 Estimated Completion: December 2015 8 RAS Pumps Waste Piping Modifications Pre-Installation Pipe Coating Progress 09/01/15 09/01/15 CIP Projects in Construction SR-11 Utility Relocations Sequence I (P2453) Relocate Existing Water Facilities to support SR-11 Construction. $2.25M Budget Start: February 2014 Estimated Completion: November 2015 9 SR-11 Connection Work for 18-inch Waterline 09/02/15 Construction Contract Status PROJECT TOTAL % P2453- 002103 SR-11 Potable Water Utility Relocations - Sequence 1 Coffman Specialties, Inc.$947,380 $992,380 $39,480 4.2%$986,860 $949,703 -0.6%96.2%November 2015 P2531 P2532 P2535 944-1, 944-2, & 458- 2 Reservoirs Interior/Exterior Coating & Upgrades Olympus and Associates Inc.$1,146,008 $1,206,008 $90,309 7.9%$1,296,317 $1,008,733 7.5%77.8%December 2015 R2111 RWCWRF RAS Pumps Replacement Cora Constructors Inc. $295,315 $315,315 $0 0.0%$295,315 $113,965 -6.3%38.6%December 2015 R2112 450-1 Disinfection Facility Rehabilitation Fordyce Construction, Inc. $108,350 $128,350 ($360)-0.3%$107,990 $107,990 -15.9%100.0% Completed August 2015 S2033 Calavo Basin Sewer Rehabilitation Phase 1 Arrieta Construction Inc. $521,890 $529,490 ($34,531)-6.6%$494,959 $494,959 -6.5%100.0% Completed August 2015 P2542 850-3 Reservoir Interior Coating Abhe & Svoboda Inc.$336,720 $366,720 $25,410 7.5%$392,130 $261,836 6.9%66.8%November 2015 R2109 Sweetwater River Trestle Improvements Fordyce Construction, Inc. $153,740 $173,740 $0 0.0%$153,740 $0 -11.5%0.0%March 2016 P2541 R2110 624 Zone PRSs & 944-R PRS Improvements CCL Contracting Inc.$445,209 $455,209 $0 0.0%$445,209 $0 -2.2%0.0%March 2016 TOTALS:$3,954,612 $4,167,212 $120,309 3.0%$4,172,521 $2,937,186 0.1% FY 2016 CIP CONSTRUCTION PROJECTS CURRENT CONTRACT AMOUNT TOTAL EARNED TO DATE **THIS CHANGE ORDER RATE INCLUDES THE CREDIT FOR UNUSED ALLOWANCES *NET CHANGE ORDERS DO NOT INCLUDE ALLOWANCE ITEM CREDITS. IT'S A TRUE CHANGE ORDER PERCENTAGE FOR THE PROJECT CIP NO.PROJECT TITLE CONTRACTOR BASE BID AMOUNT CONTRACT AMOUNT W/ ALLOWANCES % CHANGE ORDERS W/ ALLOWANCE CREDIT** % COMPLETE EST. COMP. DATE NET CHANGE ORDERS LTD* Consultant Contract Status 11 Consultant CIP No.Project Title Original Contract Amount Total Change Orders Revised Contract Amount Approved Payment To Date % Change Orders % Project Complete Date of Signed Contract End Date of Contract PLANNING ATKINS Varies 2015 WATER FACILITIES MASTER PLAN UPDATE $ 434,731.00 $ - $ 434,731.00 $ 271,627.23 0.0%62.5%1/28/2014 12/31/2016 CAROLLO ENGINEERS, INC.VARIES 2015 INTEGRATED WATER RESOURCES PLAN UPDATE $ 99,993.00 $ 6,300.00 $ 106,293.00 $ 42,778.87 6.3%40.2%11/17/2014 6/30/2016 CH2M HILL ENGINNERS INC Varies 2015 URBAN WATER MANAGEMENT PLAN UPDATE $ 49,839.00 $ 49,839.00 $ - 0.0%0.0%9/10/2015 6/30/2018 WATER SYSTEMS CONSULTING INC VARIES AS-NEEDED HYDRAULIC MODELING FY15/16 $ 175,000.00 $ - $ 175,000.00 $ 51,439.00 0.0%29.4%7/15/2014 6/30/2016 DESIGN AECOM P2451 OTAY MESA CONVEYANCE AND DISINFECTION SYSTEM (DESIGN ENGINEER) $ 3,910,297.00 $(131,859.00) $ 3,778,438.00 $1,254,374.24 -3.4%33.2%1/6/2011 6/30/2018 ARCADIS U.S., INC. P2434, P2511 VALUE ENGINEERING AND CONSTRUCTIBILITY REVIEW $ 153,628.00 $ - $ 153,628.00 $ 70,208.73 0.0%45.7%1/24/2012 6/30/2016 ARCADIS U.S. INC VARIES AS-NEEDED DESIGN FY 15-16 $ 300,000.00 $ - $ 300,000.00 $ 138,182.90 0.0%46.1%9/11/2014 6/30/2016 ATKINS Varies AS-NEEDED ENGINEERING DESIGN SERVICES FY12-13 $ 175,000.00 $ - $ 175,000.00 $ 157,396.56 0.0%89.9%10/26/2011 6/30/2016 BROWNSTEIN HYATT FARBER SCHRECK P2451 OTAY MESA CONVEYANCE AND DISINFECTION SYSTEM (BINATIONAL WATER AND RELATED ISSUES) $ 100,000.00 $ - $ 100,000.00 $ 3,240.69 0.0%3.2%7/1/2015 6/30/2017 BSE ENGINEERING INC Varies AS-NEEDED ELECTRICAL SERVICES $ 100,000.00 $ - $ 100,000.00 $ 29,859.62 0.0%29.9%7/1/2012 6/30/2016 CAROLLO ENGINEERS INC P2083 DESIGN/CONSTRUCTION FOR 870-2 PS $ 624,910.00 $ 29,000.00 $ 653,910.00 $ 346,101.40 4.6%52.9%10/11/2013 12/31/2017 HDR ENGINEERING INC Varies CORROSION SERVICES FY14-FY16 $ 684,750.00 $ 45,000.00 $ 729,750.00 $ 597,283.01 6.6%81.8%11/22/2013 12/31/2015 LEE & RO INC P2511 OTAY INTERCONNECT PIPELINE $ 2,769,119.00 $ - $ 2,769,119.00 $1,111,674.73 0.0%40.1%11/4/2010 12/31/2015 MICHAEL D.KEAGY REAL ESTATE Varies AS-NEEDED APPRAISAL SERVICES FY13-14 $ 45,000.00 $ - $ 45,000.00 $ 39,500.00 0.0%87.8%9/17/2012 6/30/2016 Consultant Contract Status 12 NINYO & MOORE Varies GEOTECHNICAL SERVICES $ 175,000.00 $ - $ 175,000.00 $ 37,595.00 0.0%21.5%4/9/2015 6/30/2018 PIPELINE INSPECTION & CONDITION ANALYSIS CORPORATION R2116 INSPECTION AND CONDITION ASSESSMENT OF THE RALPH W. CHAPMAN WATER RECYCLING FACILITY 14-INCH FORCE MAIN $ 302,092.00 $ - $ 302,092.00 $ 87,500.00 0.0%29.0%12/18/2014 4/30/2016 PSOMAS VARIES AS-NEEDED DESIGN FY 15-16 $ 300,000.00 $ - $ 300,000.00 $ 20,472.63 0.0%6.8%9/11/2014 6/30/2016 RFYEAGER Varies AS-NEEDED CORROSION ENGINEERING AND RESERVOIR COATING INSPECTION $ 175,000.00 $ - $ 175,000.00 $ 86,604.00 0.0%49.5%2/9/2015 12/31/2016 RICK ENGINEERING COMPANY S2024 CAMPO ROAD SEWER MAIN REPLACEMENT PROJECT $ 805,705.00 $ - $ 805,705.00 $ 462,731.07 0.0%57.4%5/27/2014 12/31/2017 RICK ENGINEERING COMPANY Varies TRAFFIC ENGINEERING SERVICES FY 16-18 $ 175,000.00 $ - $ 175,000.00 $ 4,838.00 0.0%2.8%7/1/2015 6/30/2018 SILVA SILVA CONSULTING P2451 OTAY MESA CONVEYANCE AND DISINFECTION SYSTEM (BINATIONAL WATER AND RELATED ISSUES) $ 115,000.00 $ - $ 115,000.00 $ 60,289.05 0.0%52.4%5/1/2014 6/30/2016 CONSTRUCTION SERVICES AIRX UTILITY SURVEYORS Varies AS-NEEDED SURVEYING SERVICES FY 14-15 $ 175,000.00 $ 45,000.00 $ 220,000.00 $ 191,519.25 25.7%87.1%9/18/2013 6/30/2016 AIRX UTILITY SURVEYORS Varies UTILITY LOCATING SERVICES FY 16-18 $ 350,000.00 $ 350,000.00 $ - 0.0%0.0%10/12/2015 6/30/2018 ALYSON CONSULTING Varies CONSTRUCTION MGMT/INSPECTION FY 13-15 $ 350,000.00 $ 35,000.00 $ 385,000.00 $ 365,213.75 10.0%94.9%10/24/2012 12/31/2015 ALYSON CONSULTING Varies CONSTRUCTION MGMT/INSPECTION FY 16-17 $ 350,000.00 $ - $ 350,000.00 $ 6,120.00 0.0%1.7%7/1/2015 6/30/2017 MICHAEL BAKER INT'L INC P2083 870-2 PS CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES $ 853,457.00 $ - $ 853,457.00 $ 27,220.50 0.0%3.2%7/30/2014 12/31/2017 Consultant CIP No.Project Title Original Contract Amount Total Change Orders Revised Contract Amount Approved Payment To Date % Change Orders % Project Complete Date of Signed Contract End Date of Contract Consultant Contract Status 13 Consultant CIP No.Project Title Original Contract Amount Total Change Orders Revised Contract Amount Approved Payment To Date % Change Orders % Project Complete Date of Signed Contract End Date of Contract ENVIRONMENTAL HELIX ENVIRONMENTAL VARIES MAINTENANCE AND MONITORING OF THE SAN MIGUEL HABITAT MANAGEMENT AREA AND CIP ASSOCIATED MITIGATION PROJECTS $ 476,173.00 $ - $ 476,173.00 $ 97,821.99 0.0%20.5%12/19/2014 12/31/2017 ICF INTERNATIONAL JONES & STOKES INC VARIES AS-NEEDED ENVIRONMENTAL SERVICES FY 15/16/17 $ 375,000.00 $ - $ 375,000.00 $ 100,549.92 0.0%26.8%7/18/2014 6/30/2017 RECON P2494 PREPARATION OF THE SUBAREA PLAN $ 270,853.00 $ - $ 270,853.00 $ 220,133.36 0.0%81.3%3/28/2008 6/30/2018 WATER RESOURCES MICHAEL R. WELCH Varies ENGINEERING PLANNING SVCS. $ 100,000.00 $ - $ 100,000.00 $ 9,750.00 0.0%9.8%4/9/2014 6/30/2019 PUBLIC SERVICES AEGIS Varies AS-NEEDED DEVELOPER PROJECTS FY 15-16 $ 400,000.00 $ - $ 400,000.00 $ 71,174.56 0.0%17.8%2/12/2015 6/30/2017 TOTALS: $15,370,547.00 $ 28,441.00 $15,398,988.00 $5,963,200.06 0.2% QUESTIONS? 14